Case Law
Subject : Regulatory Law - Electricity Law
New Delhi, June 23, 2025
– The Central Electricity Regulatory Commission (CERC), in a significant procedural order, has found POWERGRID KPS 1 and 2 Augmentation Transmission Limited prima facie eligible for a transmission licence for a critical infrastructure project in the Khavda region. The project aims to augment power transformation capacity to support
The bench, comprising Chairperson Jishnu Barua and Members Ramesh Babu V. and Ravinder Singh Dhillon, condoned a 10-day delay in the filing of the application and directed that a public notice be issued to invite suggestions or objections before a final decision is made.
The petition was filed by POWERGRID KPS 1 and 2 Augmentation Transmission Limited, a wholly-owned subsidiary of the state-run Power Grid Corporation of
This project involves installing high-capacity transformers at two key substations (KPS1 and KPS2) to evacuate power from upcoming renewable energy projects, including those by
The petitioner, represented by Shri
Successful Bid: PGCIL emerged as the successful bidder in a competitive e-reverse auction, quoting the lowest levelized transmission charges of ₹698.58 million per annum. This was lower than the competing bid from Adani Energy Solutions Limited.
Regulatory Compliance:
Following its selection, PGCIL acquired the petitioner Special Purpose Vehicle (SPV), furnished a Contract Performance Guarantee of ₹15 crores, and executed the Transmission Service Agreement (TSA) with the Central Transmission Utility of
Filing Delay: The petitioner explained that a 10-day delay in filing the licence application was due to a technical issue with the e-filing portal and requested the Commission to condone it.
Project Necessity: CTUIL, in its submission, supported the grant of the licence. It highlighted that the augmentation is essential to maintain grid stability (N-1 compliance) and facilitate the immediate injection of over 1400 MW of renewable power from the Khavda region, even before the larger evacuation systems are fully commissioned.
The 29 listed respondents, including major power distribution companies and generators, did not file any reply to the petition despite being served notice.
The CERC meticulously reviewed the case against the backdrop of the Electricity Act, 2003, and its 2024 Transmission Licence Regulations.
"The Petitioner has been incorporated under the Companies Act 2013... The Project under consideration has been identified for development under competitive bidding by a competent authority, and the selection of the Project developer has been certified to have been made in accordance with the Guidelines for competitive bidding," the Commission noted, affirming the petitioner's eligibility under Regulation 4 of the Licence Regulations.
On the procedural delay, the Commission took a pragmatic view:
"The Petitioner has submitted that there has been a delay of 10 days in the filing of the instant Petition due to the non-reflection of the filing fees of the Petition on the e-portal... Since the Petitioner could not file the Petition due to procedural lapse, we condone the said delay."
The Commission also took on record the change in the petitioner's name from ‘Khavda V-B1B2 Power Transmission Limited’ to ‘POWERGRID KPS 1 and 2 Augmentation Transmission Limited’, effective May 14, 2025.
After considering all materials and submissions, the CERC concluded that the petitioner meets the preliminary requirements for the licence. The final order stated:
"Considering the material on record, we are prima facie of the view that the Petitioner satisfies the conditions for the grant of inter-State transmission licence under Section 15 of the Act... We, therefore, direct that a public notice under clause (a) of sub-section (5) of Section 15 of the Act be published to invite suggestions or objections to the grant of a transmission licence aforesaid."
The Commission has scheduled the next hearing for July 15, 2025, after the period for public objections closes on July 11, 2025. This order moves a vital piece of
#CERCLicense #ElectricityAct #PowerGrid
No Historic Record of Saraswati Temple Demolition, Muslim Body Tells MP High Court in Bhojshala Dispute
30 Apr 2026
No Absolute Bar on Simultaneous Parole/Furlough for Co-Accused Under Delhi Prisons Rules: Delhi High Court
30 Apr 2026
Rejection of Jurisdiction Plea under Section 16 Arbitration Act Not Challengeable under Section 34 Till Final Award: Supreme Court
30 Apr 2026
'Living Separately' Under Section 13B HMA Means Cessation Of Marital Obligations, Regardless Of Residence: Patna High Court
30 Apr 2026
Consolidated SCNs under Sections 73/74 CGST Act Permissible Across Multiple FYs: Karnataka HC
01 May 2026
Allahabad HC Stays NCLT Principal Bench Order Mandating Joint Scrutiny of Allahabad Bench Filings
01 May 2026
Bombay HC Grants Interim Protection from Arrest Despite Pending Anticipatory Bail in Lower Court Due to Accused's Marriage: Sections 351(2), 64(2)(m), 74 IPC
01 May 2026
Heavy Machinery Barred in Mining Leases Except Dredging: Uttarakhand HC Directs DM to Enforce Rule 29(17) of Minor Mineral Rules
01 May 2026
No Deemed Confirmation After Probation Without Written Order Under Model Standing Orders Clause 4A: Bombay High Court
01 May 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.