SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2006 Supreme(SC) 162

2006(2) Supreme 392
Supreme Court of India
(From Andhra Pradesh High Court)
Arijit Pasayat and R.V. Raveendran, JJ.
A.P.S.R.T.C. & Ors. —Appellants
versus
G. Srinivas Reddy & Ors. —Respondents
Civil Appeal No. 3424 of 2000
Decided on 24-2-2006
Counsel for the Parties :
For the Appellants : R. Santhan Krishnan, Praveen Kr. Pandey and Guntur Prabhakar, Advocates.
For the Respondents : T.N. Rao, Advocate.

Important pointWhere contract labour are engaged in connection with work in an establishment and employment of such contract labour is prohibited by issue of a notification u/s 10(1) of Contract Labour (Regulation and Abolition) Act, there is no automatic absorption of contract labour.

Headnote:(i) Labour Law—Contract Labour (Regulation and Abolition) Act, 1970—Section 10(1)—Circular issued by appellant for absorption of persons employed on casual basis/consolidated pay/piecemeal rate whose services had been ordered to be dispensed with, under earlier Circular—Circular provided that benefit thereof will not extend to persons engaged by contractors—Writ petition by respondents claiming to be scavengers employed by Corporation sought direction for regularisation—High Court disposed of writ directing authority to consider cases of respondents—Authority passed order holding that respondent worked only under a contractor and was not entitled to absorption—Order was set aside by Single Judge in writ holding that Corporation could not reject the claim by taking stand that respondents were employed as contract labour and circular was inapplicable—Division Bench dismissed appeal holding that work for which respondents were employed as contract labour was perennial in nature and not seasonal—Appeal—There was no notification u/s 10(1) of CLRA Act prohibiting contract labour—No contention nor a finding that contract was sham and nominal—In view of principles laid down in Steel Authority case, High Court could not have directed absorption of respondents who were held to be contract labour by assuming that contract labour was only a camouflage—Only remedy of respondents was to approach Industrial Tribunal for declaring that contract labour system was camouflage and they were direct employees of Corporation—Impugned order was liable to be set aside.

       Held : In this case, there was no notification under section 10(1) of CLRA Act, prohibiting contract labour. There was also neither a contention nor a finding that the contract with the contractor was sham and nominal and the contract labour working in the establishment were, in fact, employees of the principal employer himself. In view of the principles laid down in Steel Authority, the High Court could not have directed absorption of respondents who were held to be contract labour, by assuming that the contract labour system was only a camouflage and that there was a direct relationship of employer and employee between the corporation and the respondents. If respondents want the relief of absorption, they will have to approach the Industrial Tribunal/Court and establish that the contract labour system was only a ruse/camouflage to avoid labour law benefits to them. The High Court could not, in exercise of its jurisdiction under Article 226, direct absorption of respondents, on the ground that work for which respondents were engaged as contract labour, was perennial in nature. The respondents were not also entitled to the relief of absorption/regularization on the basis of the Circular dated 1.9.1988, as it specifically excluded contract labour. The order dated 5.11.1991 in the first round (WP No. 14353/1991) and the order dated 17.3.1998 in the second round (W.P. No. 30220/1997) did not examine the status of the respondents, nor recorded a finding that they were entitled to absorption. They merely disposed of the writ petitions with a direction to consider the representation/claim of the respondents for absorption. Therefore, if the Corporation on considering the claims of respondents found that they were not employed by the Corporation, but were contract labour, who were not entitled to seek absorption under the Circular dated 1.9.1988, the Corporation was justified in rejecting their claim for absorption. The only remedy of respondents, as noticed above, is to approach the Industrial Tribunal for declaring that the contract labour system under which they were employed was a camouflage and therefore, they were, in fact, direct employees of the Corporation and for consequential relief. (Paras 10 and 11)

