1999 Supreme(SC) 733

SUPREME COURT OF INDIA
A.P.Misra : Sujata V.Manohar : U.C.Banerjee
Karnataka State Coop.Apex Bank Limited
Versus
Y.S.Shetty
Case No. : 16699 , 16712 of 1996
Date of Decision : 7/22/99

Whether a claim subsists after the completion of work and receipt of payment as 'full and final settlement' is an arbitrable dispute to be decided by the arbitrator.

Headnote:(A) Arbitration Act - Section 33 - Full and final settlement - Whether a claim subsists after the completion of work and receipt of payment as full and final settlement is a matter to be decided by the arbitrator. (Para 1)

(B) Arbitrability - Questions regarding whether a contract has been fully worked out and whether payments constitute a full and final settlement are questions to be considered by the arbitrator when there is a dispute regarding the same. (Para 1)

Facts of the case:
Certain civil works were carried out under two tenders. The party performing the work received a payment which was acknowledged as full and final settlement. Subsequently, the party claimed that outstanding dues remained and sought arbitration. An application was filed seeking a declaration that the agreement no longer subsisted as the work was completed and payment had been received in full and final settlement.

Findings of Court:
The court found that whether any amount is due to be paid and how far the claim made is tenable are matters to be considered by the arbitrator.

Issues: Whether the question of whether a contract has been fully worked out and whether payments made constitute a full and final settlement is a matter to be decided by the arbitrator.

Ratio Decidendi: The court ruled that on completion of work and settlement of the final bill, while the right to further payment may be weakened, the question of whether the claim subsists or not remains a matter which is arbitrable.

Result: Appeal allowed.

Legal Category Hierarchy

  • practice and procedure
    • arbitration
      • arbitrability of disputes (Para 1)
      • full and final settlement (Para 1)

Table of Contents

1. Civil works contract — Dispute over full and final settlement — Claim for outstanding dues — Reference to arbitration under agreement clause. (Para 1 )

2. Whether the arbitration agreement subsists after completion of work and receipt of payment in full and final settlement — Applicability of arbitration clause. (Para 1 )

3. Whether a claim subsists after settlement of the final bill is an arbitrable matter; questions of full settlement are for the arbitrator to decide. (Para 1 )

4. Disputes regarding whether a contract is fully worked out or whether payments constitute full and final settlement are matters to be determined by the arbitrator. (Para 1 )

5. Appeal allowed — High Court order set aside — Application under Section 33 of the Arbitration Act dismissed — Arbitration proceedings to continue. (Para 1 , 2 )

6. Is the question of whether a payment constitutes a full and final settlement arbitrable?

Yes, whether a contract has been fully worked out and whether payments made are in full and final settlement are questions to be considered by the arbitrator when a dispute exists regarding the same. (Para 1 )

7. Does the completion of work and settlement of the final bill extinguish the right to seek arbitration for further claims?

While the right to further payment normally weakens after the settlement of the final bill upon completion of work, whether the claim actually subsists remains a matter that is arbitrable. (Para 1 )

(1) THE appellant offered Tenders I and II to the respondents, pursuant to which certain civil works were carried out and in respect of which they made a claim for payment of money. Although several claims had been made by the appellant, ultimately on 6-2-1989, the respondents intimated the appellant to receive a cheque for a sum of Rs 2,79,600 in full and final settlement of the works relating to Tenders I and II. The appellant acknowledged the same by endorsing on the said letter stating that he had received the said amount as full and final settlement and he had no further claim in that regard. Thereafter, he wrote a letter dated 24-2-1989 stating that his statement that payment had been accepted by him on 6-2-1989 in full and final settlement is not correct and still there are outstanding dues which need to be paid otherwise the matter will have to be referred to arbitration in terms of clause 37 of the agreement. Pursuant to the said notice each of the parties nominated their respective arbitrators. At that stage, an application was filed under Section 33 of the Arbitration Act seeking a declaration that the agreement dated 7-4-1981 between the parties no longer subsists as the work has already been completed and the payment was received by Respondent 1 in full and final settlement. It was also contended that the clause providing for reference of disputes to arbitration is not attracted in such a situation. In an identical situation, this Court in Union of India v. L.K. Ahuja & Co. held that on completion of work, the right to get money would normally arise thereafter on settlement of the final bill, the right to get further payment gets weakened but whether the claim subsists or not, is a matter which is arbitrable. When this direction was cited before the High Court, the same was distinguished by stating that it was a decision on its own facts and has no application to the case. We find that this view does not appear to be correct. Whether any amount is due to be paid and how far the claim made by the appellant is tenable are matters to be considered by the arbitrator. In fact, whether the contract has been fully worked out and whether the payments have been made in full and final settlement are questions to be considered by the arbitrator when there is a dispute regarding the same. We, therefore, set aside the order made by the High Court and dismiss the application filed under Section 33 of the Arbitration Act. Now proceedings before the arbitrator/s will have to be continued in accordance with law.

(2) THE appeal is allowed. No costs.