SUPREME COURT OF INDIA
Altamas Kabir, Markandey Katju
OM CONSTRUCTION CO. - APPELLANT
v.
AHMEDABAD MUNICIPAL CORP. & ANR. - RESPONDENTS.
Civil Appeal No. 107 of 2009
Decided on : January 13, 2009.
Arbitration and Conciliation Act, 1996 - Section 11 - Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 - Section 2(1)(k) - Arbitration proceedings - Appointment of Arbitrator - Appellant filed a petition inter alia, praying for the appointment of an Arbitrator to resolve the disputes between the parties - Held, Having arrived at the aforesaid conclusion, the only question that remains to be decided is whether this matter should be remitted to the High Court for appointment of an Arbitrator or whether we should ourselves appoint an Arbitrator in terms of the Arbitration Agreement - Remitting the matter to the High Court would only mean another round of litigation, whereas if the appointment is made by us, the matter will achieve finality, which would ultimately be beneficial for all concerned - Appeals allowed
JUDGMENT
ALTAMAS KABIR, J. :
Leave granted.
The appellant herein is a "C" class approved contractor, whose tender was accepted by the Ahmedabad Municipal Corporation for providing and fixing Nibhada Stone for paving and Footpath in Kalupur and Dariapur wards in Central Zone within the City of Ahmedabad. The Work Order was issued on 6th June, 2006, and as per the appellant's version the work was completed by the end of October, 2006. According to the appellant, after giving credit for payments which had been made by the Corporation, a sum of Rs. 68,46,872/- was still due towards the work performed in the Dariapur ward, while a sum of Rs. 8,61,760/- was also due for the work carried out in Kalupur ward. It is the case of the appellant that despite notice having been served on the Corporation on 24th May, 2007, the said amounts remained unpaid. Ultimately, on 6th June, 2007, the appellant issued a notice to the Corporation setting out the facts relating to the work performed and the claim made in detail and claimed a sum of Rs. 77,08,632/-, together with interest at the rate of 18% per annum, from the due date till the date of realization, which the appellant claimed, was the total outstanding amount. In the notice it was also indicated that the claim made by the appellant should be accepted and payment should be made within a period of 30 days from the date of receipt of the notice or that an Arbitrator should be appointed by the Corporation within a period of 30 days from the date of receipt of the notice.
As there was no response to the said notice from the Municipal Corporation nor was any payment made or Arbitrator appointed, the appellant invoked clause 30 of Form B-I, which provided for the appointment of an Arbitrator and was made applicable in the contract entered into between the parties when the appellant's tender was accepted. It appears that under General Conditions of Contract of the Engineering Department of the Ahmedabad Municipal Corporation, under its General Specifications it is provided that certain conditions are required to be followed which includes the condition that Form B-I would be applicable to the contract and clause 30 of Form B-I is relevant for this case. The relevant portions of clause 30 of Form B-I reads as follows :-
"Clause 30(1) Disputes to be referred to Tribunal : The disputes relating to this contract, so far as they relate to any of the following matters, whether such disputes arise during the progress of the work or after the completion or abandonment thereof, shall be referred to the Arbitration Tribunal, Gujarat State;
(2) ...............
(3) The provision of Arbitration Act, shall in so far as they are inconsistent with the provision of this Act, cease to apply to any dispute arising from a works contract and all arbitration proceedings in relation to such dispute before an Arbitrator, Court or authority shall stand transferred to the Tribunal."
The appellant filed a petition before the Gujarat High Court on 9th July, 2007, being Arbitration Petition No. 35 of 2007, under Section 11 of the Arbitration and Conciliation Act, 1996, hereinafter referred to as "the 1996 Act", inter alia, praying for the appointment of an Arbitrator to resolve the disputes between the parties. The High Court by its order dated 20th November, 2007, rejected the said petition. While doing so, the High Court took note of Section 2(1)(k) of the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992, hereinafter referred to as the "Gujarat Tribunal Act", which defines "works contract" to mean a contract made by the State Government or Public Undertaking which is notified in the Official Gazette by the State Government. The High Court also noticed Section 2(1)(l) of the aforesaid Act, which defines "Public Undertaking" to, inter alia, mean such class of local authorities as the State Government specifies by Notification in the Official Gazette. It was further noticed that in the absence of such No
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.