IN THE SUPREME COURT OF INDIA
V.S. Sirpurkar and Cyriac Joseph
Nand Kishore Gupta & Ors.... Appellants
Versus
State of U.P. & Ors....Respondents
CIVIL APPEAL NO. 7469 OF 2010
Arising out of SLP (C) No. 33958 of 2009
CIVIL APPEAL NO. 7468 OF 2010
Arising out of SLP (C) No. 33194 of 2009
Decided on : September 8, 2010
(b) Land Acquisition – Of large tract for Yamuna Expressway – Only insignificant number of farmers approaching Court to challenge the project – Large majority already accepting compensation – Project progressed substantially – Reached a point of no return. (Para 27)
(c) Land Acquisition – Private and public purpose – Allegation of colourable exercise of power to benefit the constructing Company – Company not in existence when project was conceived – Project cannot be said to have been envisaged keeping the Company in view – Judicial Enquiry Commission report duly accepted by both Houses of State Legislature – Division Bench of High Court dismissing PIL by well reasoned order – Remaining unchallenged – Bias in favour of the Company cannot be inferred. (Para 28)
(d) Land Acquisition Act, 1894 – Section 40 – Acquisition for Expressway – Company to construct the same on BOT basis – Land not to vest in the Company – To revert back to Government after project period – Company to pay cost of compensation as well as lease rentals to the Government – Section 40 not applicable. (Para 29)
(e) Land Acquisition Act, 1894 – Section 40 and 41 – Public purpose and public necessity – Public purpose is of much wider connotation than public necessity – Yamuna expressway and five proposed industrial towns, part of one integrated project – State to benefit immensely from the project – Merely because benefit of a project goes to a particular section of the society, the acquisition does not cease to be for the public purpose – Secondly, Company not paying compensation to farmers – It is depositing the same with YEIDA being the nodal agency, which in turn paying the compensation – Thirdly, land not vesting in Company – Reverting back to State after project period – Even during project period Company paying lease rental to YIEDA – Acquisition not for Company – It is for public purpose – Instrumentalities of State can invoke and exercise powers of eminent domain. (Para 34, 35)
(2003) 10 SCC 626; (2006) 4 SCC 683; (2008) 9 SCC 552; (1996) 10 SCC 632; (2007) 8 SCC 418; AIR 1960 SC 1203; AIR 1961 SC 343 – Relied upon
AIR 1963 SC 151; (2008) 1 SCC 728; (1971) 1 SCC 671; AIR 1965 SC 427 – Referred
(f) Land Acquisition Act, 1894 – Sections 17(1) and 17(4) – Urgency of acquisition and dispensing with enquiry u/s 5A – Enormousness of the Project requiring acquisition of 1,604 hectares of land involving 12,283 farmers, would have taken years if enquiry under Section 5A was permitted – Secondly if acquisition and the project was not completed expeditiously, large scale encroachments might have occurred greatly hampering the project – State Government considering materials on record and applying its mind to arrive at satisfaction about invoking urgency provision u/s 17(1) and (4) and dispensing with enquiry u/s 5A – No infirmity (Para 39, 40)
(2008) 14 SCC 716; (2002) 4 SCC 160; (1980) 2 SCC 471; (2009) 10 SCC 115; (2009) 2 SCC 377; (2009) 14 SCC 281; (2009) 10 SCC 689 – Relied upon
2007(9) ADJ 447 (DB); 2008 (3) ADJ 289 (DB); 2009 (8) ADJ 360 (DB) – Cited with approval
Civil Misc. Writ Petition No. 48978 of 2008; Civil Misc. Writ Petition No. 31314 of 2009 – Confirmed
(1998) 6 SCC 1 – Distinguished
Facts of the case:
A notification dated 20.2.2009 was issued by the Government of Uttar Pradesh under Section 4(1) read with Sections 17(1) and 17(4) of the Act. Thereunder, the lands described in the schedules appended thereto in District Agra, Pargana Etmadpur, Tehsil Etmadpur, Village Kuberpur were covered for a public purpose, namely, the construction of the interchange under the Yamuna Expressway Project in District Agra through Yamuna Expressway Industrial Development Authority
State came out with a notification dated 15.6.2009 under Section 6(1) read with Sections 17(1) and 17(4) of the Act. It is mainly the complaint of the appellants that they had purchased the land long time back and their names were duly mutated in the Revenue records and they had thereafter raised constructions over the land in question, and in those constructions, they were running their business like shops, cold-storage etc. The appellants also complained that the area which was proposed to be cleared for the interchange, if acquired, the appellants would suffer immensely. The appellants very seriously challenged the application of urgency under Sections 17(1) and 17(4) of the Act to these acquisitions, thereby depriving the appellants of an opportunity to be heard under Section 5A of the Act.
The other major challenge opposing the acquisition related to the concept of `public purpose’.
