SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1996 Supreme(SC) 1524

1996(8) Supreme 222
SUPREME COURT OF INDIA
K. Ramaswamy and G.B. Pattanaik, JJ.
Gupta Steel Industries -Appellant
versus
M/s. Jolly Steel Industries Pvt. Ltd. & Anr. -Respondents
Civil Appeal Nos. 12995-13000 of 1996
(Arising out of SLP (C) Nos. 18321-26 of 1996)
with
CA Nos. 13001 -13005/96 @ SLP (C) No. 18933-18937/96
Decided on 23-9-1996
Counsel for the Parties :
For the Appellant : Bhimrao Naik, Sr. Advocate, and A.M. Khanwilkar, Advocates.
For the Respondents : Soli J. Sorabjee, Sr. Advocate, J.K. Das and J. Savla, Advocates.

IMPORTANT POINT
Consent decree can not be interfered with or modified by Court unless the parties agree for the same.

Headnote:CONSENT DECREE-Cannot be interfered with or modified except parties agree for the same-Appellants had agreed to hand over possession of suit land and respondents were to deposit certain amounts in the Court-default by respondent in deposit of amount by stipulated date-Status quo order by High Court-High Court passed order accepting delayed payment by respondents and directed appellants to pay damages for use and occupation as might be determined by civil Court-High Court was in correct in interfering with consent decree-Order however could not be disturbed at this distance of time-Directions issued. (Paras 5 & 6)

       

ORDER

Leave granted.

We have heard learned counsel on both sides.

2. These appeals by special leave arise from the order of the Division Bench of the High Court of Bombay made on July 18, 1996 in Civil Application Nos. 3588-89/91 in FA No. 1 & 2/90.

3. The admitted position is that pursuant to a compromise entered into between the parties, pending the first appeal in the High Court, a compromise decree came to be made by the Division Bench on 12.4.1991. Clause (2) of the Compromise Decree reads as under:

"2. (a) The parties agree that Jolly Steel Industries Pvt. Ltd. and Jolly Torsteel Pvt. Ltd., the respondents herein the Original Plaintiffs in Suit No. 446 of 1987 and Suit No. 447 of 1987, respectively, shall between them deposit in the Trial Court, a sum of Rs. 15,00,000/- (Rupees Fifteen Lakhs only) in the aggregate on or before 31st May, 1991 and a further sum of Rs. 10,40,000/- (Rupees Ten Lakhs and forty thousand only) on or before 29th June, 1991;

(b) These amounts are to be deposited in Suit No. 446 of 1987 in the Court of Additional Civil Judge, Senior Division, Pune, on account of over payment by the Appellants (Original Defendants) as the Defendants were not liable to pay and the Respondents (Original Plaintiffs) were not entitled to receive the same.

(c) The Appellants (Original Defendants) are at liberty to withdraw the aforesaid amounts."

4. Admittedly, Rs.12 lakhs was deposited after expiry of the last date, namely, June 29, 1991, after one month. In the meanwhile, the respondents filed an application for extension of time in the trial Court. That was dismissed on the ground that it had no jurisdiction. Consequently, the application came to be filed in the High Court. Similarly under Clause 5(a) the appellants also agreed to hand over possession of the disputed land and the machinery to the receiver on or before 31st March, 1992. In view of the default committed by the respondent, the appellants came to file an application, on the basis of which the High Court passed an order to maintain the status quo on March 27, 1992. The appellants have taken out contempt proceedings against the respondents in which another Division Bench of the High Court passed an order on July 18, 1996 stating that the respondents have prevented the appellants from taking possession due to the factory having been locked by the respondent. Nonetheless, no action was taken on the contempt petition. In the impugned order, the Division Bench passed an order accepting the delayed payment by the respondents and directed the appellants to pay damages for use and occupation as may be determined by the Civil Court. Thus, these appeals by special leave.

5. As principle of law, the High Court was obviously incorrect in interfering with and modifying the consent decree unless parties agree for the same. Though it is contended by Shri Bhimrao Naik, learned senior counsel for the appellants, that the High Court has no power after the expiry of the period to extend the time for the compliance on the facts and circumstances, we do not think that we would be justified to interfere with this order at this distance of time. However, as regards the direction to make payment of compensation, we do not think that it would be appropriate at this stage to give any finding; however, the trial Court is directed to conduct an enquiry whether the appellant was prevented by the acts of the respondents to remain in possession and work out the factory. In the event of the finding being recorded that the appellant was prevented by the acts of the respondent for working out the factory, the appellant will not be liable to pay damages whatsoever. On the other hand, if it is found that the appellant had worked out the factory in view of the fact that the High Court had granted the order of status quo, we think that they are liable to pay @ Rs. 2,500/- p.m.

6. It is stated by Mr. Soli J. Sorabjee, learned senior counsel for the respondents, that Rs. 12,00,000/- (Rupees Twelve lakhs




Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top