2006 Supreme(SC) 976

2006(8) Supreme 135
SUPREME COURT OF INDIA
(From Gujarat High Court)
S.B. Sinha and Dalveer Bhandari, JJ.
Union of India & Ors.—Appellants
versus
Jummasha Diwan—Respondent
Civil Appeal No. 4552 of 2006
(Arising out of SLP (Civil) No. 7337 of 2006)
Decided on 19-10-2006
Counsel for the Parties :
For the Appellants : R. Mohan, A.S.G., S. Wasim A. Qadri, B. Krishna Prasad and D.S. Mahra, Advocates.
For the Respondent : S.C. Patel, Advocate.

IMPORTANT POINT
When the project in which workman was employed comes to a close, requirement of Section 25-N of the Act were not required to be complied with.

Headnote:Industrial Disputes Act, 1947—Section 25-N—Respondent was appointed as daily wager in Railway Electrification Project and then was granted temporary status—He was retrenched on premise that project concluded and he was paid retrenchment compensation—Dispute was raised that respondent had put in 1060 days continuous service and could not have been retrenched having regard to principle of “last come first go”—Tribunal dismissed application—High Court set aside order of termination and directed reinstatement—Appeal—When services of project employee was terminated, statutory requirement of Section 25-F of the Act was required to be complied with and respondent was paid retrenchment compensation—Respondent had worked in several establishments of appellant and same would not amount to his being in continuous service—If project came to a close, requirement of Section 25-N of the Act were not required to be complied with—Impugned judgment could not be sustained.

       Held : Respondent indisputably had started working under Appellant No. 3 1986. His services had been terminated inter alia on the premise that the electrification project had come to a close. If the services of a project employee is terminated, it is trite that statutory requirements of Section 25-F of the Act are required to be complied with, but, indisputably, Respondent was given one months notice pay as also the retrenchment compensation in compliance thereof. (Para 7)

       His name might not have appeared in the seniority list of the casual labourers which was being maintained but the question, as to whether he had been in continuous service in all the departments he had served, was a disputed one. There are several establishments of the Railway Administration. If a workman voluntarily gives up his job in one of the establishments and joins another, the same would not amount to his being in continuous service. When a casual employee is employed in different establishments, may be under the same employer, e.g., the Railway Administration of India as a whole, having different administrative set up, different requirements and different projects, the concept of continuous service cannot be applied and it cannot be said that even in such a situation he would be entitled to a higher status being in continuous service. It is not in dispute that the establishment of Appellant No. 3 herein had started a project. His recruitment in the said establishment would, therefore, constitute a fresh employment. In a case of this nature, Respondent would not be entitled to his seniority. If the project came to a close, the requirements of Section 25-N of the Act were not required to be complied with.(Para 8)

       For the reasons aforementioned, we are of the opinion that the impugned judgment cannot be sustained which is set aside accordingly. This appeal is allowed.(Para 11)

       

JUDGMENT

S.B. Sinha, J.—Leave granted.

2. Respondent was appointed as a daily wager in the Railway Electrification Project at Vadodara Ratlam section. He was granted a temporary status. He is said to have joined the Railway Electrification Project as a skilled worker under the Divisional Electrical Engineer, Western Railway (Overhead Equipment) Railway Electrification Railway Yard, Pratapnagar, Baroda, Appellant No. 3 herein. He was retrenched purportedly on the premise that railway electrification works at Vadodara Ratlam section came to an end. He was paid retrenchment compensation in terms of Section 25-F of the Industrial Disputes Act, 1947 (for short "the Act").

3. He filed an original application before the Central Administrative Tribunal (Tribunal) questioning the purported retrenchment on the ground that he having put in 1060 days of continuous service should have been placed much higher in the seniority list and, thus, could not have been retrenched having regard to the principle of "last come first go". It was also contended that while passing an order of retrenchment, the provisions of Section 25-N of the Act was not complied with.

4. The Tribunal dismissed the said original application. A writ petition came to be filed wherein the same pleas were raised by Respondent herein. Invoking Section 25-N of the Act, the impugned judgment has been passed setting aside the order of termination and directing reinstatement of Respondent.

5. Mr. R. Mohan, learned Additional Solicitor General appearing on behalf of Appellants inter alia submitted that the provisions of Section 25-N of the Act will have no application to the facts and circumstances of the case.

6. Mr. S.C. Patel, learned counsel appearing on behalf of Respondent, on the other hand, submitted that Respondent having put in 1060 days of continuous service, the order of retrenchment was vitiated in law. It had been pointed out that different benches of the Central Administrative Tribunal on almost identical issues had taken different views and in that view of the matter, the impugned judgment should not be interfered with.

7. Respondent indisputably had started working under Appellant No. 3 1986. His services had been terminated inter alia on the premise that the electrification project had come to a close. If the services of a project employee is terminated, it is trite that statutory requirements of Section 25-F of the Act are required to be complied with, but, indisputably, Respondent was given one months notice pay as also the retrenchment compensation in compliance thereof.

8. His name might not have appeared in the seniority list of the casual labourers which was being maintained but the question, as to whether he had been in continuous service in all the departments he had served, was a disputed one. There are several establishments of the Railway Administration. If a workman voluntarily gives up his job in one of the establishments and joins another, the same would not amount to his being in continuous service. When a casual employee is employed in different establishments, maybe under the same employer, e.g., the Railway Administration of India as a whole, having different administrative set up, different requirements and different projects, the concept of continuous service cannot be applied and it cannot be said that even in such a situation he would be entitled to a higher status being in continuous service. It is not in dispute that the establishment of Appellant No. 3 herein had started a project. His recruitment in the said establishment would, therefore, constitute a fresh employment. In a case of this nature, Respondent would not be entitled to his seniority. If the project came to a close, the requirements of Section 25-N of the Act were not required to be complied with.

9. Lal Mohammad and Others v. Indian Railway Construction Co. Ltd. and Another [(1999) 1 SCC 596], whereupon reliance has been placed by the High Court, cannot have any applic




Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top