SupremeToday Landscape Ad
Back
Next

Case Law

Delhi High Court Sets Aside Arbitral Award for Loss of Profit on Prolongation Citing Lack of Evidence, Upholds Escalation Award Under Section 37 A&C Act - 2025-04-26

Subject : Law - Arbitration

Delhi High Court Sets Aside Arbitral Award for Loss of Profit on Prolongation Citing Lack of Evidence, Upholds Escalation Award Under Section 37 A&C Act

Supreme Today News Desk

Delhi High Court Sets Aside Contractor's Loss of Profit Award in MCD Dispute, Citing Lack of Evidence

New Delhi: In a significant ruling concerning challenges to arbitral awards, the Delhi High Court has partially set aside an award in a dispute between the Municipal Corporation of Delhi (MCD) and a contractor over delays in a polyclinic construction project. The court upheld the arbitral tribunal's decision to grant the contractor escalation costs but struck down the award for loss of profit due to contract prolongation, finding it lacked evidentiary basis.

The judgment, delivered by Justice Vibhu Bakhru , came on an appeal filed by the MCD under Section 37(1)(c) of the Arbitration & Conciliation Act, 1996 (A&C Act), challenging an order of the Commercial Court.

Case Background

The dispute arose from a contract awarded in June 2005 for the construction of a polyclinic in Bawana, Delhi, valued at over Rs. 1.41 crore. The work, originally scheduled for completion within 18 months (by December 2006), suffered extensive delays, finally finishing in October 2011, more than 76 months after commencement.

The contractor attributed the delay to the MCD's failures, including not providing a hinderance-free site, timely drawings, necessary instructions, and prompt payments. These disputes were referred to arbitration.

Arbitration Award

Before the Arbitral Tribunal, the contractor raised claims totaling over Rs. 1.02 crore, including: - Extra/deviated work costs (Claims 1 & 2 - Rs. 28.85 Lakhs and Rs. 4.54 Lakhs ) - Refund of Security Deposit (Claim 3 - Rs. 5 Lakhs ) - Arrears of escalation under Clause 10C (Claim 4 - Rs. 10.21 Lakhs ) - Damages for prolongation/Loss of Profit (Claim 5 - Rs. 47.14 Lakhs , sought Rs. 35.35 Lakhs ) - Interest and Costs (Claims 6, 7, 8)

The Arbitral Tribunal found the MCD responsible for significant delays (approximately 45 months combined due to tree removal and delay in providing drawings). It disallowed Claims 1 and 2 (extra work), noting lack of communication at the time and insufficient proof. It allowed Claim 3 (security deposit).

Crucially, the Tribunal allowed Claim 4, awarding Rs. 10.21 Lakhs for escalation under Clause 10C based on statutory wage revisions. It also partly allowed Claim 5 (loss of profit), awarding Rs. 35.35 Lakhs . The Tribunal calculated this by assuming a 10% monthly profit on the average value of work and multiplying it by the 45-month delay period attributed to MCD.

Proceedings Before Commercial Court

The contractor filed a Section 34 petition challenging the rejection of Claims 1, 2, 6, and 8. The MCD also filed a Section 34 petition challenging the award of Claims 4 and 5.

The Commercial Court dismissed the MCD's challenge to Claims 4 and 5, holding that the Arbitral Tribunal's findings were not in conflict with the fundamental policy of Indian law or basic notions of justice.

(Note: In a separate development, the Commercial Court had initially allowed the contractor's challenge regarding Claims 1, 2 & 8, but this was subsequently set aside by the Delhi High Court in a prior appeal, granting the contractor liberty to approach the Arbitral Tribunal afresh on those claims.)

MCD's Appeal to High Court (Current)

The MCD filed the present appeal challenging the Commercial Court's order insofar as it upheld the Arbitral Tribunal's award for Claims 4 (Escalation) and 5 (Loss of Profit).

The MCD argued that the contractor had not provided evidence of actually paying the enhanced wages to justify the Clause 10C award. Regarding Claim 5, the MCD contended the contractor failed to prove that the delay was attributable to MCD and that he would have earned profit on an alternative contract during the prolonged period.

High Court's Analysis and Decision

The High Court confined its examination to Claims 4 and 5, as the MCD had not challenged Claim 3 (security deposit refund) in the Commercial Court.

On Delay: The court concurred with the Arbitral Tribunal and Commercial Court that the finding of delay attributable to the MCD was based on evidence appreciation, which cannot be re-evaluated under Section 34 or 37 of the A&C Act.

On Claim 4 (Escalation under Clause 10C): The court rejected the MCD's argument regarding lack of proof of actual wage payment. It noted that the contractor had placed statutory notifications regarding minimum wage revisions on record. The MCD conceded that the contractor's computation followed the formula in Clause 10C, which calculates escalation on a normative basis assuming 25% labour component. Since the calculation methodology was undisputed and based on official notifications, the court found no perversity or ground for interference with the award for escalation.

On Claim 5 (Loss of Profit): The court found merit in the MCD's challenge. It observed that the contractor's calculation was based on assumptions: a 10% profit margin without evidentiary support and the assumption that he would have secured another profitable contract during the delay period.

Citing the Supreme Court's judgment in Bharat Coking Coal Ltd. v. L.K. Ahuja , the High Court reiterated the principle that for awarding loss of profit due to prolongation, the contractor must establish that they could have utilized the time and resources elsewhere to earn profit.

The Court noted, "It is apparent from the above that the Arbitral Tribunal has awarded claim for loss of profit for the period the Contract was prolonged without any evidence or material to support the claim. Thus, the impugned award is vitiated by patent illegality."

The court concluded that in the absence of any evidence to support the profit margin or the lost opportunity to earn profit elsewhere, the Arbitral Tribunal's award for loss of profit was "vitiated by patent illegality."

Conclusion

Accordingly, the Delhi High Court upheld the Commercial Court's decision to the extent it sustained the arbitral award for escalation under Clause 10C (Claim 4). However, it set aside the award to the extent it granted damages for loss of profit on account of contract prolongation (Claim 5).

The appeal was disposed of on these terms, reinforcing the principle that claims for loss of profit in arbitration require concrete evidence of actual loss or lost opportunities, not merely theoretical calculations based on assumed profit margins and delay periods.

#ArbitrationLaw #ConstructionLaw #DisputeResolution #DelhiHighCourt

Breaking News

View All
SupremeToday Portrait Ad
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top