       We find that at that stage, the authority considered the case of the third respondent and passed a reasoned order dated 21.4.1999 rejecting the claim on the ground that the third respondent was not a direct employee, but was a contract labour, and was not therefore entitled to absorption under the Circular dated 1.9.1988. This led to the third round of litigation in W.P. No. 17678/1999 wherein the prayer was for quashing the said order or rejection dated 21.4.1999 and for direction to absorb them into service in terms of the Circular dated 1.9.1988. Again, the High Court at the admission stage, disposed of the matter on an erroneous conclusion that the order dated 21.4.1999 was contrary to the decision in the second round (Order dated 17.3.1998 in W.P. No. 30220/1997) and directed the Corporation to pass fresh orders on the representations made by the respondents. The learned Single Judge proceeded on the assumption, without basis, that the order dated 17.3.1998 in the earlier petition (WP No. 30220/1997) had held that Respondents were entitled to the benefit of the Circular dated 1.9.1988, when in fact there was no such finding or direction. Therefore, the direction of the learned Single Judge, as confirmed by the Division Bench, to consider the cases of respondents under the Circular dated 1.9.1988 cannot be sustained. (Para 16)

       (ii) Constitution of India—Article 226—Power of judicial review concentrates and lays emphasis on decision making process rather than decision itself. (Para 13)

Judgment

Raveendran, J.—The Andhra Pradesh State Road Transport Corporation, first appellant, (for short ‘the Corporation’), issued a Circular dated 1.9.1988 containing the guidelines for absorption of persons employed on casual basis/consolidated pay/piecemeal rate/work charged establishment, whose services had been ordered to be dispensed with, under an earlier Circular dated 2.7.1987. The said guidelines provided, inter alia, that such absorption shall be only against sanctioned vacancies, and that the benefit was to be extended only to those who had been engaged for more than one year. The Circular made it clear that benefit thereof will not extend to persons engaged by its contractors at Bus Stations and certain other categories of persons detailed therein.

2. The respondents herein filed W.P. No. 14353/1991 claiming to be scavengers employed by the Corporation, seeking a direction for regularisation. That petition was disposed of by order 5.11.1991 with a direction to consider their cases in terms of the Circular dated 1.9.1988 and pass appropriate orders. The High Court did not examine the claim on merits.

3. To give effect to the said order, the Divisional Manager of the Adilabad Division of the Corporation sent a communication dated 14.7.1992 instructing the Depot Manager, Mancherial to verify the claims of the respondents (as they had claimed that they were working in the said Depot) and to send him the necessary information in the prescribed proforma. Alleging inaction thereafter, the respondents herein again approached the High Court in W.P. No. 30220/1997 for a declaration that the Corporation’s failure to take action in pursuance of the said letter dated 14.7.1992 was illegal and praying for a direction to the Corporation to absorb them into its service.

4. A learned Single Judge of the High Court by order dated 17.3.1998 disposed of Writ Petition No. 30220/1997 at the stage of preliminary hearing, without examining the matter on merits, by directing the Corporation to consider the claim for absorption in accordance with the guidelines contained in the Circular dated 14.7.1992. In the said order, the High Court proceeded on the erroneous assumption that the letter dated 14.7.1992 of the Divisional Manager was the Circular containing the guidelines relating to absorption.

5. In pursuance of it, the claim of one of the respondents - B. Madhuraiah (third respondent herein), was considered. He was required to appear before a Selection Committee on 21.4.1999. He appeared before the Committee and admitted that he had worked only under a contractor and not under the Corporation. The Regional Manager, Adilabad Division, therefore, passed an order dated 21.4.1999 holding that the third respondent was not entitled to claim absorption. He held that the provisions of the Circular dated 1.9.1988 providing for absorption were inapplicable to the third Respondent, as he had not directly worked under the Corporation. He recorded a finding that third respondent was employed as a contract labour by a contractor, receiving payment through the contractor, and that there was no relationship of employee and employer between him and the Corporation, either in regard to assignment of work, or performance of work, or payment of remuneration.

6. Feeling aggrieved, the respondents approached the High Court for the third time, by filing W.P. No. 17678 of 1999 for quashing the said order dated 21.4.1999 and seeking a direction to the Corporation to treat them as ex-casual employees and absorb them under the terms of the Circular dated 1.9.1988. A learned Single Judge by order dated 23.8.1999 disposed of the said petition at the admission stage, quashing the said order dated 21.4.1999 and directing the Corporation to pass a fresh order on the representation of the respondents herein. The learned Single Judge was of the view that the respondents herein could not be denied relief on the ground that they were employed as contract labour, as such a con






















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top