Breach of Construction Contract and Termination
Subject : Civil Law - Contract Disputes
In a detailed judgment, the High Court of Malaysia, presided over by YBhg Datuk Aliza Sulaiman H, dismissed claims by a construction company against the Ministry of Education Malaysia and the Government of Malaysia, upholding the termination of two successive contracts for building the Perlis Sports School. The court ruled the terminations valid due to the contractor's failure to perform diligently, rejected demands for unpaid work totaling over RM7 million, and allowed the government's counterclaim for termination costs amounting to RM4,030,327.79 plus interest. This case highlights the strict enforcement of public works contracts under the PWD Form 203A, emphasizing timely performance in government projects.
The plaintiff, a Malaysian-registered construction firm based in Alor Setar, Kedah, was initially awarded Contract 1 in January 2013 by the Ministry of Education (D1) and the Government of Malaysia (D2) to build and complete the Perlis Sports School for RM34,264,062.65. The 18-month contract, signed in June 2013 using PWD Form 203A (Rev. 1/2010), faced delays, leading to its termination in November 2014 amid disputes over progress and extensions of time. Despite this, the same contractor was reappointed under Contract 2 in May 2018 for RM32,012,000 to complete the stalled project over two years, with site possession in February 2018. Similar issues recurred, resulting in termination in April 2019.
The plaintiff sued seeking declarations that both terminations were invalid, payment for work done (RM6,454,861.72 for Contract 1 and RM961,550.39 for Contract 2), interest, and general damages. The defendants denied liability, counterclaimed for outstanding termination costs of RM4,030,327.79 from Contract 1, and argued the Ministry (D1) was not a suable entity, only the Government (D2) under relevant laws.
Key legal questions included: the validity of terminations under Clause 51 of the Conditions of Contract (CoC); entitlement to extensions of time (EoT); recognition of variation and remeasurement claims; legality of the Termination Costs Certificate; and deductions from progress payments.
The plaintiff contended that terminations were unlawful, citing external factors like site changes, delayed approvals, underground cable interferences, and late payments causing cash flow issues and subcontractor withdrawals. They argued for EoT approvals under Clause 43 CoC for 172 days initially (granted 109 days) and a rejected second EoT, claiming undervalued interim certificates ignored additional works not in the Bill of Quantities (BQ). For Contract 2, they asserted diligent performance evidenced by certified progress claims, blaming non-payment for delays and denying agreement to set-off termination costs against payments. They challenged the Termination Costs Certificate as mala fide, untimely, and ignoring their RM6.45 million variation claims, seeking full payment plus 5% interest.
The defendants maintained valid terminations due to the plaintiff's consistent failure to proceed "regularly and diligently" under Clause 51.1(a)(iii) CoC, supported by site meeting minutes, progress reports showing lags (e.g., 49% vs. 100% expected for Contract 1), and warnings issued. They justified denying the second EoT as claims fell outside Clause 43 grounds or were unproven, and argued the plaintiff's acceptance of Contract 2 estopped challenges to Contract 1's termination, with costs recoverable via deductions under Clause 33. For the certificate, they detailed calculations per Clause 56, including re-tendering and supervision costs, asserting no time bar under the Limitation Act 1953 and no liability for D1 as a non-legal entity.
The court applied principles from construction law, emphasizing commercial contracts must be construed sensibly (Berjaya Times Squares Sdn Bhd v M Concept Sdn Bhd). It ruled D1 non-suable under Sections 2 and 21 of the Government Contracts Act 1949 and Government Proceedings Act 1956, dismissing claims against it solely on this ground (citing Vestime Corporation Sdn Bhd v Yble Resources Sdn Bhd). The counterclaim against D2 was within the six-year limitation period, accruing upon issuance of the Termination Costs Certificate in 2020 per Clause 56 CoC, or from the last set-off in 2019 (Kerajaan Malaysia v PKNS Engineering & Construction Bhd; Goh Kiang Heng v Mohd Ali Abd Majid).
On termination validity, the court invoked estoppel (Boustead Trading (1985) Sdn Bhd v Arab-Malaysian Merchant Bank Berhad; Double Advantage Sdn Bhd v Paduan Hebat Sdn Bhd), finding the plaintiff's entry into Contract 2 with agreed set-offs precluded challenging Contract 1. Independently, evidence like progress reports and notices proved non-diligent performance (Petowa Jaya Sdn Bhd v Binaan Nasional Sdn Bhd; Kerajaan Malaysia v Ven-Coal Resources Sdn Bhd; Sunshine Fleet Sdn Bhd v Jabatan Kerja Raya Malaysia), distinguishing "regularly and diligently" as requiring constant, industrious progress tied to completion dates.
EoT denial was proper; claims like tree felling and BQ discrepancies were core obligations, not qualifying under Clause 43 (e.g., site clearance included all trees per BQ and pre-tender briefings). Variations totaling RM6.45 million failed proof, lacking technical evidence or Variation Order instructions under Clause 8 (Binaan Nasional Sdn Bhd v Bridgecon Engineering Sdn Bhd). The Termination Costs Certificate was binding per Clause 56.5, calculations reasonable under Section 74 Contracts Act 1950 (Hamdan Johan & Ors v Felcra Bhd Ors), covering re-tendering, security, and on-costs without mitigation duty proven breached. Deductions under Clause 33 were lawful, tied to the estoppel agreement.
The High Court dismissed all of the plaintiff's claims, declaring both contract terminations valid and the Termination Costs Certificate lawful. It allowed D2's counterclaim for RM4,030,327.79 (balance after set-offs) with 5% annual interest from the judgment date until full payment, plus RM50,000 costs against the plaintiff. Claims against D1 were struck out as it is not a legal entity.
This ruling reinforces accountability in public construction contracts, prioritizing diligent execution to avoid escalating costs for taxpayers. It may deter reappointments without resolving prior breaches and guide future disputes by upholding CoC mechanisms like estoppel and conclusive certificates, potentially influencing how delays and variations are litigated in Malaysian infrastructure projects.
construction delay - contract breach - extension of time - diligent performance - variation claims - termination costs
#ContractTermination #ConstructionLaw
No Historic Record of Saraswati Temple Demolition, Muslim Body Tells MP High Court in Bhojshala Dispute
30 Apr 2026
No Absolute Bar on Simultaneous Parole/Furlough for Co-Accused Under Delhi Prisons Rules: Delhi High Court
30 Apr 2026
Rejection of Jurisdiction Plea under Section 16 Arbitration Act Not Challengeable under Section 34 Till Final Award: Supreme Court
30 Apr 2026
'Living Separately' Under Section 13B HMA Means Cessation Of Marital Obligations, Regardless Of Residence: Patna High Court
30 Apr 2026
Consolidated SCNs under Sections 73/74 CGST Act Permissible Across Multiple FYs: Karnataka HC
01 May 2026
Allahabad HC Stays NCLT Principal Bench Order Mandating Joint Scrutiny of Allahabad Bench Filings
01 May 2026
Bombay HC Grants Interim Protection from Arrest Despite Pending Anticipatory Bail in Lower Court Due to Accused's Marriage: Sections 351(2), 64(2)(m), 74 IPC
01 May 2026
Heavy Machinery Barred in Mining Leases Except Dredging: Uttarakhand HC Directs DM to Enforce Rule 29(17) of Minor Mineral Rules
01 May 2026
No Deemed Confirmation After Probation Without Written Order Under Model Standing Orders Clause 4A: Bombay High Court
01 May 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.