SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2001 Supreme(SC) 180

SUPREME COURT OF INDIA
State of Madhya Pradesh
Versus
K. K. SHUKLA AND CO.
Decided On : January 31, 2001

The interpretation of contract clauses and the determination of whether they constitute arbitration clauses are crucial in deciding the permissibility of invoking statutory arbitration provisions.

Headnote:

Arbitration - Scope of Contract Clause 29 and Effect of Section 7 of the Act

Fact of the Case:

Disputes arose between the parties, leading to a reference to arbitration under Section 7 of the M. P. Madhyastham adhikaran Adhiniyam, 1983. The respondent contended that it was not open to invoke Section 7 of the Act after availing arbitration under clause 29 of the contract. The High Court upheld the view of the Arbitral tribunal, leading to this appeal.

Finding of the Court:

The court rejected the contention that invoking Section 7 of the Act after availing arbitration under clause 29 was not permissible. It interpreted clauses 29(2) of the contract, emphasizing that they did not amount to arbitration clauses and that the Superintending Engineer and Chief Engineer did not function as arbitrators. Therefore, the effect of Section 7 upon clause 29 did not arise for consideration.

Issues: The limited question raised for consideration was the scope of clause 29(2) of the contract and the effect of Section 7 of the Act upon the same.

Ratio Decidendi: The court interpreted the contract clauses to determine that they did not constitute arbitration clauses and that the Superintending Engineer and Chief Engineer did not act as arbitrators. Therefore, the contention that invoking Section 7 of the Act after availing arbitration under clause 29 was impermissible was rejected.

Final Decision: The appeal was dismissed, upholding the view of the Arbitral tribunal and the High Court.

( 1 ) DISPUTES having arisen between the appellants and the respondent, a reference was made to arbitration under Section 7 of the M. P. Madhyastham adhikaran Adhiniyam, 1983 (hereinafter referred to as "the Act" ). Before the tribunal, it was contended that having availed of arbitration under clause 29 of the contract it was not open to invoke Section 7 of the Act. This contention was rejected. A revision petition was filed under Section 19 of the Act in the madhya Pradesh High Court. The High Court upheld the view of the Arbitral tribunal. Hence this appeal by special leave. In this appeal the limited question raised for consideration is as to the scope of clause 29 (2) of the contract between the parties under which the respondent executed certain works and effect of Section 7 of the Act upon the same.

( 2 ) THE contention put forth before us is that in terms of clause 29 of the contract the respondent had invoked the jurisdiction of the Superintending engineer and the Chief Engineer and when their decision went against it, sought to avail of the remedy under provisions of Section 7 of the Act; that, it is not open to the party having acquiesced in the arbitration proceedings under the contract to seek for second reference for arbitration.

( 3 ) THE Superintending Engineer under clause 29 (2) is empowered todecide all questions relating to the meaning of the specifications, designs, drawings and constructions mentioned in the contract and as to the quality of workmanship or materials used in the work or as to any other question, claim, right, matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawings, specification estimates, instructions, orders or these conditions, or otherwise concerning the work, or the execution, or failure to execute the same, whether arising during the progress of the work or after the completion of abandonment and the Superintending engineer will have to give his decision after giving an opportunity to the party to the contract. If any party is not satisfied with the decision of the superintending Engineer, it may make a reference to the Chief Engineer within 30 days from the date of communication of the decision of the superintending Engineer and the Chief Engineer will give his decision after hearing the parties which shall be final, conclusive and binding on the parties.

( 4 ) THESE clauses are sought to be interpreted as clauses for arbitration. We fail to understand as to how these clauses can be understood to be one referring the matter to arbitration at all. So far as the Superintending engineer is concerned, he has to decide certain questions which we have adverted to and upon his decision the matter is referred to the Chief Engineer for further decision. These two provisions made in the contract are only to make a fair provision in the contract to settle any of the claims that may arise in the course of execution of contracts and the matter cannot be stretched so as to elevate to the level of an arbitration clause. Neither the Superintending engineer nor the Chief Engineer can be characterised as discharging the functions of an arbitrator. In that view of the matter, we do not think the contention put forth on behalf of the appellant that the respondent having availed of the arbitration as provided under clause 29 is trying to seek another remedy as provided under Section 7 of the Act is tenable. In the circumstances, the effect of Section 7 upon clause 29 does not arise for consideration at all. In that view of the matter, no interference is called for with the order under appeal. This appeal is therefore dismissed.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top