SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2006 Supreme(SC) 1140

2006(9) Supreme 39
SUPREME COURT OF INDIA
(From Calcutta High Court)
Dr. AR. Lakshmanan & Altamas Kabir, JJ.
M/s. Ambica Construction - Appellant
versus
Union of India - Respondent
Civil Appeal No. 5093 of 2006
(Arising out of SLP (C) No. 2753/2005)
With
Civil Appeal No. 5097 of 2006
(Arising out of SLP (C) No. 19237 of 2005)
Decided on 20-11-2006
Counsel for the Parties :
For the Appellant : Raj Kumar Mehta and Ms. Suman Kukrety, Advocates.
For the Respondent : T.S. Dobia, Sr. Advocate, Mrs. Kiran Bhardwaj, Ms. Shilpa Singh, D.S. Mehra and B. Krishna Prasad, Advocates.

Headnote:Arbitration and Conciliation Act, 1996 - Section 34 - Arbitration award allowing claims made by appellant - Respondent challenged the award on ground that arbitrator failed to consider General Condition of Contract under which appellant had issued No Claim Certificate - Single Judge found that matter had been adjudicated by Arbitrator and since Court was not sitting in appeal over the award, it could not enter into reasonableness of reasons given by Arbitrator - Division Bench in appeal came to a finding that apart from mere statement there was no proof of allegations that appellant was compelled to sign No Claim Certificate under coercion or duress and set aside the award - Appeal - Efficacy of Clause 43(2) of General Conditions of Contract regarding No Claim Certificate - It was apparent that unless discharge certificate was given in advance, payment of bills are generally delayed - Material on record showed that appellant had a genuine claim which was considered in great detail by Arbitrator - Notwithstanding Clause 43(2) of General Conditions of Contract and submission of a No Claim Certificate by appellant, appellant was entitled to claim a reference - Division Bench was wrong in holding otherwise.

       Held : From the submissions made on behalf of the respective parties and in particular from the submissions made on behalf of the appellant, it is apparent that unless a discharge certificate is given in advance, payment of bills are generally delayed. Although, Clause 43(2) has been included in the General Conditions of Contract, the same is meant to be a safeguard as against frivolous claims after final measurement. Having regard to the decision in the case of Reshmi Constructionss (supra), it can no longer be said that such a clause in the contract would be an absolute bar to a contractor raising claims which are genuine, even after the submission of such No Claim Certificate.(Para 18)

       We are convinced from the materials on record that in the instant case the appellant also has a genuine claim which was considered in great detail by the Arbitrator who was none other than the counsel of the respondent-Railways. (Para 19)

       In such circumstances we are inclined to hold that notwithstanding Clause 43(2) of the General Conditions of Contract and the submission of a No Claim Certificate by the appellant, the appellant was entitled to claim a reference under the contract and the Division Bench of the Calcutta High Court was wrong in holding otherwise.(Para 20)

       

JUDGMENT

Altamas Kabir, J. - Delay condoned in S.L.P. (C) No. 19237/2005.

2. Leave granted in both the Special Leave Petitions which have been taken up together for disposal, since SLP (C) No.19237 of 2005 is directed against the main judgment and Order dated 16th March, 2004, passed by the Calcutta High Court allowing the appeal of the Union of India and SLP (C) No. 2753 of 2005 arises out of the order dated 23rd September, 2004 passed by the said High Court on a Review Petition in respect of the main judgment.

3. Pursuant to a Tender Notice, issued by the respondent for certain new works, additions, alterations, repair and maintenance works in the Mancheswar Complex, the appellant submitted its tender on 2nd September, 1992. The appellants tender was duly accepted by a letter dated 14th September, 1992 with the stipulation that the work was to be completed in all respects by 30th June, 1993. It was also indicated that the work orders were to be issued within 7 days from the date of receipt of the acceptance letter. A formal contract was executed between the parties on 4th March, 1993 and the said agreement provided that the General Conditions of Contract and Standard Specifications of the South Eastern Railways shall be applicable to the contract. Clause 63 of the General Conditions of Contract provides for settlement of disputes by Arbitration.

4. As would appear from the materials on record, the appellant herein was unable to complete the work within the stipulated time frame and accordingly it applied for extension of time by three months upto 30th September, 1993. It is the appellants case that since it was not informed about the decision on the said application, the appellant suffered huge losses on account of idle labour and surplus staff. It appears that ultimately the appellants request was turned down and certain deductions were made from the Running Bills submitted by the appellant and in fact payment was not even made for the works already done by the appellant. According to the appellant, the respondent refused to refund even the appellants security deposit unless the appellant submitted a No-Claim Certificate in terms of Clause 43(2) of the General Conditions of Contract. Having no other alternative and having incurred huge losses on account of idle labour and surplus staff and the establishment expenses, the appellant submitted a No Claim Certificate in order to at least get refund of its security deposit.

5. By a letter dated 17th January, 1996, the appellant called upon the respondent to make payment of a sum of Rs.8,73,168/- and Rs.1,31,642/- which, according to the appellant, was due from the respondent to the appellant under the contract, failing which the respondent was requested to appoint an Arbitrator for adjudication of the disputes which had arisen between the parties. In view of the failure of the respondent either to pay the dues, as demanded, or to appoint an Arbitrator, the appellant filed an application under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter called "the 1996 Act") before the Calcutta High Court for reference of its claims in terms of its letter dated 17th January, 1996 to arbitration and for appointment of an Arbitrator. No reply was filed by the respondent to the said application but during the pendency thereof, the respondent refunded to the appellant, the security deposit of Rs. 79,000/-. The same was received by the appellant under protest.

6. As no objection was taken by the respondent to the appellants application under Section 11 of the 1996 Act or with regard to the submission of the No Claim Certificate by the appellant at the time of receiving the security deposit, the learned Single Judge of the Calcutta High Court, by his order dated 20th February, 1998, directed the matter to be placed before Honble the Chief Justice for naming an Arbitrator for adjudication of the disputes. On 12th March, 1998, the Chief Justice appointed one Shri Subrata Bagchi



















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top