Supreme Court of India
THE HONOURABLE MR. JUSTICE S.B. SINHA & THE HONOURABLE MR. JUSTICE CYRIAC JOSEPH
National Thermal Power Corporation Ltd.
Versus
Mahesh Dutta & Others
CIVIL APPEAL NOS.6228-6229 OF 2002
Decided on : 16-07-2009
(b) Land Acquisition Act, 1894 – Section 17 – Whether actual possession has been taken is a question of fact – Depends upon facts and circumstances of each case. (Para 27)
AIR 1975 SC 1967 : (1976) 1 SCC 70; (1998) 4 SCC 387; (2005) 12 SCC 489 – Relied upon
(c) Land Acquisition Act, 1894 – Section 17 – Possession – Delivery of possession – Procedure – Order XXI Rule 35, CPC – Actual possession – U/s 17 vesting of land takes effect immediately – NTPC paying 80% of entire compensation – Contention that possession of only 10 acres land out of 65 could be taken cannot be accepted – (Para 29, 30)
(1970) 2 SCC 149; (1993) 4 SCC 369; (1996) 3 SCC 1; (1996) 3 SCC 600; (1996) 8 SCC 259; (2005) 12 SCC 508; (2005) 11 SCC 493 – Relied upon
(d) Constitution of India – Article 226 – Disputed questions of fact – High Court not debarred from entering into disputed question of fact – If the question can be determined on the basis of documents and affidavits, High Court may not refuse to do so – It may also examine witnesses. (Para 33)
(1969) 3 SCC 769; (1974) 2 SCC 706; (2007) 9 SCC 255 – Relied upon
(e) Land Acquisition Act, 1894 – Section 17(1) r/w section 114, Indian Evidence Act, 1872 – Possession certificate and other documents including judicial records showing possession having been taken over – Illustration (e) of section 114 applies – Presumption of actual possession arises – It is for the State to prove contra. (Para 35)
(f) Constitution of India – Article 142 – Exercise of power – The Court cannot foresee all eventualities – However, the respondents categorically stating that none of them is in possession of acquired land – If it is found to be incorrect legal remedies are available for eviction &c. (Para 36)
(g) Land Acquisition Act, 1894 – Section 17(1) – Land vesting in State – Land originally acquired for thermal power plant – Power plant shifted – State empowered to put the vested land for another public purpose. (Para 38)
(2007) 9 SCC 255; (2003) 1 SCC 335; (2007) 5 SCC 231 – Relied upon
Facts of the case:
A Notification was published in the Official Gazette on 8th September, 1984 notifying the intention of State to acquire 105 Bighas 2 Biswas and 16 Biswanis (equivalent to 65.7125 acres) of lands.
The emergency provisions of Sections 17(1) and 17(4) of the Act were invoked. A declaration in terms of Section 6 of the Act was issued on 26th September, 1984. Notices were issued on 27th October, 1984 under Section 9 to the claimants for payment of compensation in respect of the acquired land.
Prior to taking over possession of land under the emergency powers, the Collector disbursed 80% of the amount of compensation determined. A possession certificate was issued by the Collector on 16th January, 1984
The site of the plant was shifted from Sarna, Murad Nagar to Dadri Tehsil. However, the Land Acquisition Officer despite the same proceeded to determine the amount of compensation payable for the acquisition of land.
An Award was made on 24th September, 1986.
On a reference in terms of Section 18 the amount of compensation @ Rs.155/- per sq. yards and Rs.115/-per sq. yds. in respect of two references was determined. .
First appeals were preferred thereagainst in February, 1984 by NTPC before the High Court. Inter alia on the premise that possession of the entire land of 65.713 acres had not been obtained, the District Magistrate was approached for issuance of a notification denotifying the acquisition of the balance area i.e. for withdrawal of acquisition of land admeasuring 55.498 acres.
On 11th November, 1994 the State of U.P. issued a Notification in terms of Section 48 of the Act.
Aggrieved, respondents filed a writ application before the High Court on or about 29th August, 1995 and a Division Bench of the High Court stayed the consequential effect of the Notification dated 11th November, 1994. On or about 9th September, 1997 the appellant filed an application for vacating the stay which having been refused, a Special Leave Petition was filed before this Court, which was dismissed by an order dated 14th October, 1997.
By reason of a judgment and order dated 21st July, 1998 the said writ petition was allowed.
Indisputably on the same day, the same Bench passed judgment in the First Appeals preferred by appellant (NTPC) against the order of the Reference Court dated 22nd October, 1993.
Finding of the Court:
There is no infirmity in the impugned judgment.
Result:
Appeal dismissed with cost.
Judgment :-
S.B. Sinha, J.
1. As all the cases involve similar questions of fact and law, they were taken up for hearing together and are being disposed of by this common judgment.
