Interlinking of Rivers - Water Resources - The court found that there was a consensus among the States and Union Territories in favor of interlinking of rivers in India. The court emphasized the benefits of the project, including relief to drought-prone areas, flood control, and water harvesting. The court also discussed the need for a realistic timeline for completion and the requirement for consent from all affected states.
Fact of the Case:
The Union of India and the State of Tamil Nadu filed affidavits in support of interlinking of rivers. No other State or Union Territory opposed the prayer made in the writ petition, indicating a consensus among them in favor of the project.
Finding of the Court:
The court emphasized the benefits of the interlinking of rivers project and the need for a realistic timeline for completion. It also discussed the requirement for consent from all affected states and the possibility of legislation to facilitate the project.
Issues: Consensus among States and Union Territories in favor of interlinking of rivers, realistic timeline for completion, requirement for consent from affected states, and the possibility of legislation to facilitate the project.
Ratio Decidendi: The court found a consensus among the States and Union Territories in favor of interlinking of rivers and emphasized the need for a realistic timeline for completion and the requirement for consent from all affected states. The court also discussed the possibility of legislation to facilitate the project.
Final Decision: The court did not issue a specific direction but emphasized the need for a realistic timeline for completion and the requirement for consent from all affected states. It also discussed the possibility of legislation to facilitate the project.
( 1 ) PURSUANT to the notice issued by this Court to all the States and the Union Territories in relation to the interlinking of the rivers, an affidavit has been filed by the Union of India and also by the State of Tamil Nadu. No other State or Union Territory has filed any affidavit and the presumption, therefore, clearly is that they do not oppose the prayer made in this writ petition and it must be regarded that there is a consensus amongst all of them that there should be interlinking of rivers in India.
( 2 ) IN the counter - affidavit filed on behalf of the Union of India, it has, inter alia, been stated that after the Rao Committees report was received, the Government of India has been studying and planning for interlinking of rivers for over two decades. It is also mentioned in this affidavit that the Ministry of Water Resources had made a representation on 5/10/2002 before the Prime Minister on interlinking of rivers and in that presentation the Deputy Prime Minister and other senior Ministers and officers were also present. It was suggested that a High Level Task Force can be formed which will go into the modalities for bringing consensus among the States. This affidavit further states that the presentation was also made to the President of India on 16/10/2002 which also shows interest of the President of India in this project and it is in view of his broadcast to the nation on the eve of Independence Day where emphasis was laid on interlinking of rivers that has given rise to the filing of the present petition.
( 3 ) LEARNED Attorney General states that a High Powered Task Force, as referred in the affidavit of the Union of India, has not yet been formed and by the next date of hearing he should be in a position to inform this Court with regard to the formation of the said Task Force as well as the decision of the said Force. The Union of India has accepted the concept of interlinking of rivers and in the affidavit spelt out the benefits which will enure after the entire project has been completed.
( 4 ) THE State of Tamil Nadu is the only State which has responded to the notice issued by this Court and filed an affidavit. The said State also supports interlinking of the rivers and in its affidavit has prayed that a direction be issued to the Union of India for constituting a High Powered Committee in order to see that the project is completed in time schedule. Along with this affidavit the perspective plan for implementation of inter-basin water transfer proposals prepared by the National Water Development Agency in May 2000 has been placed on record. We are distressed to note that milestone for the perspective plan indicated in the report of the agency shows that even though the pre-feasibility reports regarding the Peninsular and Himalayan Projects are already completed, the completion of the link projects ultimately will be by the year 2035 in respect of Peninsular Link Project and 2043 regarding Himalayan Link Project.
( 5 ) IT is difficult to appreciate that in this country with all the resources available to it, there will be a further delay of 43 years for completion of the project to which no State has any objection and whose necessity and desirability is recognised and acknowledged by the Union of India. The project will not only give relief to the drought-prone areas but will also be an effective flood-control measure and would be a form of water harvesting which is being rightly propagated by the Union of India and all the States.
( 6 ) LEARNED Attorney General states that a more realistic view will be taken and a revised programme on completion would be drawn up and be presented to the Court. We do expect that the programme when drawn up would try and ensure that the link projects are completed within a reasonable time of not more than ten years. We say so because recently the National Highways Projects have been undertaken and the same are nearing completion and the interlinking of the rivers is compl
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.