2004 Supreme(SC) 1497

NATIONAL BUILDINGS CONSTRUCTION CORPORATION LTD. – Appellant
Versus
LLOYDS INSULATION INDIA LTD. – Respondent


Judgment

( 1 ) LEAVE granted.

( 2 ) THE parties had entered into an agreement under which the respondent was to supply certain material and make construction. Disputes arose between them. The disputes were referred to arbitration. Claims and counterclaims were made by the parties before the arbitrator. Ultimately, the arbitrator, by an award dated 9-1-2001, held that an amount of rs 13,97,072. 24 was due to the respondent and an amount of Rs 9,85,316 was due to the appellant. In the circumstances, the arbitrator held that ultimately the respondent was entitled to recover a sum of Rs 4,11,756 being the amount of Rs 13,97,072. 24 less Rs 9,85,316 from the appellant. Accordingly, the award was passed directing the appellant to pay the respondent the said sum together with interest at 12% from the date of the award till payment.

( 3 ) AN application was made by the respondent challenging that part of the award which related to the finding of the arbitrator in favour of the appellant. While the challenge was pending, an application for execution was moved by the respondent for recovery of the entire amount of Rs 13,97,072. 24 from the appellant. The application for execution was allowed.





Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top