Delhi High Court: Retaining Bank Guarantees After Settled Award Unjustified Against ANS Construction

Once the underlying arbitral award is settled and paid, the party cannot retain or invoke performance bank guarantees, security deposits or fixed deposit receipts – the Delhi High Court has firmly held while dismissing the Union of India's twin petitions under Section 34 of the Arbitration and Conciliation Act, 1996.

Justice Tushar Rao Gedela, on August 11, 2026, upheld an arbitral award dated April 5, 2019 that permanently restrained the Union from encashing three bank guarantees and an FDR, and directed their immediate release to M/S ANS Construction Ltd. The Court also awarded ₹7,08,375 as reimbursement for bank charges incurred in keeping the guarantees alive.

A Tale of Two Arbitrations and a Consent Order

The dispute originated from a construction contract awarded to ANS Construction on September 7, 2010 for building family quarters and development works at Balrampur, Uttar Pradesh. The contractor furnished an FDR of ₹9,50,487 as earnest money, along with bank guarantees for performance security, EMD and security deposit.

Disputes led to arbitration before Sole Arbitrator V.K. Malik, who passed a final award on July 26, 2017 granting ₹1.63 crore to the contractor after adjusting the Union's counterclaim. That award was later amicably settled between the parties through a settlement agreement dated December 5, 2017, and the Union duly paid the agreed sum.

Six additional claims — primarily concerning the release of the guarantees — had been referred to a second arbitrator, S.K. Verma, but those proceedings were terminated on February 15, 2018 after the contractor failed to file its statement of claim. Undeterred, ANS Construction approached the Delhi High Court by way of a Section 9 petition seeking protection against encashment.

On September 4, 2018, with both sides present and agreeing, the Court appointed former judge Justice Pratibha Rani as arbitrator to adjudicate the very same six additional claims. The order explicitly recorded that the Union's counsel had "categorically agreed" to this arrangement and continued interim protection in respect of three specified bank guarantees.

Union's Objections – Too Little, Too Late

Before the High Court, the Union argued that since the second arbitral proceedings had already been terminated for non-prosecution, a fresh reference of those claims was legally impermissible. It also challenged the award of ₹7,08,375 for bank renewal charges, contending that the guarantees were kept alive because of the court's own interim order.

Justice Gedela cut through both submissions. On the first objection, he noted that the Union had not raised any such plea when it consented to Justice Rani's appointment on September 4, 2018 . "Having regard thereto, raising the said argument at this belated stage is not permissible," the Court observed.

As for the renewal charges, the September 4 order itself expressly authorised the arbitrator to "adjudicate upon a claim, if any, filed by the petitioner for repayment of interest and/or charges paid to keep the aforementioned bank guarantees alive." Since that direction was never challenged, the arbitrator acted well within the scope of reference .

The Core Principle: No Grounds to Retain After Settlement

The Court found that the arbitrator's reasoning was in complete consonance with settled legal principles. Once the main contractual disputes had been fully adjudicated and the resultant award settled, there remained no conceivable basis for the Union to retain or invoke the security instruments.

In paragraph 18 of the impugned award , the arbitrator had reasoned: "After determination of the reciprocal obligations of the parties under the contract agreement in the earlier arbitration, nothing survives in favour of the Respondent to allow it to en-cash the Bank Guarantees/FDR in question."

The High Court endorsed this view, stating: "If that be so, then once the main claims in respect of the dispute arising out of the contract between the parties is adjudicated and subsequently the arbitral award is settled between parties, there is no reason as to why and on what basis the performance bank guarantees , security deposits , FDRs in respect thereto, can be retained or sought to be invoked by the petitioner."

Key Observations from the Judgment

  • On the consent-order objection: "Having regard thereto, raising the said argument at this belated stage is not permissible."
  • On the bank charges claim: "It was specifically noted vide order 04.09.2018 that the parties by consent not only agreed for appointment of an Arbitrator but also to the claims noted therein."
  • On the effect of settlement: "If that be so, then once the main claims... is adjudicated and subsequently the arbitral award is settled between parties, there is no reason as to why and on what basis the performance bank guarantees ... can be retained or sought to be invoked by the petitioner."

The Final Word

Finding no perversity or violation of the fundamental policy of Indian law in the arbitrator's findings, Justice Gedela dismissed both Section 34 petitions with no order as to costs. The ruling reinforces the principle that once a contractual dispute is finally resolved and the award settled, the security instruments furnished to secure performance must be returned — they cannot be held hostage by the employer.

Case Title: Union of India vs. M/S ANS Construction Ltd | O.M.P. (COMM) 373/2019 & 377/2019 | Coram: Justice Tushar Rao Gedela | Date of Decision: August 11, 2026