2010 (6) Supreme 129
SUPREME COURT OF INDIA
R.V. Raveendran and H.L. Gokhale, JJ.
M/s. Sumitomo Heavy Industries Limited — Appellant
versus
Oil & Natural Gas Commission of India — Respondent
Civil Appeal No. 3185 of 2002
Decided on : 28-7-2010
(1976) 4 SCC 147 – Relied upon
AIR 1965 SC 1288; (2005) 9 SCC 174 – Distinguished
(b) Contract – Clause 17.3 – It is confined only to the necessary and reasonable extra cost, caused by change in law occurring after the date of bid closing – The claim of appellant being restricted only to that extent, respondent is liable to pay the same. (Para 33)
(c) Arbitration Act, 1940 – Section 30 – If the arbitrator has taken one of the possible view of the matter, the court should not interfere with the award. (Para 35)
(2009) 10 SCC 63 – Relied upon
(d) Judicial Review – Perverse finding – It is a finding which is not only against the weight of evidence but altogether against the evidence – Instantly, the umpire’s award cannot be said to be perverse. (Para 36)
AIR 1994 SC 1341; (2009) 10 SCC 206 – Relied upon
(e) Arbitration Act, 1940 – Section 30 – The court while considering challenge to arbitral award does not sit in appeal over the findings and decision of the arbitrator. (Para 36)
(2009) 5 SCC 142 – Relied upon
(f) Arbitral award – Whether arbitrator can decide a question of law – Question left open. (Para 39)
(1973) 1 SCC 708; AIR 1984 SC 1072; JT 1999 (7) SC 379 – Referred
Facts of the case:
This case raises a question regarding the legality of award of the umpire in arbitration proceedings.
Finding of the Court:
The award does not suffer from any infirmity and does not warrant interference.
Result : Appeal allowed.
JUDGMENT
Gokhale, J. —
This appeal is directed against the judgment and order dated 19th December 2001 rendered by a Division Bench of the Bombay High Court in Appeal No. 126 of 2000 confirming the decision of a single Judge of that Court dated 29th November, 1999, in Arbitration Petition No. 104 of 1998 whereby the High Court has set aside the Award dated 27th June, 1995 made by the umpire in an Arbitration claim of the appellant against the respondent. The question involved in this appeal is as to whether as held by the Division Bench, the umpire had failed to apply his mind to the material on record and the clauses of the contract between the parties thereby rendering a perverse award, or whether his decision was a possible one and the High Court had erred in interfering therein.
2. The appellant had entered into a contract with the first respondent for installing and commissioning of Well-cum-Production Platform Deck and connected system including submarine pipelines on a turn-key basis at its Bombay High (South) Offshore Site for extraction of oil. The appellant had appointed M/s.Mc Dermott International Inc (in short ‘MII’) as the Sub-Contractor in execution of this work by a back to back contract to the full knowledge of the respondent. The appellant had sought from the respondent the reimbursement of the Income-tax amount which MII was required to pay to the Union of India under newly added Clause 44BB of the Income Tax Act 1961 (concerning the profits and gains in connection with the business of exploration of minerals) and which amount was paid by the appellant to MII. The respondent had declined to reimburse the tax amount.
3. The appellant, therefore, invoked the Arbitration clause in the agreement between the appellant and the respondent. The appellant contended that their liability had arisen due to change of law and that under clause 17.3 of the General Conditions of Contract forming part of the contract between the parties, the respondent was required to reimburse this amount since it was in the nature of necessary and reasonable extra cost arising out of change of law. (In the General Conditions of contract its clauses are referred to as sections.) As against this, the submission of the respondent was that they were responsible only for the appellant’s tax liability under clause 23 of the General Conditions, and if at all, it was the responsibility of the appellant under clause 13.2.7 thereof to take care of the obligations of the Sub-Contractor.
4. The two arbitrators appointed by the appellant and the respondent differed while deciding this claim of the appellant for reimbursement. This led to Sir Micheal Kerr entering the reference as the Umpire who has accepted appellant’s claim, by award dated 27.6.1995. By the said award, the umpire directed the respondent to pay the appellant the sum of Japanese Yen 129,764,463/- with interest at 4.5% per annum from 15.5.1991 to date of award. He declared that in the event of appellant becoming liable to pay further sums to MII thereafter, due to any assessment of income tax on MII under the present sub-contract pursuant to Section 44 BB of Income Tax Act, then Respondent shall indemnify the appellant against any such payment on demand. He awarded costs also. The respondent sought setting aside of the award of the umpire by invoking the jurisdiction of a learned single Judge of Bombay High Court under Clause - 30 of the Arbitration Act, 1940. The learned single Judge took the view that the said reimbursement by appellant to MII was a voluntary act on the part of the appellant and the terms of the contract did not require the respondent to reimburse the said income-tax amount to the appellant. The learned single Judge held that the construction placed by the umpire on clause 17.3 of the agreement was ‘clearly an impossible one’, and therefore, the Court would be justified in interfering with the findings and the award. The learned single Judge, therefore, allowed the Ar
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.