SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2012 Supreme(SC) 47

SUPREME COURT OF INDIA
ASOK KUMAR GANGULY & JAGDISH SINGH KHEHAR, JJ.

STATE OF GUJARAT & OTHERS - Appellant(s)
VERSUS
ESSAR OIL LIMITED AND ANOTHER - Respondent(s)
Civil Appeal No 599 of 2012 (Arising out of SLP (C) No.17130/2008)-
Decided on 17-01-2012

IMPORTANT POINTS
Restitution is a remedy against unjust enrichment or unjust benefit.
In case of a mere erroneous judgment of a Court the principle of "actus curiae" cannot be invoked.

Headnote:(a) Administration of Justice – Restitution – It is a remedy against unjust enrichment or unjust benefit – When by an erroneous decree of the court a party is prevented from retaining money or some benefit derived from another, the court is obliged to order restitution to the party so prejudiced – If one party has not been unjustly enriched, no order of recovery can be made against that party – Alternately, when a party acquires benefits lawfully, which are not conferred by the party claiming restitution, Court cannot order restitution – High Court, on the ground that respondent could not commence production due to injunction granted by it, reducing tax liability by Rs.700 crores – State not receiving any unjust benefit or unjust enrichment by stay order of High Court – Principle of restitution cannot be applied against State. (Para 62, 67, 69)

       AIR 1953 SC 136; AIR 1966 SC 948 – Relied upon

       (2003) 8 SCC 648; (2010) 10 SCC 422; (2004) 2 SCC 783; (1988) Supp SCC 174; (2003) 2 SCC 716; (2005) 7 SCC 190 – Distinguished

       (b) Administration of law – Doctrine – "Actus curiae neminem gravabit" – An act of court cannot prejudice anyone – When a court passes a judgment per incuriam some binding precedent it is duty bound to correct the same – However, in case of a mere erroneous judgment of a Court the principle of "actus curiae" cannot be invoked. (Para 74)

       (1988) 2 SCC 602; (1869-71) LR 3 PC 465 – Relied upon

       (1984) 2 SCC 183; AIR 1952 SC 75 – Referred

       (c) Interpretation of statute – Exemption provisions – To be construed strictly – The principle that in case of ambiguity, a taxing statute should be construed in favour of the assessee, does not apply in case of an exception or an exempting provision – In case of doubt or ambiguity in exempting provision, benefit must go to the State – An exemption is a stand-alone process – Either an industry claiming exemption comes within it or it does not. (Para 88)

       (1994) Supp 3 SCC 606; (1990) 4 SCC 256 – Relied upon

       Facts of the case:

       Essar was encouraged by the State Government to set up a major venture at Vadinar in Jamnagar District of Gujarat as a 100% export oriented unit for refining of petroleum products in collaboration with M/s Bechtel Inc., USA.

       The clearance for setting up the oil refinery was granted by the Government of India.

       

       `No Objection Certificate’ and a Site Clearance Certificate was also granted by the GPCB.

       Permission under Section 2 of the Forest Conservation Act ("FCA") was required for the entire 15.49 hectares. At the same time, permission of State Government was required under the Wildlife Protection Act ("WPA").

       High Court directed Essar not to carry on any construction activity in the Marine National Sanctuary and Marine National Park in violation of the statutory provisions including the provisions contained in Wild life (Protection) Act, 1972.

       Government of Gujarat discontinued the said Scheme with effect from 01.01.2000.

       The time to start commercial production was extended to 01.01.2002.

       By judgment and order dated 13.07.2000, 18.07.2000, 20.07.2000, 27.07.2000 and 03.08.2000 the High Court restrained the Government of Gujarat from granting any more authorization and permission for laying down any pipeline in any part of the sanctuary or the national park. As a result of this order, Essar was not given permission to lay down pipelines by the State Government.

       Meanwhile, on 12.04.2001 the Government of Gujarat extended the time for going into commercial production upto 15.08.2003 for various pipeline units including Essar. By that time Essar had obtained Provisional Premier Unit Registration before 15.08.2000 and had also incurred 25% of the Project Cost before 15.08.2000 and therefore, it was entitled to the benefit of this extension.

