1997 Supreme(SC) 124

G.T.NANAVATI, K.RAMASWAMY
H. P. Nagar Vikas Pradhikaran – Appellant
Versus
Aggarwal And Company – Respondent


ORDER

Leave granted.

2. This appeal by special leave arises from the judgment and order dated May 2, 1996 of the Himachal Pradesh High Court passed in O.M.P. No. 626/93 in Ex. P. No. 27/1993. The admitted facts are that the respondent had entered into an agreement with the appellant to execute certain works pursuant to which there was a dispute which was referred to the Arbitrator, on directions of the High Court. The Arbitrator in the award dated April 25, 1992 stated as under:

"After considering whole matter submitted to me by both the parties, both verbally and in writing I have come to this conclusions that delay lies on the part of the respondent-Executive Engineer.

It is awarded that the plaintiffs shall be paid by the respondent-Executive Engineer an increase of 25% over and above their tendered rates for all works executed by them after the stipulated date of completion i.e. 21.5.89."

3. The award was made rule of the Court. In implementation of the award, the appellant worked out the details, as mentioned in the letter No.SDA (D)-Acctt-7/93-644-47 dated November 12, 1993 which reads as under :

"With reference to your letter No. AV/SIM/804-93-94 dated 5.10.1993, I am enclosing he
















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top