Case Law
Subject : Regulatory Law - Electricity Law
New Delhi:
The Central Electricity Regulatory Commission (CERC), in a significant order dated June 25, 2025, has directed
The bench, comprising Chairperson Jishnu Barua and Members Ramesh Babu V. and Harish Dudani, allowed DBPL's claims for additional costs related to Station Heat Rate (SHR), consequential tax increases, and carrying cost, while partially disallowing its claim on Development Surcharge.
The dispute originates from a petition filed by DB Power Ltd. in 2017, seeking compensation under its PPAs dated November 1, 2013, with PTC India Ltd., which had a back-to-back agreement with
In its initial order dated December 19, 2017, the CERC had allowed some claims (like increase in Royalty, Forest Transit Fee, and Clean Energy Cess) but disallowed others, including claims related to Station Heat Rate (SHR) and carrying cost. Both DBPL and the
In a crucial judgment on July 25, 2023, the APTEL set aside the CERC's 2017 order and remanded the matter for fresh consideration on four key issues: 1. Compensation based on actual Station Heat Rate. 2. Admissibility of Carrying Cost. 3. The impact of increased levies (like NMET, DMF) on VAT and Entry Tax. 4. The claim for Development Surcharge on coal.
DB Power Ltd. (Petitioner): -
Station Heat Rate (SHR): Argued for compensation based on the actual SHR, subject to normative ceilings in CERC regulations, rather than the lower, indicative rate of 2250 kCal/kWh used in the original order. They calculated a shortfall of over ₹40 crore. -
Development Surcharge: Claimed it as a 'Change in Law' event, citing Supreme Court precedent. -
Consequential Taxes: Contended that while the rates of VAT/Entry Tax were unchanged, the tax base expanded due to new levies like NMET and DMF (which were already recognized as 'Change in Law'), leading to higher tax outgo. -
Carrying Cost: Insisted on carrying cost at the Late Payment Surcharge (LPS) rate stipulated in the PPA, to be fully restituted for the delay in receiving compensation.
Station Heat Rate (SHR): Initially contested the SHR calculations, demanding rated Design Heat Rate data, but did not dispute the final computation submitted by DBPL. -
Carrying Cost: Argued against allowing carrying cost, stating the PPA had no specific restitution clause. If allowed, it should be limited to the interest on working capital and not granted for the period of litigation delay caused by the petitioner. -
Other Claims: Urged the Commission to subject all claims to a fresh prudence check.
The CERC meticulously analyzed each claim on remand, guided by the principles of restitution and recent judicial precedents.
The Commission accepted DBPL's methodology of calculating compensation using the lower of actual SHR or normative SHR, and the lower of actual or normative Auxiliary Power Consumption. It noted that the respondents did not contest the final revised calculation of ₹40,17,79,869 submitted by DBPL.
"As the Respondents have not contested the claim or the methodology adopted by the Petitioner, the claim is found to be admissible. As far as the compensation amount is concerned, the Petitioner and the Respondent may carry out reconciliation, if any, based on the additional coal quantum."
The CERC agreed with the petitioner that an increase in the tax base due to other 'Change in Law' events warrants compensation for the resulting higher tax payments.
"In line with the aforesaid findings, the Petitioner in this case too shall be eligible to recover the additional expenditure incurred towards the consequential increase in VAT, Entry Tax, and
Niryatkar on account of increase in the underlying taxes and duties on which the VAT, Entry Tax, andNiryatkar are computed provided these taxes and duties are also recognized as Change in Law."
The Commission recognized that the levy of Development Surcharge is a 'Change in Law' event. However, it rejected DBPL's claim for compensation based on an increase in the Busy Season Surcharge, as the latter had not been allowed as a 'Change in Law' event in the original order and was not appealed. Conversely, it directed DBPL to pass on the benefit of the withdrawal of the Development Surcharge from January 15, 2018, to the respondents.
Rejecting the respondents' argument, the CERC affirmed that the PPA's restitutionary clause justifies the grant of carrying cost. Citing recent APTEL judgments, the Commission adopted a balanced approach on the rate of interest.
"Given the actual interest rates on the working capital arranged by the Petitioner is lower than the LPS rates as well as the interest rates on working capital as worked out as per the applicable Tariff Regulations, we find it appropriate to permit the Petitioner to claim the carrying cost at the actual rate of interest on the working capital arranged by the Petitioner."
The Commission also adhered to the APTEL's direction to exclude the period from April 29, 2017, to January 25, 2019, from carrying cost calculations for the SHR component, due to litigation delays attributed to the petitioner.
The CERC has disposed of the petition to the extent of the remand, directing the parties to reconcile the final amounts within a month and for payments to be made within 15 days thereafter. This order reinforces the legal sanctity of 'Change in Law' and restitution clauses in PPAs, ensuring that power generators are not economically disadvantaged by unforeseen regulatory and fiscal changes, while also holding them accountable for passing on any subsequent benefits to the distribution companies and, ultimately, the consumers.
#ElectricityLaw #ChangeInLaw #CERC
Vague 'Bad Work' Can't Presume Penetrative Sexual Assault Under POCSO Section 4 Without Evidence: Patna High Court
28 Apr 2026
Limiting Crop Damage Compensation to Specific Wild Animals Excluding Birds Violates Article 14: Bombay HC
28 Apr 2026
Appeal Limitation in 1991 Police Rules Yields to Uttarakhand Police Act 2007 on Inconsistency: Uttarakhand HC
28 Apr 2026
Nashik Court Reserves Verdict on Khan's TCS Bail Plea
29 Apr 2026
Delhi Court Grants Bail to I-PAC Director in PMLA Case
30 Apr 2026
No Historic Record of Saraswati Temple Demolition, Muslim Body Tells MP High Court in Bhojshala Dispute
30 Apr 2026
No Absolute Bar on Simultaneous Parole/Furlough for Co-Accused Under Delhi Prisons Rules: Delhi High Court
30 Apr 2026
Rejection of Jurisdiction Plea under Section 16 Arbitration Act Not Challengeable under Section 34 Till Final Award: Supreme Court
30 Apr 2026
'Living Separately' Under Section 13B HMA Means Cessation Of Marital Obligations, Regardless Of Residence: Patna High Court
30 Apr 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.