By Sai Teja , Legal News & Court Updates.
Add Sai Teja on Google
Case Law
Subject : Legal News - Arbitration & Contract Law
New Delhi: In a significant ruling concerning contract interpretation and the applicability of arbitration clauses, the High Court of Delhi has dismissed an application seeking to refer a property dispute to arbitration. The court held that an arbitration clause contained in an initial Flat Buyer's Agreement did not extend to claims arising from a subsequent 'Second Agreement' which specifically stated it would override the first agreement, including dispute settlement mechanisms.
Justice
JasmeetSingh
, presiding over the case of
The dispute originated from a Flat Buyer's Agreement dated December 3, 2015, for the purchase of a flat in Gurgaon for Rs. 2 crore. Parallel to this, a 'Second Agreement' was executed on the same date. While the Flat Buyer's Agreement had a standard arbitration clause (Clause 14.2) covering disputes "arising out or touching upon or relating to the terms of this Agreement," the Second Agreement did not.
Crucially, the Second Agreement stipulated specific obligations for the developer: to complete refurbishment and handover possession by December 2, 2016, or refund the entire Rs. 2 crore consideration. This agreement also contained an overriding clause (Clause 9) stating it "shall have an overall overriding effect over the Flat Buyer's Agreement including the settlement of any dispute."
According to the plaintiff,
The defendant, Raheja Developers Ltd, filed an application under Section 8 of the Arbitration and Conciliation Act, 1996, arguing that the suit was not maintainable as the dispute fell under the purview of the arbitration clause in the Flat Buyer's Agreement. Their counsel contended that the two agreements were "inextricably connected" and the arbitration clause in the initial agreement should govern all disputes.
However, the plaintiff's counsel countered that the relief sought was based on the Second Agreement, which contained the specific obligations regarding timely possession or refund, and importantly, lacked an arbitration clause while simultaneously overriding the dispute settlement mechanism of the first agreement.
Justice Singh , in his analysis, noted the distinct nature of the primary obligations in each agreement. While the Flat Buyer's Agreement dealt with the general terms of sale, the Second Agreement fixed the specific deadline for possession or refund – a key element underlying the plaintiff's claim for recovery.
Referencing the Supreme Court's judgment in NBCC (India) Limited vs Zillion Infraprojects Pvt. Ltd (2024 SCC OnLine SC 323) , the High Court reiterated that a general reference to another contract is insufficient to incorporate an arbitration clause from the referred document. A specific reference to the arbitration clause or a conscious acceptance under Section 7(5) of the Arbitration Act is required.
The court found that Clause 9 of the Second Agreement did not merely make a general reference but contained an express condition giving the Second Agreement "overall overriding effect over the Flat Buyer's Agreement, including the settlement of any dispute." The judgment stated, "meaning thereby that there is a specific exclusion of the arbitration clause for settlement of any dispute."
Distinguishing the present case from precedents cited by the defendant (
Olympus Superstructures Pvt. Ltd. vs Meena Vijay Khetan & Ors.
and
Amit Guglani & Anr. vs L&T Housing Finance Ltd & Anr.
), the court highlighted that those cases involved situations where
both
agreements contained arbitration clauses, requiring the court to harmonise them. Here, the Second Agreement had no arbitration clause, and its overriding effect specifically addressed dispute settlement. Similarly, defendant's reliance on
Consequently, the Delhi High Court concluded that the parties, by agreeing to the overriding effect of the Second Agreement, had implicitly waived the arbitration mechanism for disputes governed by the Second Agreement. The application seeking reference to arbitration was therefore dismissed.
The court directed the defendant to file their written statement in the suit within the statutory time period, listing the matter before the Joint Registrar for further proceedings on August 20, 2024. The ruling underscores the critical importance of clear and consistent dispute resolution clauses when multiple agreements govern a single transaction.
#Arbitration #ContractLaw #DelhiHighCourt #DelhiHighCourt
Kerala High Court Salutes R. Rajesh's Supreme Sacrifice, Urges Vigilance in Kochi Flood Prevention
08 Aug 2026
Supreme Court Backs Balanced Calcutta High Court Order on TMC Frozen Accounts in ED Probe
12 Aug 2026
Subsisting Contract Cannot Create Continuing Cause of Action for Time-Barred Debt: Supreme Court
13 Aug 2026
Supreme Court Records Centre's Assurance That Pre-2026 Transgender Identity Cards Stay Valid
17 Aug 2026
Allahabad High Court Grants Bail to Javed Akhtar in GST ITC Fraud Case, Citing Undue Delay
19 Aug 2026
SC Collegium Recommends Appointing Advocate, Judicial Officer to Gauhati High Court
19 Aug 2026
Supreme Court Rules Caste Abuse Inside Closed Room Not Public View Under SC/ST Act
21 Aug 2026
Bombay High Court Pulls Up BMC for Defying Assurance on Bandra Football Ground
21 Aug 2026
RPNLUP Denies Recruitment Irregularities, Files Police Complaint Amid State Law Department Inquiry
21 Aug 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.