In the two impugned judgments, the Allahabad High Court has repelled all the challenges.
Finding of the Court:
There is no infirmity in the impugned judgment.
Result:
Appeals dismissed.
The two impugned judgments of the High Court i.e. Balbir Singh Vs. State of U.P., Civil Misc. Writ Petition No. 48978 of 2008 decided on 5.10.2009; and Nand Kishore Gupta Vs. State of U.P., Civil Misc. Writ Petition No. 31314 of 2009 decided on 30.11.2009 are confirmed.
JUDGMENT
V.S. SIRPURKAR, J.
1. This judgment will govern Special Leave Petition (Civil) Nos. 33194 of 2009, 33958 of 2009 and 35336 of 2009.
2. Leave granted in all the Special Leave Petitions.
3. In the first two Special Leave Petitions, judgment passed by the High Court of Judicature at Allahabad dated 30.11.2009, is in challenge while in the third Special Leave Petition, judgment dated 5.10.2009 on the same subject is impugned. By the impugned judgments, the Writ Petitions filed by the land owners challenging the notification under Sections 4 and 6 of the Land Acquisition Act, 1894 (hereinafter called `the Act' for short) relating to Yamuna Expressway Project, were dismissed by the High Court. In the Writ Petitions, directions were sought, firstly not to give effect to the notifications issued and further not to dispossess the landholders/ petitioners after demolishing their constructions on the lands which were proposed to be acquired. All the challenges were repelled by the High Court. The High Court, in the judgment dated 30.11.2009 passed in Civil Misc. Writ Petition No.31314 of 2009 (Nand Kishore Gupta & Ors. Vs. State of U.P. & Ors.), basically pointed out that out of 12,282 land owners, 11,397 had already received their compensation under the agreement and the challenge related only to 21.03 hectares out of 1,604 hectares of land. The High Court also took the view that the scales of justice must tilt towards the right to development of the millions who will be benefited from the road and the development of the area, as against the human rights of 35 petitioners therein, whose main complaint was that they were not heard before the declaration under Section 6 of the Act. The High Court also declined to give any direction to the State Government to consider to exempt 21.03 hectares of land relating to the 35 petitioners therein on account of the fact that the construction of the road had to be made in an alignment and that alignment could not be changed. Identical view was taken in another Writ Petition filed by one Balbir Singh. The High Court also expressed its concerns that any direction to exempt the land covered by the construction might seriously jeopardize the Project. The High Court also reiterated that the acquisition of the land for interchange of the road was the essential part of the Project, as also the construction of bridges, culverts and interchanges, which were essential for the fast moving six lane Expressway.
4. Before we approach the arguments, it would be interesting to see some facts of this litigation.
5. A notification dated 20.2.2009 was issued by the Government of Uttar Pradesh under Section 4(1) read with Sections 17(1) and 17(4) of the Act. Thereunder, the lands described in the schedules appended thereto in District Agra, Pargana Etmadpur, Tehsil Etmadpur, Village Kuberpur were covered for a public purpose, namely, the construction of the interchange under the Yamuna Expressway Project in District Agra through Yamuna Expressway Industrial Development Authority (hereinafter called `YEIDA' for short). In fact, in the year 2001 itself, the State Government had taken a decision for the construction of Yamuna Expressway which sometimes earlier was named as Taj Expressway, which was to proceed from Greater Noida to Agra. This was to be done on Build, Operate and Transfer (BOT) basis and the builder was to get the rights to collect the tolls for a period of 36 years from the date of commencement of commercial operations. On account of the public outcry, the State Government appointed a Commission of Enquiry under the Chairmanship of Mr. Justice Siddheshwar Narain (Retd.). A Public Interest Litigation was also filed. The Project was cleared in the enquiry and the Public Interest Litigation also ended in favour of the Government of U.P. It is on the backdrop of this that the State Government came up with a notification dated 20.2.2009, i.e. only after its way was cleared, which itself took about 8 yea
Pratibha Nema v. State of M.P.
State of Karnataka v. All India Manufacturers Organization
Sooraram Pratap Reddy v. District Collector, Ranga Reddy District
Naihati Municipality v. Chinmoyee Mukherjee
Dhampur Sugar (Kashipur) Ltd. v. State of Uttaranchal
Babu Barkya Thakur v. State of Bombay
Pandit Jhandu Lal v. State of Punjab
Smt. Somavanti v. The State of Punjab
Devinder Singh v. State of Punjab
Shyam Behari v. State of Madhya Pradesh
Sheikhar Hotels Gulmohar Enclave v. State of Uttar Pradesh
First Land Acquisition Collector v. Nirodhi Prakash Gangoli
State of Punjab v. Gurdial Singh
Manju Lata Agrawal v. State of U.P.
Sudhir Chandra Agrawal v. State of U.P.
Essco Fabs Pvt. Ltd. v. State of Haryana
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.