SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2009 Supreme(SC) 1188

SUPREME COURT OF INDIA
J M Panchal, R V Raveendran
M. K. ABRAHAM & CO., 2. VIJAY CONSTRUCTIONS - APPELLANT
v.
STATE OF KERALA & ANR. - RESPONDENTS.
Civil Appeal No. 4151 of 2009
Decided on : July 7, 2009.

Advocates appeared:
L. N. Rao, John Mathew, Rajeev George - Appellant.
R. Sathish - Respondent.

Headnote:

Arbitration & Conciliation Act, 1996 - Section 11 - Formal contract agreement - Appointment of arbitrator - Appellant filed a petition contending that the contract between the parties provides for settlement of disputes by arbitration and that in spite of appellant taking necessary pre-arbitration steps in terms of the arbitration clause, there was no compliance - Held, Court finds from the record that the respondents, apart from contending that there was no arbitration agreement at all, had also contended that the appellants had given full and final settlement receipt with a no claim undertaking in regard to the respective contract and therefore no dispute much less arbitral disputes can exist - As it held that there was no arbitration agreement, it did not examine the further objection of the respondents that there was a full and final settlement and consequently there is no arbitral dispute - In the absence of any material on that issue, Court is not in a position to decide the same - Appeals allowed

JUDGMENT

R. V. RAVEENDRAN, J.

Delay condoned as appellants were pursuing the remedy by way of writ petition till 14.12.2005. Leave granted.

FACTS (M.K. ABRAHAM & CO.)

A section of the work relating to NH-49 was awarded to the appellant under letter of acceptance dated 1.12.1999 issued by the second respondent [Project Director (SE), National Highway (ADB), Circle Edappally, Cochin]. A formal contract agreement was executed by them on the same day. By letter dated 9.10.2001, the appellant - contractor called upon the Executive Engineer, National Highways (Roads) Division to pay certain amounts as compensation for the losses caused on various accounts. The Executive Engineer denied the claim by a reply sent in December, 2001 contending that there was a full and final settlement of the claims by paying the amounts due under the final bill. Being dissatisfied with the said rejection, the appellant by notice dated 1.4.2002 called upon the Executive Engineer to refer the disputes in regard to its claims aggregating to Rs. 42,26,432.58 to arbitration. As there was no response, the appellant by letter dated 26.8.2002 nominated his arbitrator and called upon the second respondent to nominate the department's arbitrator in terms of the contract so that the Director-General (Road Development), Ministry of Surface & Transport, could nominate the Chairman - Arbitrator. The second respondent failed to comply. Therefore, the appellant by letter dated 28.10.2002 requested the Director-General to appoint the arbitrator on behalf of the employer as also the Chairman of the Arbitration Committee. As the Director-General also failed to comply, the appellant filed an application dated 9.4.2003 under section 11 of the Arbitration & Conciliation Act, 1996 (for short 'the Act'). The designate of the Chief Justice dismissed the application by order dated 19.12.2003.

FACTS (VIJAY CONSTRUCTIONS)

A section of the work relating to NH-49 was awarded to the appellant under letter of acceptance dated 7.9.2000 issued by the second respondent. A formal contract agreement was executed on 26.9.2000 between them. The work was completed on 30.4.2001. According to Appellant, the Executive Engineer informed him that unless it gave a no claim certificate, even the admitted dues would not be released. Under such coercion, it gave such a certificate on 23.1.2002, so that it can receive at least the admitted amounts. Immediately on receiving the admitted dues, the appellant claims to have informed the respondents by letter dated 2.2.2002 that it signed the no claim undertaking under coercion and therefore, it had no legal effect. It also called upon the respondent to redress its grievances and claims. As there was no response, the appellant by notice dated 19.8.2002 called upon the Executive Engineer, who was the "Engineer" under the contract to give his decision on its claims, in terms of the contract. As the "Engineer" failed to do so within 60 days, the appellant wrote to the Director-General (Road Development), Ministry of Surface & Transport on 26.10.2002, to appoint a sole Arbitrator to adjudicate upon the disputes. The appellant filed a petition under section 11 of the Arbitration & Conciliation Act, 1996 (for short 'the Act') contending that the contract between the parties provides for settlement of disputes by arbitration and that in spite of appellant taking necessary pre-arbitration steps in terms of the arbitration clause, there was no compliance. The designate of the Chief Justice dismissed the application by order dated 19.12.2003.

COMMON ISSUE

In both cases, the appellants contend that there is an arbitration agreement in their contracts dated 1.12.1999 and 26.9.2000. They submitted that each was entrusted a section of the project "National Highway 49 - Mathura Cochin Road" which was executed by the Ministry of Surface Transport, Government of India through the respect State Public Works Department. The Ministry of Surface Transport, Government of India,



































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top