Judicial Review of Arbitral Awards
Subject : Dispute Resolution - Arbitration
In a significant ruling that reinforces the judiciary's role in preventing patent illegality in arbitral awards, the Bombay High Court has set aside a ₹75 lakh compensation awarded to a beverage manufacturer, describing the arbitral tribunal's decision as one that "shocks the conscience of the Court."
The single-judge bench of Justice Somasekhar Sundaresan, in the case of Hersheys India Pvt Ltd v Kanti Beverages Pvt. Ltd. , held that an arbitral tribunal cannot grant compensation, however nominal, after having conclusively found that no breach of contract occurred. The court characterized the compensation amount as a figure “picked virtually out of the hat” with no discernible legal or factual basis.
This judgment serves as a critical reminder for arbitrators on the necessity of grounding every part of an award in sound legal reasoning and evidence, and for legal practitioners on the specific grounds under which a domestic arbitral award can be successfully challenged under Section 34 of the Arbitration and Conciliation Act, 1996.
The genesis of the dispute lies in a 2004 manufacturing and packaging agreement between Kanti Beverages Pvt. Ltd. and Godrej Industries (whose beverage division was later acquired by Hersheys India Pvt. Ltd.). Under the three-year contract, Kanti was tasked with producing the popular fruit drink brand 'Jumpin'. A key feature of the agreement was a "take or pay" clause, obligating Hersheys to purchase a minimum of 12 lakh litres of the beverage annually.
As the contract's expiration date of December 6, 2007, approached, renewal discussions commenced. However, the parties failed to reach a consensus, with Hersheys citing uncompetitive pricing from Kanti as the primary reason for its decision not to extend the agreement. Consequently, Hersheys formally informed Kanti that the contract would lapse upon its expiry.
Dissatisfied with this outcome, Kanti Beverages initiated arbitration proceedings. Kanti’s claims were threefold: 1. The contract had been implicitly extended by the conduct of the parties. 2. Hersheys had wrongfully terminated the purportedly extended contract. 3. Hersheys had misappropriated Kanti's proprietary PET hot-filling technology.
The arbitral tribunal undertook a detailed examination of the evidence and arguments presented by both sides. In its final award, the tribunal systematically rejected each of Kanti’s primary claims on their merits. It found no evidence to support the assertion that the contract was extended by conduct, and therefore, the question of wrongful termination did not arise. The claim of technology misappropriation was also dismissed.
Despite these clear and unequivocal findings, the arbitral tribunal made a surprising and ultimately fatal decision. It directed Hersheys to pay Kanti a sum of ₹75 lakh as compensation. The tribunal's rationale was that Hersheys' silence during certain phases of the renewal discussions had created an "implied hope" for Kanti, leading to "inconvenience."
This reasoning formed the crux of Hersheys' challenge before the Bombay High Court. Hersheys argued that the award was patently illegal and perverse, as it granted a remedy without establishing any corresponding right or breach.
Justice Sundaresan’s judgment provides a sharp critique of the arbitral tribunal's reasoning, deconstructing the logical fallacies that underpinned the compensation award. The court found the decision to award ₹75 lakh completely disconnected from the tribunal's own substantive findings.
The court observed with pointed criticism:
“Having arrived at such a finding, it is inexplicable that the Learned Arbitral Tribunal would think it fit to pick a number of Rs.75 lakhs virtually out the hat, to award it to Kanti as compensation for harbouring hope from the alleged silence in reaction to Kanti's emails.”
Justice Sundaresan highlighted the inherent contradiction in the tribunal's award. If the tribunal believed that silence could constitute an agreement, it should have ruled that the contract was indeed renewed. By explicitly finding that the contract was not renewed, the tribunal had removed any legal basis for awarding damages flowing from a contractual breach.
“If there had been no firm agreed consent to extend the Agreement beyond December 6, 2007, it would naturally follow that there could have been no other compensation even contemplated or, much less, inference of any implied commitment or implied hope,” the court said.
The High Court emphasized that compensation cannot be awarded for a party's subjective "hope" in the absence of a legally enforceable obligation. The tribunal's award effectively created a liability out of thin air, a move the court found to be a patent illegality that "shocks the conscience of the Court." Furthermore, the court noted a complete lack of evidence or calculation methodology to justify the specific figure of ₹75 lakh, reinforcing the assertion that it was an arbitrary number.
An important aspect of the High Court's decision was its application of the doctrine of severability. The court found that the flawed direction to pay compensation was "out of sync with the rest of the Impugned Award." The core of the award, which correctly adjudicated the merits of the contractual claims, was sound. The illegal portion—the compensation—could be cleanly severed and set aside without disturbing the tribunal’s valid findings.
Accordingly, the court set aside only the part of the arbitral award that directed the payment of ₹75 lakh, leaving the remainder of the award intact.
This judgment holds several important lessons for the legal and business communities, particularly those involved in arbitration:
Compensation Must Follow Breach: The ruling unequivocally affirms the fundamental legal principle that compensation or damages are remedies for a proven legal wrong, typically a breach of contract or a tort. An arbitral award that grants compensation without finding any such breach is fundamentally flawed and susceptible to being set aside.
Judicial Scrutiny of 'Perverse' Awards: While the scope of judicial review under Section 34 is narrow, this case demonstrates that courts will not shy away from intervening when an award is patently illegal or based on findings that no reasonable person could have reached. An award that is internally contradictory, as this one was, falls squarely into this category.
Silence is Not Acceptance: The judgment implicitly reinforces the established contract law principle that silence, on its own, generally does not constitute acceptance of an offer or a proposal for contract renewal, especially in formal commercial relationships.
Arbitrators Must Show Their Work: The High Court's sharp criticism of the "out of the hat" figure underscores the necessity for arbitrators to provide clear, reasoned justifications for any monetary sums awarded. The basis for calculating damages or compensation must be transparent and rooted in the evidence presented.
For arbitration practitioners, this case serves as a powerful precedent to cite when challenging awards that grant unreasoned or baseless monetary relief. It also acts as a guide for arbitrators to ensure their awards are logically consistent and legally sound from start to finish, thereby enhancing their robustness against judicial challenge.
#ArbitrationLaw #ContractDispute #BombayHighCourt
No Prima Facie Case of Anti-Competitive Agreements or Abuse of Dominance in Solar Tender: CCI Closes Matter Under Section 26(2) of Competition Act
17 Apr 2026
Delhi HC Quashes POCSO FIR in Consensual Case, Lays Guidelines When 'De-Jure Victim' Denies Harm Under Section 6 POCSO
17 Apr 2026
Supreme Court Orders CCTV, GPS to Curb Chambal Mining
17 Apr 2026
Delhi High Court Rejects EWS Age Relaxation Plea
17 Apr 2026
Supreme Court Denies Khera Bail Extension, Directs Gauhati HC
17 Apr 2026
Madras HC Directs Municipality to Auction Amusement Rides Licenses on Vaigai Riverbed for Chithirai Festival: Madurai Bench
17 Apr 2026
TCS Nashik Accused Seek Bail in Harassment Probe
17 Apr 2026
Insurer Liable for Gratuitous Passenger in Goods Vehicle, Can Recover from Owner: Kerala High Court
17 Apr 2026
MP High Court Issues Notice in PIL Alleging Disrespect to National Song 'Vande Mataram' by Indore Councillors: Article 51A(a)
17 Apr 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.