       Supreme Court directed the State Government to issue the authorization to Essar in the requisite format under Sections 29 and 35 of the Wild Life (Protection) Act.

       The Chief Wild Life Warden issued the requisite permission on 27.02.2004.

       On 26.11.2006 Essar commenced commercial production and started paying sales tax on the products sold by it, under protest.

       By impugned order-dated 22.04.2008 the High Court excluded the intervening period from 13.07.2000 to 27.02.2004 and extended the time limit for commencement of commercial production from 15.08.2003 to 02.04.2007.

       Finding of the Court:

       Impugned judgment is not sustainable.

       Result: Appeal allowed.

JUDGMENT

Ganguly, J.-Leave granted.


2. This appeal is directed against the judgment of the High Court of Gujarat dated 22.04.2008 in Special Civil Application No.24233/2007, whereby the Respondent No. 1 herein, Essar Oil Limited (hereinafter "Essar") was given the benefit of Sales Tax incentive under the Government of Gujarat 1


"Capital Investment Incentive to Premier/Prestigious Unit Scheme, 1995-2000" (hereinafter "the said Scheme")


3. The State Government in the Industries and Mines Department vide Resolution dated 11.09.1995 introduced the said scheme to accelerate development of the backward area of the State and to create large-scale employment opportunities.


4. The operative period of the said scheme was from 16.08.1995 upto 15.08.2000, during which new units have to go into commercial production.


5. The Scheme envisaged grant of Sales Tax incentives by way of Sales Tax Exemption or Sales Tax Deferment or Composite Schemes, for Premier/Prestigious Units according to the location, investment and status of the project. Essar fell in the category of premier unit i.e. new industrial unit having a project cost of more than Rs.1,000/- crores and employing 100 workers on a regular basis and following the employment policy of the State Government. Clause (v) of the Scheme defined premier unit in the following terms:-


"(v) PREMIER UNIT


A new industrial unit or industrial complex fulfilling the following criteria will be considered for granting status of a "Premier Unit".


(a) The industrial unit shall have a project cost of Rs.500 crores or more. Such units having project cost of Rs.1,000 crores and above shall be entitled for extended period to avail incentive as provided under para 6 B.


(b) Only one unit per taluka will be eligible for the Premier Unit status. In banned area no unit is permitted.


(c) The unit shall employ at least 100 workers on a regular basis and shall follow the employment policy of the State Government."


6. Part II of the said Scheme provided that the rate of incentive would depend on the location, investment and status of the project. The incentives offered were sales-tax exemption or sales-tax deferment or composite scheme. There is no dispute about the fact that Essar opted for sales-tax deferment scheme. As per clause 6(i)(B), the rate of incentive applicable to Essar was the rate available for the most backward area. The extent of exemption was 125% of eligible fixed capital investment.


7. Part II Clause (iii) (b) provided that Under the Sales Tax Deferment incentive scheme, the recovery of sales tax connected by the unit on sale of goods manufactured by it including intermediate products, by products and scrap/waste generated as incidental to manufacturing activities and turnover tax, leviable to Government will be deferred and amount so deferred will be recovered in six equal annual installments by Sales Tax Department beginning from the financial year subsequent to the year in which the unit exhausts limit of incentive granted to it under the scheme or after the expiry of relevant period or time limit during which deferment is available or whichever is earlier.


8. Since Essar's investment was going to be more than Rs.1,000 crores, the duration of incentive of sales- tax deferment was to be for a period of 17 years from the date of commercial production.


9. Clause 6(v) of the said Scheme provided for effective steps for extending date of commercial production in the following terms :


"6(v) Effective steps for extending date of commercial production : The unit which cannot go into commercial production before expiry of the scheme will be allowed to go into commercial production beyond the last date of the scheme provided it has taken the following effective steps:


(1) The industrial unit should have obtained provisional registration as a Prestigious/Premier unit before 15th August 2000.


(2) 25% of project cost should have been incurred before 15th August 2000. The unit which has taken above


























































































































































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top