SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1995 Supreme(SC) 1128

SUPREME COURT OF INDIA
G.B.Pattanaik : S.C.Agrawal
State Of U.P.
Versus
Ram Nath International Construction Private Limited
Case No. : .
Date of Decision : 11/10/95
Advocates Appeared: Agarwala Pramod B. : Agarwala Satish : Mishra R.B. : Roy M.K. : Sanghi G.L. : Sehgal D.V. : Tripathi Nalin

Advocates:
D.V.Sehgal, G.L.SANGHI, M.K.ROY, NALIN TRIPATHI, PRAMOD AGARWAL, R.B.MISHRA, SATISH AGGARWAL

Headnote:

Arbitration Act - Section 39 - Contractor had entered into an agreement - Held to be without jurisdiction - Arising out of an arbitration proceeding - According to respondent-contractor, on account of substantial change in designs and drawings there has been abnormal increase in the quantity of work compared to the estimated quantity of work in the original agreement and in respect of such additional quantity of work he is not bound to be paid at the agreed rate but at an enhanced rate on the basis of the analysis of rate submitted by him - It was further averred that when the drawings and designs were changed, the contractor had resisted and prayed for alteration in the rate but the authorities concerned had assured him orally for such change though ultimately did not agree to the same - It was also averred in the claim petition that under the agreement he was bound to carry out the work as per the directions of the authorities concerned and accordingly he has carried out the same – Held, Unfortunately, this position has been lost sight of by the arbitrator as well as by the subordinate Judge and the High Court possibly because this has not been brought to notice by State learned counsel appearing for the respondent on instruction from his client does not dispute the position that subsequent in respect of the quantity of work executed by the contractor, he has been paid at an escalated rate on the basis of calculation made in accordance with the escalation clause in agreement - This being the position, we would have ordinarily set aside the award of the arbitrator and remitted the matter for recalculation. But in the course of hearing learned counsel appearing for the respondent, submitted that the matter may be decided by this court since a considerable period has lapsed in the meantime and did not dispute the calculation-sheet that was filed by learned counsel appearing for the State, as well as the affidavit of Executive Engineer Construction Division. In the same affidavit after making necessary adjustments of payment, made at the escalated rate, it has been stated that the contractor would be entitled to the amount in respect of Item for the extra work executed and a sum respect of extra quantity of work for Item 15 for the period and thus in all the claimant-contractor would be entitled in respect of the extra quantity of work executed by him for the period - Since the calculation made in this affidavit is not disputed and in view of the submission made by appearing for the claimant-contractor, we modify the award of the arbitrator and direct that claimant would be entitled to an additional in respect of the work executed by him up – Appeal allowed

Judgment

G.B.PATTANAIK, J.

(1) THIS appeal is directed against the judgment of the Allahabad High court dated 16/12/1993 in First Appeal from Order No. 930 of 1991, arising out of an arbitration proceeding.

(2) THE respondent-contractor had entered into an agreement with the appellant for construction of non-overflow and overflow S. with bridge spillway and other appurtenant works of Maudaha Dam in Hamirpur District in the State of Uttar Pradesh. The agreement was entered into on 26/8/1985 and work commenced from 1/9/1985. The period stipulated for completion of the work was 42 months. In the year 1987 in respect of two items of work namely Items 13 and 15, it is alleged that the appellant changed the designs and drawings as a result of which the quantity of work became abnormally high compared to the estimated quantity of work in the agreement. On account of such abnormal increase of the quantity of work the contractor claimed higher rate than what was agreed to in the agreement. The State having refused to accede to the contractors demand and disputes having arisen between the parties, the arbitration clause of the agreement was invoked and dispute was referred to the sole arbitration of the Joint secretary and Joint Legal Remembrancer to the government of Uttar Pradesh. Before the arbitrator the respondent-contractor made a claim of Rs. 91,56,750.00 for the increased quantity of work in respect of Item 13 executed till 30/4/1990 and Rs. 9,92,402.50 for the increased quantity of work in respect of Item 15 executed till 30/4/1990 together with interest @ 10% thereon. The entire basis of the claim of the contractor was that in respect of the quantity of work in excess of the estimated quantity in the agreement he is entitled to be paid @ Rs. 453.50 per cubic metre in place of the agreed rate of Rs. 243.00 for Item 13 and the rate of Rs. 739.55 per cubic metre in place of agreed rate of Rs. 460.00 for Item 15. It was alleged in the claim petition that the State of Uttar Pradesh has paid and is paying the agreed rate of Rs. 243.00 per cubic metre in respect of the additional quantity of work in Item 13 and similarly has paid and is paying @ 460.00 per cubic metre even in respect of the additional quantity of work in respect of Item 15. According to the respondent-contractor, on account of substantial change in designs and drawings there has been abnormal increase in the quantity of work compared to the estimated quantity of work in the original agreement and in respect of such additional quantity of work he is not bound to be paid at the agreed rate but at an enhanced rate on the basis of the analysis of rate submitted by him. It was further averred that when the drawings and designs were changed, the contractor had resisted and prayed for the alteration in the rate but the authorities concerned had assured him orally for such change though ultimately did not agree to the same. It was also averred in the claim petition that under the agreement he was bound to carry out the work as per the directions of the authorities concerned and accordingly he has carried out the same.

(3) THE appellant-State filed written statement before the arbitrator denying its liability to pay at the revised rate as claimed by the contractor. It was admitted that there has been a change in the drawings and designs relating to Items 13 and 15 and on account of such change, the quantity of work in respect of the aforesaid two items has increased. But the claimant is not entitled to any enhanced rate, in view of the different clauses of the agreement itself. It was also averred in the written statement that the so- called variation in the quantity of work is covered by clauses 11.25 and 13.11 of the agreement and therefore the contractor is not entitled to any higher rate.

(4) THE learned arbitrator after analysing the different clauses of the agreement, came to the conclusion that the contractor could not have






Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top