SUPREME COURT OF INDIA
SURINDER SINGH NIJJAR & A.K. SIKRI, JJ.
Kashmir Singh – Appellant
Versus
State of Haryana & Others – Respondents
Civil Appeal No. 11030 of 2013 (Arising out of Special Leave Petition (Civil) No. 3711 of 2011) with C.A.No. 11031 of 2013 @ SLP(Civil) No. 3743 of 2011 C.A.No. 11032 of 2013 @ SLP(Civil) No.3776 of 2011 C.A.No. 11033 of 2013 @ SLP(Civil) No. 3791 of 2011 C.A.No.11034 of 2013 @ SLP(Civil) No.3901 of 2011 C.A.No.11035 of 2013 @ SLP(Civil) No.3909 of 2011 C.A.No.11036 of 2013 @ SLP(Civil) No.3911 of 2011 C.A.No.11037 of 2013 @ SLP(Civil) No.3914 of 2011
Decided On : 13-12-2013
Held: Going by the formula adopted in the aforesaid judgment, 12% per annum increase can be applied on the value of land determined as Rs.520/- per square yard in the year 1993, upto the year 2001 when the Notification under Section 4 of the Act was issued in the instant case. However, we cannot be oblivious to the fact that from 1993 to 2001, there was a period when instead of increase in the land price, there was attrition in the land rates. Therefore, we would like to enhance the value by applying the formula of 12% per annum increase for a period of 4 years, instead of taking entire period 1993 and 2001 (and this would not be treated as a precedent). When calculated in this manner, the valuation of the land in the year 2001 shall come to Rs.770/- per square yard. After making a deduction of onethird therefrom the net valuation comes to Rs.514/- per square yard. Compared to the land value of this very area in 1993 which was fixed at Rs.350/- per square yards, we have increased the same by about 50% over a period of 7 years or so, which we think, is quite reasonable as this much compensation is legitimately due to the appellants. We, accordingly, fix the compensation @ Rs.514/- per square yard for the acquired land of the appellants. The appeals are allowed to the aforesaid extent.
Result: Appeals allowed.
Judgment :-
A.K. Sikri, J.
1. Leave granted.
2. In all these appeals, challenge is laid to the judgment of the High Court pronounced on 20th September 2010, whereby number of appeals filed for enhancement of compensation under the Land Acquisition Act, 1894 (hereinafter referred to as the ‘LA Act’) were dismissed by the High Court. The land of the appellants was acquired by the Government of Haryana, which falls in the Revenue Estate of Tohana, Tehsil Tohana, District Fatehabad, Haryana. The Land Acquisition Collector (LAC) had assessed the market value of the acquired land @ Rs.2,75,000/- per acre for chahi, Rs.1,75,000/- per acre for Tibba/Tall and Rs.3,25,000/- per acre for gair mumkin land. The appellants had filed objections to the said determination of compensation by the LAC and the matter was referred to the learned Additional District Judge, Fatehabad under Section 18 of the LA Act. The learned ADJ passed the award dated 21.2.2006. Vide this award, he categorized the land into two categories, namely category-A and category-B and fixed the compensation of Rs.8,00,000/- per acre for category-A and Rs.6,50,000/- per acre for category-B. Still dissatisfied and aspiring for further enhancement of the compensation, the appellants filed Regular First appeal from the aforesaid orders of the learned ADJ. However, these appeals have been dismissed holding that the compensation as fixed by the learned ADJ is appropriate and does not call for any further enhancement. Feeling aggrieved, present appeals have been filed. Since the land of all the appellants is situate in Revenue Estate of Tohana, District Fatehabad, Haryana and is acquired by the same Notification, facts pertaining to the said Notification apply to all these appellants. The only difference is in the quantum of land which was owned by these appellants and has been taken away by the State in acquisition. Therefore, taking general note of the particulars of acquisition and the nature of land, would serve the purpose.
3. Notification under Section 4 of the Land Acquisition Act, 1894 was issued on 11.1.2001. This was published in official gazette on 08.01.2002. The land is situate in revenue estate of Tohana, District Fatehabad, Haryana. The public purpose mentioned was the construction of godowns and rice mills at Tohana, for HAFED (Haryana State Co-operative Supply and Market Federation Ltd.). In pursuance to the Land Acquisition Collector’s Award dated 19.9.2003, the acquired lands were taken possession on 17.12.2003. The Reference Court under Section 18 of the Act vide its award dated 21.2.2006 assessed the compensation @ Rs.8/- Lac per acre and Rs.6.50 Lac per acre by categorizing the acquired land in two categories, viz. Category-A and Category-B. Under Section 23 (1-A) of the Act, the escalation was fixed at 12% per annum on the assessed compensation. The other statutory benefits were also allowed thereby. The appeals filed by land owners before the High Court, seeking enhancement of compensation and the appeal filed by HAFED seeking reduction of compensation are decided by the High Court of Punjab and Haryana vide a common judgment dated 20.9.2010. Appeals of both the parties have been dismissed as noted above.
4. A perusal of the judgment of the High Court would reveal that though the appellants had produced on record certain sale deeds and other documents showing higher value of the land, the High Court chose to rely upon only one document, namely, Ex.P-15 which is a conveyance deed registered for sale by Haryana State Industrial Development Corporation (HSIDC) to the Central Warehousing Corporation (CWC). Vide this Conveyance Deed 34,475 square meters of land was sold by the HSIDC to CWC @ Rs.150/- per square meter. The allotment letter issued in this behalf was dated 4.9.2001 and from this the High Court inferred that process for sale must have been started much prior thereto. In the instant case, since the Notification under Section 4 of the LA Act is dated 11.1.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.