SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1987 Supreme(SC) 732

SABYASACHI MUKHARJI AND G.L. OZA, JJ.
Spl. Leave Petn. (Civil) No. 9524 of 1987, D/- 17-9-1987.
Municipal Corporation of Delhi, Petitioner
Versus
M/s. Jagan Nath Ashok Kumar and another, Respondents.

Advocates:
R.B.DATAR, RANJIT GHOSAL

Headnote:

Arbitration Act, 1940 - Section 20 - Constitution Of India, 1950 - Article 136 - Evidence Act, 1872 - Section 1 - Contract - Construction - Work Was Not Completed - Respondent No. 1 herein was awarded contract in question for construction of staff quarters for Municipal Corporation of Delhi, petitioner herein and work had to be completed within stipulated period mentioned in contract - Since, however, work was not being done in manner as Delhi Municipal Corporation thought it ought to have been done, petitioner wrote 29 letters during regarding timely completion of work - It is alleged that work was not completed as per schedule in contract - Show cause notice was given to respondent-contractor - Contractor failed to give satisfactory reply and according to petitioner, contract was rescinded - Thereafter several other letters were written which are not material to refer - There was an arbitration clause in agreement - An application was filed - Whether reasonableness of reasons in a speaking award is justiciable under Article 136 of Constitution - Whether in a particular contract time was essence of contract or not is a mixed question of law and fact – Held, In this case reasons given by arbitrator are cogent and based on materials on record - In Strouds Judicial Dictionary, Fourth Edition, page 2258 states that it would be unreasonable to expect an exact definition of word "reasonable. Reason varies in its conclusions according to idiosyncrasy of individual, and times and circumstances in which he thinks - Reasoning which built up old scholastic logic sounds now like jingling of a childs toy - But mankind must be satisfied with reasonableness within reach; and in cases not covered by authority, verdict of a jury or decision of a judge sitting as a jury usually determines what is "reasonable" in each particular case - After all an arbitrator as a Judge in the words of Benjamin N. Cardozo, has to exercise a discretion informed by tradition, methodized by analogy, disciplined by system, and subordinated to "the primordial necessity of order in social life – Appeal Dismissed.

Judgement

SABYASACHI MUKHARJI, J.:- The respondent No. 1 herein was awarded the contract in question for the construction of staff quarters for the Municipal Corporation of Delhi, the petitioner herein and the work had to be completed within the stipulated period mentioned in the contract. Since, however, the work was not being done in the manner as the Delhi Municipal Corporation thought it ought to have been done, the petitioner wrote 29 letters during June, 1978 to July, 1980 regarding the timely completion of the work. It is alleged that the work was not completed by the 15th of January, 1980 as per the schedule in the contract. Show cause notice was given to the respondent-contractor. The contractor failed to give satisfactory reply and according to the petitioner, the contract was rescinded. Thereafter several other letters were written which are not material to refer. There was an arbitration clause in the agreement. On 2nd November, 1982 an application was filed under section 20 of the Arbitration Act, 1940 (hereinafter called the Act) in the Delhi High Court. A learned single Judge, of the said High Court directed reference of the dispute and directed the Commissioner of the Municipal Corporation or anyone nominated by him to enter into reference. The Commissioner on 17th of March, 1983 appointed one Shri S. M. Hasnain, Arbitrator and Superintending Engineer No. II, of the Municipal Corporation of Delhi as the arbitrator. He is respondent No. 2 in this petition. The said arbitrator entered upon the reference and thereafter on 21st of August, 1984 submitted his award allowing some claims of the contractor and some counterclaims of the Municipal Corporation. The Municipal Corporation filed its objections to the said award. The learned single Judge of the High Court by his judgment and order dated 22nd of October, 1986 directed that the award be made a rule of the Court. A Letters Patent Appeal was filed thereafter but the same was summarily dismissed by a Division Bench of the Delhi High Court on 25th May, 1987. The petitioner seeks leave in this petition under Article 136 of the Constitution to challenge the said order. As the learned Division Bench did not give reasons, we must refer to the order of the learned single Judge.

2. The arbitrator gave reasons in support of the award, The question is whether reasonableness of the reasons in a speaking award is justiciable under Article 136 of the Constitution. We are of the opinion that such reasonableness of the reasons given by an arbitrator in making his award cannot be challenged in a proceeding like the present. It is desirable, however, that we state our reasons for so holding.

3. In order to appreciate this the award of the arbitrator must be looked into. The arbitrator in his award has dealt with various claims, one of the main claims was the claim of Rs. 23,850/- out of which Rs. 8,300/- was in the form of fixed deposit receipt carrying interest and the balance amount of Rs. 15,520/- was deducted as security of 10% from the bills of the claimant. According to the claimant this amount had wrongly been forfeited by the Corporation at the time of rescission of the contract and that the same should be refunded to him. It was held by the arbitrator that there was provision in the agreement for extension of time for completion of the contract, as well as for levy of compensation for delay. Therefore, it could not be taken that time was the essence of the contract. The arbitrator had opined that according to the respondents own admission there was delay of nearly four months in the commencement of the work due to giving of the layout etc. There was also delay in the execution of sanitary work by another contractor previously employed by the petitioner and this work was still incomplete at the time of the making of the award and as such complete site had not been made available to the present contractor in time. Further there was provision in the agreement for extension of t









Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top