2006(5) Supreme 890
SUPREME COURT OF INDIA
(From Kerala High Court)
Arijit Pasayat and Lokeshwar Singh Panta, JJ.
Kerala State Science and Technology Museum — Appellant
versus
Rambal Company & Ors. — Respondents
Civil Appeal No. 4854 of 2000
With
Civil Appeal No. 3211 of 2006
(Arising out of SLP (C) No. 7048/2001)
Decided on 2-8-2006
Counsel for the Parties :
For the Appellant : Harish Beeran, N. Rao and Radha Shyam Jena, Advocates.
For the Respondents : Mrs. Beena Prakash, G. Prakash and B.V. Deepak (for M/s. T.T.K. Deepak & Co.), Advocates.
Held : It is fairly well settled that when reference is made on a specific issued either by a learned Single Judge or Division Bench to a larger Bench i.e. Division Bench or Full Bench or Constitution Bench, as the case may be, the Larger Bench cannot adjudicate upon an issue which is not the question referred. (See: Kesho Nath Khurana v. Union of India and Others [1981 (Supp.) SCC 38], Samaresh Chandra Bose v. The District Magistrate, Burdwan and Others [1972 (2) SCC 476] and K.C.P. Ltd. v. State Trading Corporation of India and Another [1995 Supp. (3) SCC 466]. In the instant case, there was no reference to Division Bench. Learned Single Judge felt that in view of the contentions, a Division Bench should hear the case. We find that before learned Single Judge there was practically no dispute that there was breach of conditions of contract. In fact learned Single Judge noted the position as follows:
"The question of termination of contract with effect from 25.11.1989 is not disputed. Petitioner did not challenge the termination order. As per the terms of the contract, if it is re-tendered, the difference in the re-tender amount and the loss suffered have to be paid by the petitioner apart from the liquid damages."
(Underlined for emphasis)
The learned Single Judge also noted that the main contention of the writ petitioner was that the amount demanded was time barred. Reference was made to Section 71 of the Kerala Revenue Recovery Act, 1968. Therefore, it was contended before learned Single Judge that when the matter is time barred even if the demand is correct it cannot be enforced through revenue recovery proceedings. Stand of the appellants on the contrary was that the society is owned by the State and, therefore, Article 112 of the Limitation Act, 1963 is applicable and the demand was raised within time. Considering the rival submissions learned Single Judge held that in view of the nature of contention the matter should be heard by a Division Bench. Unfortunately the Division Bench did not consider the contentions which were raised before the learned Single Judge. It also did not record any positive finding as to whether the document relied upon by the appellant clearly established admission of a breach of contract. The portion of the order of learned Single Judge, quoted above, suggests that there was no dispute when read in the context of the letter dated 14.2.1990. As rightly contended by learned counsel for the appellant the basic issue related to the question whether the demand was barred by limitation. As noted above the Division Bench of the High Court did not examine this question. Above being the question we set aside the order of the Division Bench and remit the matter back for fresh consideration limiting the examination to the question whether the demand by barred by limitation.(Paras 8 to 15)
JUDGMENT
Arijit Pasayat, J. — Challenge in these appeals is to the judgment of a Division Bench of the Kerala High Court holding that quantification of damages done and demanded from the respondent No.1 cannot be legally sustained and accordingly they were set aside. The writ petition was directed to be placed before the Division Bench by a learned Single Judge. But the question referred by learned Single Judge i.e. question of limitation was left open to be adjudicated by the appropriate authority in accordance with law.
2. The background facts in a nutshell are as follows:-
The respondent No.1 had entered into Ext. P1 agreement with the appellant-Kerala State Science and Technology, Thiruvananthapuram which is a society registered under the Travancore Cochin Literary and Scientific Societies Registration Act, 1995, on 16.05.1988 for the construction of planetarium building of the Kerala State Science and Technology Museum and allied Civil Works. Dispute having arisen between the parties the agreement came to be terminated by Ext. P2 termination notice dated 03.11.1989 issued by the appellant. Ext. P2 was followed by Ext. R1(c) letter from the managing Partner of the respondent No.1 allegedly admitting the breach of contract. Suit notice dated 06.11.1990 issued by the appellant to the respondent No.1 which was replied by it as per Ext. P3 dated 31.12.1990 repudiating the alleged breach and raising a counter-claim. According to the respondent No.1 there was a long silence after Ext. P3 which was broken on 12.01.1998 on which date it received Ext. P4 demand notice from the Deputy Tahsildar (RR), Thiruvananthapuram under Section 34 of the Revenue Recovery Act 1968 calling upon it to remit an amount of Rs.22,10,303/- with future interest at the rate of 12% from 01.04.97. On receipt of Ext. P4 the respondent No.1 moved the High Court with Arbitration Request No.2/98 under Section 11 of the Arbitration and Conciliation Act, 1996 for the appointment of an arbitrator for resolution of all disputes and differences between the parties concerning the performance of the work under Ext. P1 agreement. The request was resisted by the appellant contending, inter-alia, that there is no provision for arbitration in Ext. P1 agreement. It was also contended that as per clause 54 of Ext P1 agreement, there is a specific exclusion of resolution of disputes by arbitration and the Civil Courts at Thiruvananthapurarn alone are clothed with jurisdiction to resolve the disputes arising between the parties out of Ext.P1 agreement. In other words, not only Ext. P1 does not contain an arbitration clause, on the contrary, Ext. P1 specifically rules out arbitration as a mode of settlement of disputes or claims arising out of Ext. P1. Accepting the said contentions the High Court rejected the request. After the said order was passed by the High Court, the respondent No.1 filed writ petition, being O.P. No. 22633/98 to quash Ext. P4 demand notice and for other reliefs which came to be disposed of by judgment dated 17.11.98 directing the District Collector to consider and pass orders on the representation preferred by the respondent No.1 within one month from the date of receipt of a copy of the judgment. Pending issuance of orders by the District Collector as aforesaid, the demand notice as evidenced by Ext. P4 was stayed. As a sequel to the judgment, the District Collector passed an order rejecting Ext. P8. Upon rejection of Ext.P8 by District Collectors order Ext.P4 was revived and the respondent No.1 was called upon to pay the amount mentioned therein being the loss suffered by the appellant in re-arranging the work at the risk and cost of the respondent No.1. It was at this stage, that the said respondent moved the High Court by filing a writ petition praying for the issuance of a writ of certiorari or any other appropriate writ, direction or order quashing the order and Ext.P4 demand notice as illegal and arbitrary and for the issuance of a writ of manda
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.