Case Law
Subject : Corporate Law - Insolvency and Bankruptcy
New Delhi: The National Company Law Tribunal (NCLT), New Delhi Bench, has dismissed an application filed by the successful resolution applicants (SRA) of Shubhkamna Buildtech Pvt. Ltd., holding that it has no jurisdiction under Section 60(5) of the Insolvency and Bankruptcy Code, 2016 (IBC) to issue directions that would effectively modify a resolution plan already approved by it.
The bench, comprising Hon’ble Member (Judicial) Shri Manni Sankariah Shanmuga Sundaram and Hon’ble Member (Technical) Shri Atul Chaturvedi, emphasized that once a resolution plan attains finality under Section 31 of the IBC, it is binding and irrevocable. The Tribunal ruled that the reliefs sought, though framed as protective measures, would substantively alter the approved plan, which is impermissible in law.
The case pertains to an application filed by Surender Kumar Singhal and Sunil Kumar Agarwal, the SRAs whose resolution plan for Shubhkamna Buildtech was approved by the NCLT on September 12, 2022. The approval of this plan is currently under appeal by the Greater Noida Industrial Development Authority (GNIDA) before the National Company Law Appellate Tribunal (NCLAT).
The applicants sought the NCLT's intervention to conduct a structural audit of the corporate debtor's project, "Shubhkamna City," citing significant structural damage caused by waterlogging from a leaking sewage pipeline. They argued that urgent retrofitting was necessary to preserve the project's viability and ensure the successful implementation of the resolution plan once the pending appeal is resolved.
The SRAs contended that the application was maintainable under the NCLT's residuary powers in Section 60(5) of the IBC. Their key arguments were:
The NCLT, after careful consideration, rejected the applicants' arguments and dismissed the application on the grounds of maintainability. The Tribunal's reasoning was firmly rooted in the principle of finality attached to an approved resolution plan.
> "The reliefs sought by the Applicants, though framed as requests for protective directions and structural audit, would in substance amount to modification of the approved Resolution Plan. This is because any direction for carrying out audit or retrofitting works, and any consequential financial impact thereof, would necessarily alter the cost, timelines, and implementation structure envisaged under the approved Plan."
The bench heavily relied on the Supreme Court's landmark decision in Ebix Singapore Pvt. Ltd. v. Committee of Creditors of Educomp Solutions Ltd. [(2022) 2 SCC 401] , which established that a resolution plan, once approved by the Committee of Creditors and submitted to the Adjudicating Authority, is irrevocable.
The NCLT observed that the SRAs are presumed to have conducted due diligence and analyzed all potential risks before submitting their bid.
> "A Resolution Applicant, after obtaining the financial information of the Corporate Debtor...is assumed to have analyzed the risks in the business of the Corporate Debtor and submitted a considered proposal," the Tribunal noted, quoting the Supreme Court.
Furthermore, the NCLT held that entertaining such an application would amount to "judicial overreach," as the primary approval order is already under scrutiny by the appellate authority (NCLAT). Applying the doctrine of colourable legislation, the bench stated, “what cannot be done directly can also not be done indirectly.”
The Tribunal concluded that the application was an attempt to revisit and vary the terms of a finalized plan under the guise of implementation, which falls beyond the scope of Section 60(5) of the IBC. Accordingly, I.A. 3991 of 2025 was dismissed as not maintainable.
This order reinforces the critical principle of certainty and finality in the corporate insolvency resolution process, underscoring that once a resolution plan is approved, the doors for its modification are firmly shut, even to address unforeseen post-approval challenges.
#NCLT #IBC #ResolutionPlan
Juvenile Justice Act: Gravity and Nature of Alleged Offenses Can Defeat Bail Rights: J&K High Court
25 Mar 2026
Rigors of Section 37 NDPS Act Prevail Over Detention Period Claims: High Court of J&K and Ladakh
11 Mar 2026
Failure to Pay Compensation Vitiates Limitation Claims in Land Acquisition: High Court of Jammu and Kashmir and Ladakh
04 Mar 2026
Discretionary Nature of Section 143-A NI Act: J&K&L High Court Upholds Interim Compensation Based on Accused's Conduct
12 Jun 2026
Salman Khan Files Delhi HC Plea Against 'Kala Hiran'
12 Jun 2026
Writ Court Cannot Exercise Jurisdiction to Grant Interim Relief After Directing Litigant to Civil Forum: MP High Court
12 Jun 2026
Delayed Registration of Birth Certificate Without Statutory Compliance Is Not Proof of Minority: Sikkim High Court
12 Jun 2026
Personal Participation in Contract Work Creates Employer-Employee Tie Under Employees Compensation Act: Kerala High Court
12 Jun 2026
Supreme Court Dismisses Plea Against Rajya Sabha Nomination Rejection
12 Jun 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.