SupremeToday Landscape Ad
Back
Next

Section 35 Construction Industry Payment and Adjudication Act 2012

Back-to-Back Payment Clauses Void Under Section 35 CIPAA Even Without Adjudication Proceedings: Malaysian High Court - 2026-01-20

Subject : Civil Law - Construction Contract Disputes

Back-to-Back Payment Clauses Void Under Section 35 CIPAA Even Without Adjudication Proceedings: Malaysian High Court

Supreme Today News Desk

Back-to-Back Payment Clauses Void Under Section 35 CIPAA Even Without Adjudication Proceedings: Malaysian High Court

Introduction

The Malaysian High Court, in a judgment delivered by Judicial Commissioner Wong Kian Kheong, dismissed an appeal against a Sessions Court decision awarding payment to a sub-subcontractor in a construction dispute. The case centered on the validity of a "back-to-back" payment clause under the Construction Industry Payment and Adjudication Act 2012 (CIPAA), ruling that such conditional provisions are void under Section 35, irrespective of whether adjudication proceedings have been initiated. The plaintiff, a steel works subcontractor, successfully claimed RM346,857 plus interest from the defendant sub-contractor, despite the main contractor's delayed payments.

Case Background

The dispute arose from a construction project in Jasin, Malacca, appointed by Jabatan Kerja Raya (JKR) to main contractor Pembinaan & Letrik MALS Sdn. Bhd. (MALS) in February 2018. MALS subcontracted the defendant company for the project works. The defendant then engaged the plaintiff company via two purchase orders dated 30 March and 30 May 2018 for steel works valued at RM676,857, incorporating a "back-to-back" payment term obliging payment only upon the defendant's receipt from MALS.

The plaintiff completed the works, but the defendant paid only RM330,000 before MALS terminated the main subcontract on 23 July 2018, leaving a balance of RM346,857 unpaid. This delay caused the plaintiff to incur RM45,500 in late payment interest to its steel supplier, Yick Hoe Ferrous Steel Sdn. Bhd. The plaintiff sued in Sessions Court for the balance and interest, relying on quantum meruit and claiming MALS had paid the defendant for the works. The Sessions Court Judge, Datin Setia Nursinah Bt. Adzmi, awarded the full judgment sum of RM346,857 plus interest, finding the back-to-back defense an afterthought and accepting evidence that MALS's payments covered the works. The defendant appealed to the High Court, raising issues on proof burdens, factual errors, and the applicability of quantum meruit.

Arguments Presented

The defendant argued that the back-to-back clause excused payment since MALS had not fully settled its dues, claiming only RM2.66 million was received against an entitlement of RM7.05 million up to termination. It contended the plaintiff failed to prove MALS paid for the specific works, shifting no evidential burden under Sections 102 and 106 of the Evidence Act 1950. The defendant also alleged factual errors by the Sessions Court in accepting the plaintiff's evidence and argued quantum meruit was inapplicable with an existing contract, urging the High Court to set aside the judgment under Sections 29 and 72 of the Courts of Judicature Act 1964.

The plaintiff countered that it discharged its evidential burden via an uncontroverted email and witness testimony from MALS's managing director, Noreldzleen Bt. Mohd. Idris, confirming payments included the works. It invoked quantum meruit for unjust enrichment and maintained the back-to-back clause did not bar recovery, emphasizing the works' completion entitled it to payment regardless of upstream delays. Both parties agreed in pre-trial that the back-to-back clause applied, but the court questioned its validity under CIPAA.

Legal Analysis

The High Court first addressed whether Section 35(1) and (2)(a) of CIPAA voids back-to-back clauses outside adjudication. Overruling prior views limited to adjudication contexts (e.g., Bond M&E (KL) Sdn Bhd v Isyoda (M) Sdn Bhd), the court held the clause void generally, as CIPAA's long title promotes timely payments independently of dispute resolution. It applied CIPAA's four cumulative requirements under Section 2—written construction contract for Malaysian works—and placed Section 35 in Part VI (General), not adjudication-specific parts, interpreting "any conditional payment provision" broadly per precedents like Metramac Corp Sdn Bhd v Fawziah Holdings Sdn Bhd.

On burden of proof, the court clarified under Evidence Act Sections 101-102, 106: the plaintiff bore the legal burden but shifted evidential onus by prima facie evidence (unreplied email and credible testimony), with the fact of MALS's payments especially within the defendant's knowledge. No "plain errors of fact" warranted appellate interference per Gan Yook Chin & Anor v Lee Ing Chin & Ors.

The court acknowledged the Sessions Court's error in applying quantum meruit (inapplicable with a subsisting contract, per Tanjung Teras Sdn Bhd v Kerajaan Malaysia), but deemed it immaterial under Section 72 Courts of Judicature Act, as the contract itself supported recovery. Precedents like Barisan Tenaga Perancang (M) Sdn Bhd v Dr Mansur bin Hussain & Ors affirmed courts' duty to raise illegality sua sponte, unbound by parties' concessions on law (Ahmad Tajudin Bin Hj Ishak v Suruhanjaya Pelabuhan Pulau Pinang).

Distinguishing pre-CIPAA cases like Globe Engineering Sdn Bhd v Bina Jati Sdn Bhd, the ruling prioritizes CIPAA's specificity over general contract law, allowing the defendant recourse against MALS separately.

Key Observations

  • On CIPAA's broad application: "Section 35 is expressly placed by Parliament in Part VI (CIPAA) and is therefore intended by the legislature to be of general application irrespective of whether AP have been instituted pursuant to CIPAA or not."
  • Regarding illegality: "If there is an illegal contract or transaction, the court is duty bound to take cognizance of the illegality and cannot enforce the illegal contract or transaction (even if the illegality is not pleaded or raised by any party)."
  • On burden shift: "The Prima Facie Case is based on the following evidence... The proof of a Prima Facie Case justifies the Shifting (Evidential Burden) in this case."
  • Quantum meruit limitation: "Liability under s 71 is not based on any existing contract between the parties. Rather it is based on the equitable principle of conscionable conduct and restitution to prevent unjust enrichment."
  • Appellate discretion: "Notwithstanding SC’s Legal Error, pursuant to s 29... the Plaintiff’s Works (Balance Sum) had been performed for which the Defendant was liable to the Plaintiff under the Contract (Plaintiff-Defendant)."

Court's Decision

The High Court dismissed the appeal without costs, upholding the Sessions Court's judgment for RM346,857 plus interest. The back-to-back clause was declared void under Section 35 CIPAA, enforcing direct payment obligations in construction subcontracts to ensure timely industry payments. This promotes cash flow down the chain, deterring payment delays, and applies to all qualifying written contracts without needing adjudication. Future cases may see broader CIPAA enforcement in court proceedings, potentially reducing "pay-when-paid" defenses, though the court urged appellate clarification. The defendant retains claims against MALS in separate suit WA-22C-76-10/2018.

back-to-back agreement - conditional payment - quantum meruit doctrine - evidential burden - construction subcontract - illegality in contracts

#CIPAA #ConstructionContracts

Breaking News

View All
SupremeToday Portrait Ad
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top