NATIONAL BUILDINGS CONSTRUCTION CORPORATION LTD. – Appellant
Versus
LLOYDS INSULATION INDIA LTD. – Respondent
Judgment
( 1 ) LEAVE granted.
( 2 ) THE parties had entered into an agreement under which the respondent was to supply certain material and make construction. Disputes arose between them. The disputes were referred to arbitration. Claims and counterclaims were made by the parties before the arbitrator. Ultimately, the arbitrator, by an award dated 9-1-2001, held that an amount of rs 13,97,072. 24 was due to the respondent and an amount of Rs 9,85,316 was due to the appellant. In the circumstances, the arbitrator held that ultimately the respondent was entitled to recover a sum of Rs 4,11,756 being the amount of Rs 13,97,072. 24 less Rs 9,85,316 from the appellant. Accordingly, the award was passed directing the appellant to pay the respondent the said sum together with interest at 12% from the date of the award till payment.
( 3 ) AN application was made by the respondent challenging that part of the award which related to the finding of the arbitrator in favour of the appellant. While the challenge was pending, an application for execution was moved by the respondent for recovery of the entire amount of Rs 13,97,072. 24 from the appellant. The application for execution was allowed.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.