The has affirmed an ’s mandate for the () to reimburse ₹5.50 crore to the German firm . In a significant judgment, the court rejected the majority of the municipal body's challenges to an , upholding the tribunal's findings regarding the of a . While the court maintained the core of the refund order, it exercised its discretionary power under the , to modify the rate of interest, reducing it from 12% to 10% per annum.
The dispute stems from a contract executed in for the rehabilitation of the Bandra Collector Tunnel, a critical component of the Bombay Sewage Disposal Project. , acting through its successor entity, had successfully completed the civil works by , obtaining a completion certificate shortly thereafter. However, the project was marred by delays, leading the contractor to seek an (EOT). In , the project engineer advised the municipal corporation to retain security against potential pending the finalization of the extension request.
Despite ongoing arbitral proceedings regarding the EOT, the municipal corporation invoked the in . The contractor alleged that this action was not only premature but also an abuse of power, as the underlying dispute regarding remained . The encashment of the ₹5.50 crore left the contractor without the necessary operational liquidity, triggering a long-standing legal battle that spanned several rounds of arbitration and judicial review.
Dispute Origins and Encashment
The , after assessing the merits of the case, concluded that the encashment of the was illegal, as the corporation's entitlement to had not been established. The tribunal determined that the claims for an were valid, thereby invalidating the grounds upon which the corporation had initially retained the . In its award, the tribunal directed the municipal corporation to refund the encashed amount with interest calculated from the date of the guarantee's invocation in .
During the stage, a technical dispute arose regarding a clerical error in the tribunal’s award, which had initially specified as the date for interest commencement. The contractor filed an application under , requesting a correction to —the actual date the bank remitted the payment to the municipal corporation. The tribunal allowed this correction, an action which the municipal corporation subsequently challenged, arguing that the modification was substantive rather than clerical and therefore exceeded the tribunal's jurisdiction.
Tribunal’s Power of Correction Under Review
In its analysis of the challenge, the High Court emphasized the distinct nature of the powers conferred upon arbitrators by Section 33 of the Act. Justice Aarti Sathe clarified that the threshold for interference under is restricted and that the court must distinguish between a genuine correction of a typographical error and an attempt to reconsider the merits of a dispute. The court noted that the municipal corporation failed to raise objections when the correction was initially presented before the tribunal.
Addressing the procedural requirement of recording reasons, the court observed: “ does not expressly prescribe a separate requirement to record reasons for every correction of a falling within its scope. Accordingly, the absence of elaborate reasons in the order allowing such a correction does not, by itself, render the corrected impugned invalid.” The court further added: “The correction was... a correction of a typographical error within the scope of Section 33 of the Act.”
The High Court held that the tribunal’s decision to correct the date was aimed at aligning the award with the relief originally sought by the contractor in its statement of claim. By rectifying the date, the tribunal did not alter the substance of its decision but rather remedied an oversight that was evident on the face of the record.
Interest Rates and Statutory Mandates
The municipal corporation also contended that the 12% per annum rate of interest imposed on the refund was excessive and placed an unjust burden on public funds. The court examined the provisions of , which governs interest rates. While the tribunal had initially applied a 12% rate, the High Court noted that the post-2016 for interest calculation requires adherence to a rate linked to the prevalent market interest rate.
Relying on recent precedents regarding the court's authority to modify interest rates to ensure equity, the High Court determined that a 10% interest rate was more appropriate in the context of the market conditions existing at the time of the award in . Consequently, the court modified the arbitral direction to ensure that the interest component aligned with current legislative standards without setting aside the underlying award.
The High Court disposed of the petition, ordering that any funds currently deposited in court be released to the contractor in accordance with the law within one month of the judgment’s upload. The operation of the court's order has been stayed for four weeks to allow the municipal corporation to explore potential appeals to a higher forum. This ruling concludes a significant chapter in the long-running dispute between the municipal body and the contractor, reinforcing the limits of judicial intervention in the correction of clerical arbitral errors while maintaining oversight on interest liabilities.
bank-guarantee-encashment - arbitral-award-enforcement