JT 2008 (11) SC 596
IN THE SUPREME COURT OF INDIA
S.H. Kapadia and B. Sudershan Reddy, JJ.
Pundlik Jalam Patil (D) by Lrs.- Appellant(s)
Versus
Exe. Eng. Jalgaon Medium Project & Anr.- Respondent(s)
Civil Appeal Nos.6414-6417 of 2008
Arising out of SLP © Nos. 21011-21014 of 2007
Decided On: 03/11/2008
Administration of Justice - Stale claims - Settled rights cannot be lightly interfered with by condoning inordinate delay without there being any proper explanation of such delay on the ground of involvement of public revenue - It serves no public interest - Public interest is a paramount consideration in exercising the Courts discretion wherever conferred upon it by the relevant statues - Pursuing stale claims and multiplicity of proceedings in no manner sub serves public interest - Prompt and timely payment of compensation to the land losers facilitating their rehabilitation/resettlement is equally an integral part of public policy - Dragging land losers to Courts of law years after termination of legal proceedings would not serve any public interest. (Para 24)
Limitation Act, 1963 - Section 5 - Limitation Act does not provide for a different period to government in filing appeals or applications as such - In a given case if any such facts about public interest are pleaded or proved they cannot be excluded from consideration and those factors may go into in the judicial verdict. (Para 25)
(1981)1 SCC 495; 1969(2) SCR 824; (1998)7 SCC 123; (1973)2 SCC 705; AIR 1962 SC 361; (2000)10 SCC 611; (1997)9 SCC 69 - Referred to.
Leave granted.
2. These appeals, by Special Leave, are directed against the common judgment
and order dated 22/23.08.2007 of the High Court of Bombay, Bench at Aurangabad allowing the applications filed by the first respondent under Section 5 of the Limitation Act, 1963 (hereinafter referred to as `the said Act) to condone the delay of 1724 days in filing appeals against the award passed by the Civil Judge, Senior Division, Jalgaon in land acquisition cases. The High Court accepted the explanation offered by the respondent no. 1 herein for the apparent inordinate delay in filing the appeals against the award of the Reference Court.
3. Brief facts needed for disposal of these appeals are as under:
4. The lands belonging to the appellants were acquired at the instance of the respondent for a public purpose under the draft Notification published in Maharashtra Government Gazette on 06.03.1997. The Special Land Acquisition Officer, Upper Tapi Project (Hatnur), Jalgaon passed the award dated 31.3.1999. The appellant sought for reference of the said award under Section 18 of the Act seeking enhancement of the compensation. The learned Civil Judge, Senior Division, Jalgaon disposed of the references vide award/judgment dated 9.3.2000 enhancing the compensation over and above the amount fixed in the award passed by the Special Land Acquisition Officer. Be it noted, not only the Special Land Acquisition Officer but the first respondent herein was also impleaded as a party respondent in the land acquisition reference case. The Executive Engineer, Medium Project Division, Jalgaon filed appearance through its counsel but did not lead any evidence though a written statement opposing the claim of enhancement was filed in the Reference Court. On 24.03.2000 the Government Pleader, Jalgaon submitted report and expressed his opinion that it is a fit case for filing the appeal on the grounds stated in the report itself. The Law and Judiciary Department took decision on 13.4.2000 to `acquiesce in the decision of the Reference Court and communicated the same to all the concerned including the first respondent herein who is the beneficiary of the acquisition.
5. It is required to notice that neither the Special Land Acquisition Officer nor the beneficiary of the acquisition raised little finger and objected to the decision taken in the matter. The Special Land Acquisition Officer after about one year vide its letter dated 31.5.2001 addressed the Principal Secretary to Law & Judiciary Department, Government of Maharashtra for reviewing the decision taken regarding acquiesce in the decision of Reference Court in the matter. The government reiterated its decision and expressed its view that under the rules the Joint Secretary Law & Judiciary Department was competent to take appropriate decision in the matter on behalf of the Government and found no reason to review the decision so taken by its Joint Secretary. The Government accordingly informed not only the Special Land Acquisition Officer but also the first respondent that more than one year had elapsed and there were no grounds for condoning the delay in filing the appeals.
6. The beneficiary of the acquisition who is contesting the appeals before us did not take any steps whatsoever after receiving the said communication until 25.2.2005 on which date the appeals were preferred along with the applications to condone the delay of 1724 days except indulging in some correspondence long after expiry of limitation. It is required to notice that the beneficiary of the acquisition made arrangements for the deposit of the decreetal amount to be deposited by the Special Land Acquisition Officer in the Reference Court in May, 2001 itself. Some further amounts towards interest etc. were of course not deposited. The appellant executed the decree and realised the entire money deposited into the court.
7. The High Court having considered the applications filed under Section 5 of Limitation Act condoned the inordinate d
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.