2. We may, however notice the fact of the matter involved in Civil Appeal Nos.6228-6229 of 2002.
Appellant is a Government of India Undertaking (NTPC). It is engaged in the business of generation of electricity. It, for the purpose of setting up of a Thermal Power Station at Village Sarna in the District of Ghaziabad in the State of Uttar Pradesh, submitted a proposal to the State of Uttar Pradesh for acquisition of lands situated in Village Dadri, Tehsil Ghaziabad, District Ghaziabad.
3. Pursuant or in furtherance of the said request, a Notification was issued in terms of Section 4 of the Land Acquisition Act, 1894 (for short `the Act) notifying the intention of State to acquire 105 Bighas 2 Biswas and 16 Biswanis (equivalent to 65.7125 acres) of lands situated at the aforementioned village. It was published in the Official Gazette on 8th September, 1984.
4. On the premise that generation of electricity was extremely urgent and National Capital Region faced acute shortage of electricity, the emergency provisions contained in Sections 17(1) and 17(4) of the Act were invoked. A declaration in terms of Section 6 of the Act was issued on 26th September, 1984. As the provisions of sub-section (4) of Section 17 of the Act were applied, notices were issued on 27th October, 1984 under Section 9 of the Act to the claimants for payment of compensation in respect of the acquired land.
5. However, admittedly prior to taking over possession of land under the emergency powers, the Collector disbursed 80% of the amount of compensation determined in terms of Section 17(3A) of the Act. A possession certificate was issued by the Collector on 16th January, 1984, which reads as under:-
"POSSESSION CERTIFICATE
LAND PERMANENT REQUIRED FOR THE PLANNED Industrial Construction of NTPC Plant, District Ghaziabad through the NTPC Ltd., Ghaziabad
Certified that I on behalf of the Collector, Ghaziabad have on this day the 16.11.1984 taken over the possession of the land detailed below comprising an area 105 B - 2Bs16B or 6751.3 acres and (not legible (name not ligible) of D.L.A.Os Office to hand over the possession of the same land to the NTPC Ltd., Ghaziabad.
Through Sri. D.V. (not ligible), village Sarna, Muradnagar, Pargana Jalalabad, District, Ghaziabad.
Sd/-
(District Land Acquisition Officer, Ghaziabad)
Notification u/s. 6 :- 7574/P-3-84-23-26
Land P-84__264-84 published on 29.9.84.
Certified that I on behalf of the Manager, NTPC Ltd., Ghaziabad have to take over possession of the abovementioned land through ____________________ today."
Khasra numbers and area of the plots, possession whereof had been taken, were specified therein.
6. Despite the same, the appellant contended that it had obtained the requisitioned physical possession of land admeasuring 10.215 acres only and the rest of the land continued to remain in possession of the land owners.
It is stated that the Ministry of Environment made recommendations that the choice of place for setting up a Thermal Power Station, having regard to its proximity to the National Capital being incorrect, the site thereof should be shifted. Pursuant thereto or in furtherance thereof, the site of the plant was shifted from Sarna, Murad Nagar to Dadri Tehsil. However, the Land Acquisition Officer despite the same proceeded to determine the amount of compensation payable for the acquisition of land.
7. An Award was made on 24th September, 1986.
A reference in terms of Section 18 of the Act was made which was answered by the learned Additional District Judge, Ghaziabad by a order dated 22nd October, 1993 determining the amount of compensation @ Rs.155/- per sq. yards and Rs.115/-per sq. yds. in respect of two references made separately before it. .
8. First appeals were preferred thereagainst in February, 1984 by NTPC be
Balwant Narayan Bhagde v. M.D. Bhagwat
Larsen & Toubro Ltd. v. State of Gujarat & Ors. (1998) 4 SCC 387
P.K. Kalburqui v. State of Karnataka & Ors. (2005) 12 SCC 489
Lt. Governor of Himachal Pradesh & Anr. v. Sri Avinash Sharma (1970 (2) SCC 149
Satendra Prasad Jain & Ors. v. State of U.P. & Ors. (1993) 4 SCC 369
Pratap & Anr. v. State of Rajasthan & Ors. (1996) 3 SCC 1
Tamil Nadu Housing Board v. A. Viswam(Dead) by Lrs. (1996) 8 SCC 259
State of Kerala & Ors. v. V.P. Kurien & Ors. (2005) 11 SCC 493
Smt. Gunwant Kaur & Ors. v. Municipal Committee
Babubhai Muljibhai Patel v. Nandlal Khodidas Barot (1974) 2 SCC 706
T.N. Housing Board v. Keeravani Ammal
Kasturi & Ors. v. State of Haryana (2003) 1 SCC 335
Ravi Khullar & Anr. v. Union of India & Ors.(2007) 5 SCC 231
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.