1998(5) Supreme 147
Supreme Court of India
K. Ramaswamy, Faizan Uddin and G.B. Pattanaik, JJ.
Supreme Co-operative Group Housing Society -Petitioner
versus
M/s. H.S. Nag & Associates (P) Ltd. -Respondent
Special Leave Petition (Civil) No. 11037 of 1996
Decided on 9-5-1996
Counsel for the Parties :
For the Petitioner : K. Madhava Reddy, Sr. Advocate, U.U. Lalit and Satish Vig, Advocates.
(ii) Delhi Co-operative Societies Act, 1972-Section 90-Arbitration Act, 1940-Section 20 -Notice required u/s. 90 of the Act, a precondition to lay the suit-Mandatory requirement of Section 90 does not get attracted to proceedings laid u/s. 20 of the Arbitration Act. (Para 3)
Order
This special leave petition arises from the order of the Division Bench of the High Court of Delhi made on 8.3.1996 in F.A.O. (OS) 44/96. The petitioner had entered into a contract on September 4, 1996 with the respondent with covenant contained therein as under :
“And whereas the contractor has also agreed to execute the work of seven towers with 100% external works with the said contract amount in the first instance and further work of the balance towers that would be entrusted to him within 4 months of the date of award of work at the same per sq. m. rates arrived at the above lamp sum price for each tower and for the alternate specifications.
And whereas the employer has accepted the offer of the contractor the said contract amount subject to the terms and conditions set forth herein and mutually agreed to by both the parties”
Therein clause 32 relates to settlement of dispute by arbitration which read as under:
“32. Settlement of Disputes by Arbitration:
If any dispute, question of controversy, the settlement of which is not herein specifically approved for, shall at any time arise between the owner and the contractor relating to this contract or any clause or thing contained or the construction thereof or any portion of the same or the rights or duties or liabilities of either party, then in every such cases the matter in dispute shall be referred to the Arbitration of the Hony. Director, owner or his nominee and his decision shall be final and binding on both the parties...........”
2. In furtherance of the agreement, apart from 7 towers entrusted for construction, the construction of 3 more towers was awarded on December 12, 1988 and 4 more towers on March 12, 1990. Dispute and differences had arisen in construction of the latter 7 towers. The respondent invoking clause 32 of the agreement filed application under Section 20 of the Arbitration Act, 1940 (for short, the ‘Act’) for calling upon the petitioner to produce the agreement and to have the dispute referred to arbitration. It was numbered as a suit on the original side of the High Court. Therein, the petitioner filed I.A. No. 7860 of 1994 in Suit No. 2760/93 under Order 7, Rule 11, CPC to dismiss the suit. Two grounds were mainly pressed for consideration in support thereof. The first contention urged was that the petitioner being a co-operative society registered under the Delhi Co-operative Societies Act, 1972, the dispute is arbitrable under Section 60 of that Act and Section 93 thereof puts an embargo on the power of the civil Court to decide the dispute and that, therefore, the, suit is not maintainable. The learned single Judge and the Division Bench negatived the contention and in our view rightly, on the ground that Section 60 of the Co-operative Societies Act would apply to a dispute among members, past-members or persons claiming through them or between them and the society or the members of the committee or officers or agents etc. as envisaged in clauses (a) to (d) of Section 60(1) of the Co-operative Societies Act. By operation of the non obstante clause, the bar of suit attracts only if the dispute falls within the parameters of clauses (a) to (d) thereof and the bar of jurisdiction of the Court under Section 93 gets attracted in respect of the specified subjects in sub-section (1) of Section 93 thereof. Therefore, the plea of the bar of Sections 60 and 93 is devoid of substance.
3. It is then contended in this Court that notice as required under Section 90, is a pre-condition to lay the suit. Since the proceedings under Section 20 of the Act was a suit, absence of notice meets with dismissal of the suit. We find no force in the contention. As per ratio in Kalyan Peoples’ Co-operative Bank Ltd. v. Dullhanbibi Aqual Aminsaheb Patil & Ors.3 prior to CPC 1976 Amendment Act, insistence upon a notice under Section 80 CPC in a suit under Order 21 Rule 63 renders no assistance to the petitioner. Even analogy of Section 80 CPC sought for in support of
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.