Ashok.Paper Mills Kamgar Union
Versus
Union Of India
Case No. : 13 , 174 of 1991
Date of Decision : 4/26/99

The court held that a State failing its obligation to provide power for a factory's rehabilitation must guarantee alternative power sources. Additionally, an agreement signed by one registered union is valid for scheme implementation, provided other unions are given an opportunity to join on identical terms.

Headnote:(A) Rehabilitation Scheme - Implementation - Power Supply - State Obligation - Where a State has undertaken the responsibility of providing uninterrupted power supply for the rehabilitation of a factory and fails to do so, and the financial institution refuses to allow diversion of term loans for alternative power sources, the State may be directed to stand as a guarantor for the purchase of generating sets to ensure the factory's operation and protect the interests of the workforce. (Para 1)

(B) Labour Unions - Tripartite Agreement - Validity - If a registered union has entered into an agreement for the implementation of a rehabilitation scheme, such agreement is valid, even if another union has resiled or failed to enter into the agreement, provided the latter is given a reasonable opportunity to join on the same terms. (Para 2)

Facts of the case:
A rehabilitation scheme for a factory was finalized by the Court. Implementation was delayed due to the State's failure to provide uninterrupted power and a dispute over which registered labour union should sign the tripartite agreement. The financial institution refused to divert sanctioned loans for the purchase of diesel generators required for power supply.

Findings of Court:
The State is directed to stand as a guarantor for the purchase of four diesel generating sets to the tune of three crores. Regarding the labour dispute, the agreement signed by one registered union is held valid, but the other union is granted four weeks to enter into an agreement on the same terms. If the other union fails to do so, individual members may abide by the existing agreement.

Issues: Whether the State should provide a guarantee for alternative power sources following its failure to supply power, and whether an agreement signed by one registered union is sufficient for the implementation of the rehabilitation scheme.

Ratio Decidendi: The State's failure to discharge its obligation to provide power necessitates it acting as a guarantor for alternative arrangements to ensure the factory remains operational. A registered union's agreement is valid for scheme implementation, but equity requires offering other unions the chance to adhere to the same terms within a specified period.

Result: Directions issued for the State to provide a guarantee and for the labour unions to finalize agreements.

Legal Category Hierarchy

  • industrial law
    • rehabilitation schemes
      • implementation obligations (Para 1)
    • labour relations
      • tripartite agreements (Para 2, 3)
  • practice and procedure
    • impleadment (Para 5)

Table of Contents

1. Rehabilitation scheme implementation — failure of state to provide power supply — dispute over validity of tripartite agreement signed by a registered labor union. (Para 1 , 2 )

2. State's failure to provide power versus funding for generators — validity of tripartite agreement signed by one registered union over another. (Para 1 , 2 )

3. State's failure to fulfill power obligations justifies requiring it to guarantee alternative power sources; agreement by a registered union is valid for scheme implementation. (Para 1 , 2 )

4. State failure to discharge obligations under a rehabilitation scheme may necessitate providing guarantees for alternative solutions; agreements by registered unions are valid for scheme implementation. (Para 1 , 2 )

5. State directed to guarantee power generating sets; agreement by registered union held valid; other union granted time to join. (Para 1 , 2 , 3 )

6. Can a state be required to provide a guarantee for alternative infrastructure if it fails to fulfill a specific obligation under a rehabilitation scheme?

Yes, if the state fails to discharge its obligation, such as providing uninterrupted power, which hinders the implementation of a rehabilitation scheme, the court may direct the state to stand as a guarantor for alternative solutions to obviate the difficulty. (Para 1 )

7. Is a tripartite agreement signed by one registered union valid for the implementation of a scheme if another union refuses to sign?

Yes, if a registered union has entered into the agreement, it is considered a valid agreement for the purpose of implementing the scheme, although other unions may be given an opportunity to join on the same terms. (Para 2 )

(1) THE scheme of rehabilitation of Ashok paper Mills in Darbhanga in the State of Bihar was finalised by this Court after prolonged negotiations by order dated July 6, 1996. More than two and a half years have elapsed, yet the implementation has not been possible for one reason or the other and the parties required to implement the scheme are putting forth blame on one side or the other. This Court had called upon by order dated July 8, 1996 to file a status report indicating what all has happened in the matter of implementation of the scheme and pursuant to the aforesaid order, the Secretary, Government of India, Department of Industrial Policy and Promotion in the Ministry of Industry has filed a status report. The said report indicates that the main obstacle in implementing the scheme by way of running the factory is the supply of power. Under the scheme, the State of Bihar had taken the responsibility of supplying uninterrupted power obviously in the interest of the hundreds of labourers who would have otherwise been disengaged if the factory would have come to a closure. From the status report it transpires that the State is not in a position to supply uninterrupted power to the factory and, therefore, it was suggested that the alternative method of installing four diesel generating sets of 1000 KVA each should be adopted by the entrepreneur NCFL for getting the power in question. The Company wanted to utilise the term loan that was sanctioned by IDBI under the scheme but IDBI does not agree to any part of the term loan being utilised for this purpose as there would be a deviation of the scheme itself. Since the State of Bihar had undertaken the responsibility of continuous power supply to the Company and it has failed to discharge its obligation, we think that the State of Bihar should stand as a guarantor to the Company on whose guarantee the four diesel generating sets of 1000 KVA can be purchased for getting uninterrupted power supply. On query to Mr. K.K. Venugopal, learned senior Counsel appearing on behalf of the Company he states that the approximate cost of these four diesel generating sets would be three crores. In the circumstances, we direct that the State of Bihar would stand guarantee for the supply of the aforesaid four diesel generating sets to the tune of three crores so that the difficulty in getting the power supply will stand obviated. The Company should give immediate proposal to the State of Bihar in this regard and on getting the said proposal, within three weeks from the receipt of the proposal appropriate orders may be passed by the State of Bihar for standing guarantee to the tune of rupees three crores to meet the costs of the four diesel generating sets.

(2) THE further dispute is with regard to the labour union who were under the scheme required to sign the tripartite agreement. Under the scheme in question Ashok Paper Mills Kamgar Union was to enter into an agreement An on behalf of the labourers. From the status report as well as other documents presented before us in this proceeding it appears that the President of the said Kamgar Union though initially had participated in deliberations but later on resiled from entering into an agreement. According to Mr. Rakesh Dwivedi, learned senior Counsel appearing for the said Union, the Union was all along prepared to enter into the agreement but it is the manoeuvring of the Management which prevented them from entering into an agreement and the agreement has been entered into by another registered union, namely Ashok Paper Mills Mazdoor Panchayat Union which is represented by Mr. Mishra in this Court. Without delving into the question as to whether the Kamgar Union itself did not participate in the proceedings and did not enter into an agreement or the Union was prevented by some other process since a registered union has already entered into an agreement and that such Union has a membership of 243, we think it appropriate to hold