SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1995 Supreme(SC) 948

SUPREME COURT OF INDIA
PARIPOORNAN, JJ
LARSEN and TOUBRO LIMITED
Vs.
MAHARASHTRA STATE ELECTRICITY BOARD
Decided on September 13, 1995

Advocates:
A.S.BHASME, B.M.Naik, BHARAT SANGAL, HARISH N.SLAVE, V.B.Trivedi

Headnote:

Arbitration Act – Section 41 – Appellant, petitioner in arbitration petition Lodg in the High Court of Judicature at Bombay, initiated, has filed this appeal by special leave against the order passed – Appellants prayer for injunction against the first respondent (Maharashtra State Electricity Board) from invoking or claiming or demanding or releasing any amount whatsoever under certain bank guarantees given by the respondent was dismissed by the aforesaid order by the learned Judge – Respondent in the arbitration petition Lodg as also in this appeal are - (1) Maharashtra State Electricity Board, Bombay; (2) Standard Chartered Bank, branch Bombay; (3), branch Bombay; (4) City Bank, N. A. branch Bombay; and (5) Bank of Baroda, branch Bombay –Held, There is no force in the above pleas. It is common ground that the arbitration proceeding for resolving the dispute between the parties (appellant and the respondent) is pending before the Arbitrator – Parties are at issue as to whether the Plant was completed in time or was delayed –They are blaming each other for the delay – That is a matter to be adjudicated in the proceedings – It is also brought to our notice that the first respondent has claimed liquidated damages as per Clause 75. 01 of the contract of more than eight crores - much more than the amount guaranteed – Since the decision in the arbitration proceedings has an impact on this aspect, court are of the view that no prima facie case of fraud of irretrievable injustice is made out to restrain respondents 1 and 5 from invoking the Bank Guarantee – Plea that the invocation was not in proper time is also without substance.

( 1 ) LEAVE granted.

( 2 ) THE appellant, petitioner in arbitration petition Lodg. No. 240/94 in the High Court of Judicature at Bombay, initiated under Section 41 of the Arbitration Act, has filed this appeal by special leave against the order passed by N. D. Vyas, J. dated 20-10-1994. The appellants prayer for injunction against the first respondent (Maharashtra State Electricity Board) from invoking or claiming or demanding or releasing any amount whatsoever under certain bank guarantees given by the respondent Nos. 2 to 5 was dismissed by the aforesaid order by the learned Judge. Respondent Nos. 1 to 5 in the arbitration petition Lodg. No. 240/94 as also in this appeal are - (1) Maharashtra State Electricity Board, Bombay; (2) Standard Chartered Bank, branch Bombay; (3) Grindlays Bank p. l. c. , branch Bombay; (4) City Bank, N. A. branch Bombay; and (5) Bank of Baroda, branch Bombay.

( 3 ) THE first respondent invited tenders for supply and commission of Coal Handling Plant. The appellants tender, which was accepted, culminated in a contract, executed between the parties, dated 9-3-1989. The value of the contract was Rs. 61,11,200. 00. The appellant furnished the following five Bank Guarantees;

THE completion of the Plant seems to have been delayed. The parties are blaming each other for the delay. After taking the trial and performance test, the Plant was taken over by the first respondent on 10-6-1994. On the same day a take over certificate was also issued. It is seen that earlier on 29-3-1994, the appellant lodged its claim. The first respondent denied the claims so made. They did not make any counter-claim then. On 4-6-1994, the appellant invoked the arbitration clause as per the contract. A meeting of the Arbitrators took place on 14-9-1994. The Arbitrators gave certain directions. In pursuance thereto the appellant filed its claim on 30-9-1994. The Arbitrators gave time to the first respondent to file their counter-claim on or before 30-11-1994. In the meanwhile on 1-10-1994 the first respondent invoked all the Bank Guarantees except Guarantee No. 2 mentioned hereinabove (Performance Guarantee ). The Court passed an order directing the status quo to be maintained on 17-10-1994. Appellant filed arbitration petition Lodg. No. 240/94 and contended that the Bank Guarantees have been fraudulently and dishonestly invoked. Regarding Guarantees in respect of advance and liquidated damages, it was further alleged that they were invoked after the date of expiry of the said Guarantees. Vyas, J. rejected the above pleas and declined to grant the interim relief as prayed for by the appellant. As agreed to by counsel on both sides, the interim order was made the order in the main petition itself. Arbitration Petition Lodg. No. 240/94 was dismissed. Hence this appeal by special leave.

( 4 ) BANK of Baroda, Respondent No. 573/309security against liquidated damage6,13,40,97826-9-94

( 5 ) STANDARD Chartered Bank, Respondent No. 2529/93/380partial release of retention money1,12,00,00031-12-94

( 6 ) IN the order appealed against the learned Judge has referred to the decisions aforesaid and has held thus:-

". . . Only in the event of fraud or irretrievable injustice, the Court would be entitled to interfere in a transaction involving a bank guarantee and under no other circumstances. The petitioners have failed on both these counts".

(PAPER Book - Vol. I. p. 7)

( 7 ) APPELLANTs counsel contended that the Bank Guarantees have been fraudulently and dishonestly invoked by the first respondent. It was submitted that so far as the Bank Guarantee towards advance was concerned, no amount remains as balance towards advance and in fact a sum of Rs. 27,000. 00 is recoverable from the first respondent. With regard to the two Bank Guarantees, dealing with retention money (Item Nos. 3 and 5) it was contended that the trial was taken by the first respondent after which performance test was also done and thereafter the take over was completed and so, on th
























Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top