SUPREME COURT OF INDIA
Anil R. Dave, Dipak Misra, JJ.
Arasmeta Captive Power Company Pvt. Ltd. and another – Appellants
Vs.
Lafarge India Pvt. Ltd. – Respondent
[Civil Appeal No.11003 of 2013 arising out of SLP (Civil) No. 29651 of 2013]
Decided On : 12-12-2013
(2007) 4 SCC 599 - Relied upon
(b) Interpretation of Judgment - ratio decidendi - Case is only an authority for what it actually decides, and not what logically follows from it - One or two observations out of a long judgment do not constitute ratio decidendi - If more reasons than one are given, all are taken as forming the ratio decidendi - Ratio decidendi of a judgment has to be found out only on reading the entire judgment - Observations of Courts are neither to be read as Euclid's theorems nor as provisions of the statute and that too taken out of their context - Judgments interpret words of statutes; their words are not to be interpreted as statutes. (Paras 29, 31, 33 and 35)
(1987) 1 SCC 213; (1901) AC 495; (1990) 4 SCC 207; (1882) 7 App Cas 259 : 46 LT 826 (HL); (2006) 1 SCC 275; (2003) 6 SCC 697; (2012) 10 SCC 1; (2004) 3 SCC 75; (2008) 3 SCC 574; (2011) 5 SCC 532 - Relied upon
(2002) 2 SCC 388 - Referred
(c) Arbitration and Conciliation Act, 1996 - Section 11(6) - Question whether there is a dispute relating to excepted matters under the agreement in question or not - Designated Judge not justified in deciding the same on merit - Designated Judge deciding whether a dispute is billing dispute - Not permissible - Same should have been left to the Arbitrator. (Para 42)
(2013) 1 SCC 641; (2005) 8 SCC 618; (2009) 1 SCC 267(2009) 1 SCC 267; (2007) 4 SCC 599 - Relied upon
AIR 2001 SC 499; (2011) 13 SCC 258 - Referred
Facts of the case:
The appellant and the respondent entered into an agreement whereby the appellant was to generate and supply power to the respondent as power two PPAs signed on two different dates.
After some time disputes arose between the parties which the appellant termed as 'billing dispute' and requested the respondent to appoint an expert to resolve the same. The respondent instead moved the High Court for appointment of an arbitrator.
The High Court opining that the dispute did not come within the category of 'billing dispute' and appointed an arbitrator.
Finding of the Court:
Designate Judge erred in deciding the issues on merit whereas they should have been left to the arbitrator.
Result : Appeal allowed partly.
Dipak Misra, J.
1. Leave granted.
2. In Government of Andra Pradesh and others v. A. P. Jaiswal and others, AIR 2001 SC 499 a three-Judge Bench has observed thus:- "Consistency is the cornerstone of the administration of justice. It is consistency which creates confidence in the system and this consistency can never be achieved without respect to the rule of finality. It is with a view to achieve consistency in judicial pronouncements, the Courts have evolved the rule of precedents, principle of stare decisis etc. These rules and principle are based on public policy..."
3. We have commenced our opinion with the aforesaid exposition of law as arguments have been canvassed by Mr. Ranjit Kumar, learned senior counsel for the appellants, with innovative intellectual animation how a three-Judge Bench in Chloro Controls India Private Limited v. Seven Trent Water Purification Inc. and others, (2013) 1 SCC 641 has inappositely and incorrectly understood the principles stated in the major part of the decision rendered by a larger Bench in SBP & Company v. Patel Engineering Ltd. and another, (2005) 8 SCC 618 and, in resistance, Mr. Harish Salve and Dr. A.M. Singhvi, learned senior counsel for the respondent, while defending the view expressed later by the three-Judge Bench, have laid immense emphasis on consistency and certainty of law that garner public confidence, especially in the field of arbitration, regard being had to the globalization of economy and stability of the jurisprudential concepts and pragmatic process of arbitration that sparkles the soul of commercial progress. We make it clear that we are not writing the grammar of arbitration but indubitably we intend, and we shall, in course of our delineation, endeavour to clear the maze, so that certainty remains "A Definite" and finality is 'Final'.
4. The present appeal, by special leave, is directed against the judgment and order dated 22.7.2013 passed by the learned Judge, the designate of the Chief Justice of the High Court of Chhattisgarh at Bilaspur, in Arbitration Application No. 24 of 2012 whereby and whereunder, while dealing with an application preferred under Section 11(5) and (6) of the Arbitration and Conciliation Act, 1996 (for brevity "the Act"), has repelled the submission of the appellant herein, the respondent in the original proceedings, that the disputes raised by the applicant, being excepted matters, were squarely covered within the ambit of clause 9.3 of the agreement and hence, it was only to be referred to an expert for resolution and not to an arbitrator and, further addressing the issue on merits, opined that as the disputes are not covered under the subject-matter of billing disputes that find place in clause 9.3 of the agreement, the parties are not under obligation to refer the matter to the expert, and, accordingly, called for the names from both the parties and taking note of the inability expressed by the counsel for the respondents therein, appointed an arbitrator to adjudicate the disputes that have arisen between the parties.
5. Regard being had to the narrow compass of the controversy that has emanated for consideration before this Court, we need not dwell upon the factual matrix in extenso. Suffice it to state that the appellant No. 1 is a company carrying on business in generation of power. The respondent owns 49% equity of the appellant No. 1 company and the appellant No. 2 owns 51% equity of the appellant No. 1 company. The appellant-company had entered into two agreements with the respondent for supply of power to the respondent. The first agreement, namely, a Power Purchase Agreement (PPA) was entered into on 10.2.2005 and the second agreement of similar nature was entered into on 1.11.2007 for supply of power.
In course of subsistence of the agreements dispute arose between the parties relating to amounts that is due and payable. The appellants treated the dispute raised to be a "billing dispute" and sought to appoint an expert in accordanc
Government of Andra Pradesh v. A. P. Jaiswal
Chloro Controls India Private Limited v. Seven Trent Water Purification Inc.
SBP & Company v. Patel Engineering Ltd.
APS Kushwaha (SSI Unit) v. Municipal Corporation, Gwalior
National Insurance Company Limited v. Boghara Polyfab Private Limited
Shree Ram Mills Ltd. v. Utility Premises (P) Ltd.
Ambica Quarry Works v. State of Gujarat
Krishena Kumar v. Union of India
State of Orissa v. Mohd. Illiyas
Islamic Academy of Education v. State of Karnataka
Natural Resources Allocation, In Re, Special Reference No. 1 of 2012
Union of India v. Amrit Lal Manchanda
Som Mittal v. Government of Karnataka
Konkan Railway Corporation Ltd. v. Rani Construction (P) Ltd.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.