2011 Supreme(SC) 1146

ALTAMAS KABIR, CYRIAC JOSEPH
Yograj Infrastructure Ltd. – Appellant
Versus
Ssangyong Engineering & Construction Co. Ltd. – Respondent


ORDER

Altamas Kabir, J.

1. Interlocutory Application No.3 of 2011 has been filed by SSANGYONG Engineering & Construction Company Limited in disposed of Civil Appeal No.7562 of 2011, seeking clarification and correction of certain clerical errors in the judgment passed by this Court on 1st September, 2011, under Order XIII Rule 3 of the Supreme Court Rules, 1966.

2. Mr. Dharmendra Rautray, learned Advocate-on-Record, who had earlier appeared for SSANGYONG Engineering & Construction Company Limited, submitted that in paragraph 5 of the aforesaid judgment it had been mentioned that his clients had filed an application before the Sole Arbitrator on 5th June, 2010, for interim relief under Section 17 of the Arbitration and Conciliation Act, 1996. Mr. Rautray pointed out that the said application had been made not under Section 17 of the above Act, but under Rule 24 of the SIAC Rules and the same would be evident from the application made before the sole Arbitrator in SIAC Arbitration No.37 of 2010, by the Respondent, being Annexure-B to the present application.

3. Mr. Rautray then submitted that through inadvertence, in paragraph 35 of the judgment, it has been indicated that there was








Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top