SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2003 Supreme(SC) 478

2003(3) Supreme 431
SUPREME COURT OF INDIA
(From Delhi High Court)
M.B. Shah & Arun Kumar, JJ.
Delhi Transport Corporation Ltd. -Appellant
versus
Rose Advertising -Respondent
Civil Appeal No. 105 of 2002
Decided on 17-4-2003
Counsel for the Parties :
For the Appellant : Raju Ramachandran, Additional Solicitor General, Ms. A. Subhashini, Advocate.
For the Respondent : Ms. Meenakshi Arora, Ms. Mona Chhetri and Anshul Singal, Advocates.

IMPORTANT POINT
By virtue of Section 85 of Arbitration and Conciliation Act, Arbitration Act, 1940 stood repealed but it is always open to parties to agree as to which law will continue to govern their relationship.

Headnote:(i) Arbitration and Conciliation Act, 1996-Section 85-Agreement between parties entered on 15.1.1993 regarding display of advertisements on body of appellant buses-Agreement contained arbitration clause-Disputes and difference arose-Petition under Section 20 of Old Arbitration Act filed by respondent on 16.1.1996-Petition became infructuous when counsel for appellant stated before Court on 19.7.1996 that arbitrator had already been appointed-Award made by arbitrator on 6.10.1998-Execution application for enforcement of award-Single Judge of High Court upheld objection regarding maintainability of execution under Act, 1996 and held that Act, 1940 continued to apply-Division bench set aside the judgment and held that case would be governed by 1996 Act-Appeal-It was open to parties to agree as to which law will continue to govern their relationship-Conduct of arbitration proceedings and participation of parties showed that parties acted under 1996 Act-Impugned judgment was unassailable. (Paras 4 and 5)

       (ii) Arbitration and Conciliation Act, 1996-Section 34-Arbitration award -Parties continued controversy on point whether old Act, 1940 applied or case was governed by 1996 Act-There was no occasion for appellant to apply for setting aside the award-Question whether time for making application for setting aside award could be extended will have to be decided when application was made-Question left open. (Paras 6 and 7)

       

JUDGMENT

Arun Kumar, J.-The main question for consideration in the present appeal is as to whether Arbitration Act, 1940 (hereinafter referred to "the old Act") would apply in the facts and circumstances of the case or the case will have to be dealt with under the Arbitration & Conciliation Act, 1996 (hereinafter referred to as "the 1996 Act").

2. Briefly the facts as gathered from the impugned judgment of the High Court are that the parties had entered into an agreement on 15.1.1993 regarding display of advertisements on the body of DTC buses. DTC is the Delhi Transport Corporation which runs the public road transport for commuters in the city and outskirts of Delhi. The agreement was for a period of 3 years commencing from 15.1.1993 upto 14.1.1996. The agreement contained an arbitration clause. Dispute and differences arose between the parties. A request was made by the contractor on 9.1.1995 for appointment of arbitrator to settle the disputes that had arisen between the parties. This was followed by another letter dated 26th November, 1995 containing similar request. On 16th January, 1996 the contractor filed in Court a petition under Section 20 of the old Arbitration Act. The notice of the petition was issued to the opposite party i.e. the appellant herein. The counsel appearing for the appellant made a statement in Court on 19th July, 1996 that an arbitrator had already been appointed on 4th July, 1996 as per the terms of the agreement. The petition thus became infructuous. The arbitrator conducted the arbitration proceedings and ultimately made an award on 6th October, 1998. To enforce the award the appellant filed an application under the 1996 Act which was registered as an Execution Application. The appellant DTC contested the said application on grounds including maintainability of the execution petition. The question of maintainability was raised on the basis that the 1996 Act was not applicable to the proceedings and therefore execution application did not lie. The contention of the appellant before the High Court was that the proceedings had commenced under the old Act and the said Act would continue to govern the proceedings. The learned Single Judge upheld the objection regarding maintainability of the application. It was held that the Arbitration Act 1940 continued to apply. This was based on the view that the arbitration proceedings commenced on the date when request for appointment of arbitrator was made and that was prior to the coming into force of the 1996 Act. Once the arbitration proceedings commenced, Section 85 of the 1996 Act read with Section 21 would lead to the conclusion that the old Act would continue to apply. Reliance was placed on the judgment of this Court in Thyssen Stahlunion GMBH vs. Steel Authority of India Ltd. [AIR 1999 SC 3923]. The contractor went in appeal against the said order of the learned Single Judge. The Division Bench noted in its judgment that the parties went for arbitration with clear understanding and belief that the proceedings were being conducted under the 1996 Act. It was noted that the appointment of arbitrator was made after the new Act had come into force and the parties participated in the arbitration proceeding with the understanding and belief that the proceedings are governed under the 1996 Act. In the award itself the arbitrator noted that "both the parties submitted claims before me under the Arbitration & Conciliation Act, 1996". He concluded the award by observing "I further award that the advertiser shall also be entitled for future interest at the rate of 18% p.a. on all payments awarded in accordance with Section 31 (7)(b) of the Arbitration & Conciliation Act, 1996 from the date of award till the date of payment. "

3. While referring to the judgment in Thyssen s case (supra) the Court noted that parties can always agree that provision of law prevailing at the relevant time would apply to arbitral proceedings. The case of Rani Construction Pvt. Ltd. decid







Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top