SUPREME COURT OF INDIA
G.N.Ray : S.B.Majmudar
Surendra Kumar Jain Alias Sunni
Versus
Shanti Swaroop Jain
Case No. : .
Date of Decision : 7/24/95
Advocates Appeared: Jain P.K. : Jain Praveen : Rohatgi K.B. : Rohtagi Avadh Behari : Rohtagi K.B. : Sharma Rakesh K. : Sibal Kapil : Singhvi A.M.
U.P. Urban Buildings Act, 1972 - Section 2 – Tenant – Claim of compensation - . In the Explanation to the said section it has been indicated that the construction of a building shall be deemed to have been completed on date on which completion thereof is reported or otherwise recorded by local authority having jurisdiction and in the case of building subject to assessment date on which first assessment thereof comes into effect and where the said dates are different, the earliest of the said dates and in the absence of any such report record or assessment date on which it is actually occupied (not merely for the purpose of supervising the construction or granting the building under construction for the first time – Held, IT, therefore, appears that in terms of Explanation l construction is deemed to have been completed on the date on which the completion thereof is reported to or otherwise recorded by the local authority having jurisdiction if such reporting or recording happens to be on the earliest point of time various dates referred to hereinbefore. It is contended that in the instant case, the Municipal Authority having given notice for assessment such date should be held to be the date when the Municipal Authority had already taken note of construction of the building. Since that date is the earliest of the dates as referred to in Explanation l(a), that date becomes relevant for purpose of considering deemed date of construction. It 0 does not appear that such consideration has been made by High court in deciding case - High court has proceeded on the footing only on the basis of the assessment effected in 1981 - Learned counsel for the respondent has relied on a decision of this court in 0m But it appears to us that in that case, there was no question of Municipal Authority having taken note of construction on an earlier date for the purpose of giving notice for assessment. Hence, that decision is not applicable for purpose of deciding the issue raised in this case. We, therefore, set aside the impugned decision of the High court and remit the case back to High court for disposal on merits in the light of above discussion preferably within a period of four months from the date of receipt of the order of this court. The High court will decide as to which is the earliest date of deemed construction in terms of date Explanation l(a) of Ss. (2 of Section 2 of the said Act for the purpose of deciding the dispute involved in the case. Until the matter is disposed of by the High court, there will be stay of eviction from the disputed premises – Appeal disposed of
(1) LEAVE granted.
(2) RESPONDENT 1 has already entered appearance. Notice of the appeal need not be served on Respondents 2 and 3 who are formal parties and such notice on them is dispensed with.
(3) HEARD learned counsel for the parties. It appears to us that for the purpose of deciding the date of construction it is necessary to refer to Explanation l(a) of Section 2(2 of the U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972. In the Explanation to the said section it has been indicated that the construction of a building shall be deemed to have been completed on the date on which completion thereof is reported or otherwise recorded by local authority having jurisdiction and in the case of building subject to assessment, the date on which the first assessment thereof comes into effect and where the said dates are different, the earliest of the said dates and in the absence of any such report record or assessment, the date on which it is actually occupied (not merely for the purpose of supervising the construction or granting the building under construction) for the first time.
(4) IT, therefore, appears that in terms of Explanation l(a) the construction is deemed to have been completed on the date on which the completion thereof is reported to or otherwise recorded by the local authority having jurisdiction if such reporting or recording happens to be on the earliest point of time vis-a-vis various dates referred to hereinbefore. It is contended that in the instant case, the Municipal Authority having given notice for assessment on 15/11/1977 such date should be held to be the date when the Municipal Authority had already taken note of the construction of the building. Since that date is the earliest of the dates as referred to in Explanation l(a), that date becomes relevant for the purpose of considering deemed date of construction. It 0 does not appear that such consideration has been made by the High court in deciding the case. The High court has proceeded on the footing only on the basis of the assessment effected in 1981. The learned counsel for the respondent has relied on a decision of this court in 0m Prakash Gupta v. Dig Vijendrapal Gupta But it appears to us that in that case, there was no question of Municipal Authority having taken note of construction on an earlier date for the purpose of giving notice for assessment. Hence, that decision is not applicable for the purpose of deciding the issue raised in this case. We, therefore, set aside the impugned decision of the High court and remit the case back to the High court for disposal on merits in the light of above discussion preferably within a period of four months from the date of receipt of the order of this court. The High court will decide as to which is the earliest date of deemed construction in terms of date Explanation l(a) of Ss. (2 of Section 2 of the said Act for the purpose of deciding the dispute involved in the case. Until the matter is disposed of by the High court, there will be stay of eviction from the disputed premises.
(5) THE appeal is accordingly disposed of without any order as to costs.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.