SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2014 Supreme(SC) 253

SUPREME COURT OF INDIA
Surinder Singh Nijjar, JJ.
Reliance Industries Ltd. & Ors. – Appellants
Vs.
Union of India – Respondent
[Arbitration Petition No. 27 of 2013]
Decided On : 31-03-2014

IMPORTANT POINT
In international arbitration a foreign national not of the nationality of any of the parties should be appointed as the third and presiding arbitrator.

Headnote:(a) Arbitration and Conciliation Act, 1996 – Section 11(6) – Petitioner 1 – whether acting on behalf of all three petitioners – Respondent granting approval to Petitioner No.1 to assign 30% of its Participating Interest under the PSC to BP, thereby also making BP a partner in the Block KG-D6 – Reference to arbitration by petitioner no. 1 was on behalf of all three partners – Petitioner no. 1 serving notice for arbitration as Operator – Capacity of Operator included all the three petitioners – Therefore arbitration petition has been filed by all the three petitioners. (Para 48, 49)

       (b) Arbitration and Conciliation Act, 1996 – Section 11(6) – Dispute between the parties clearly identified in the correspondence – Disputes raised by petitioner no. 1 also includes disputes of other two petitioners. (Para 52)

       (C) Arbitration and Conciliation Act, 1996 – Section 7 – Petitioner no. 1RIL is an Indian Company – Petitioner no. 2 Niko is a Company incorporated in Cayman Islands, British Virgin Islands – Petitioner No.3 BP is a company incorporated according to the laws of England & Wales – PSC signed by all the three petitioners as well as the respondent, UoI – Arbitration by invoking arbitration clause in the PSC is an international arbitration. (Para 54)

       (d) Arbitration and Conciliation Act, 1996 – Section 11(6) – Parties already appointing one arbitrator each – Not open to the respondent at this stage to raise plea about non-existence of dispute. (Para 55)

       (e) Administration of Justice – Approbation and Reprobation – UOI contending on the one hand that arbitral award would bind all the three petitioners – On the other hand, insisting that arbitration proceeding is only between petitioner no. 1 and UOI – Not tenable. (Para 57)

       (f) Arbitration and Conciliation Act, 1996 – Section 11(6) r/w Articles 33.5 And 33.6, PSC, and, Article 11(5), UNCITRAL Model Law and Article 6(4), UNCITRAL Rules, 1976 – Third arbitrator – Nationality – International arbitration problems necessarily have to be viewed pragmatically – Neutrality of third arbitrator – To ensure, the third arbitrator should be from nationality other than the parties to the arbitration. (Para 58)

       (g) Interpretation of statute – Arbitration and Conciliation Act, 1996 – Section 11 uses similar phraseology as Article 11, UNCITRAL Model Law – same can be used as legitimate aid to interpret section 11. (Para 67)

       (h) Arbitration and Conciliation Act, 1996 – Section 11 r/w Article 33.6, PSC – Section 11(1) – No agreement between the parties to chose third arbitrator from India only – Section 11(9) specifically empowering CJI to appoint an arbitrator of a nationality other than the nationality of the parties involved in the litigation. (Para 68)

       (2008) 10 SCC 240; (2001) 1 SCC 509 – Relied upon

       2013 (7) SCALE 216 – Referred

        (i) Arbitration and Conciliation Act, 1996 – Section 11(6) – Both parties appointing one Indian arbitrator each – Instantly, seat of arbitration is in India – Applicable law is Indian Law – Does not oblige Court to appoint third arbitrator who is an Indian national. (Para 72)

       (2005) 13 SCC 719 – Relied upon

       (j) Arbitration and Conciliation Act, 1996 – Section 11(6) – Appointment of a foreign national as third and presiding arbitrator – Apprehension of lack of knowledge of Indian Laws – Parties have already appointed one retired CJI each – Apprehension unfounded. (Para 79)

       Facts of the case:

       In 1999, UOI announced a policy-New Exploration and Licensing Policy ("NELP"). Under NELP, certain blocks of hydrocarbon reserves were offered for exploration, development and production to private contractors under the agreements which were in the nature of Production Sharing Contract (PSC). One of the said blocks was Block KG-DWN-98/3 ("Block KG-D6"). The joint bid made by the Petitioners No.1 and 2 for the Block KG-D6 was accepted by the UOI. Thereafter 'PSC' was executed between the Petitioners No.1 and 2 as Contractor on one side and UOI on the other. The Arbitration Agreement in the PSC is contained in Article 33.

       On 8th August, 2011, UOI granted its approval to the Petitioner No.1 to assign 30% of its participating interest in the Block KG- D6, under the PSC to Petitioner No.3. On the same date, i.e. 8th August, 2011, Petitioner No. 3 also entered into PSC as a party. Further, Petitioner No.1 was appointed as the 'Operator' for Block KG-D6, both under the terms of the PSC, and the Joint Operating Agreement that was executed between Petitioner No. 1 and Petitioners No. 2 & 3.

       In the financial year 2010-2011, differences relating to the scope and interpretation of the provisions of the PSC arose between the Petitioners and Respondent after the publication of some media reports.

       On 23rd November, 2011, Petitioner No.1 (RIL), through its Advocates, served upon the Respondent a notice invoking arbitration, in accordance with the arbitration agreement contained in Article 33 of the PSC. In this letter, Petitioner no.1 also nominated Mr. Justice S.P. Bharucha, former Chief Justice of India, as its arbitrator and called upon the Respondent to nominate its arbitrator within 30 days of the receipt of this letter.

       In its letter dated 5th July, 2012, the Respondent stated that the Ministry had nominated Mr. Justice V.N.Khare, former Chief Justice of India as the arbitrator on behalf of the Government of India.

       Both the arbitrators failed to appoint the third arbitrator.

       In these circumstances the present arbitration petition has been filed under Section 11(6) of the Arbitration Act, 1996.

       Finding of the Court:

       A foreign national not of the nationality of any of the parties should be appointed as the third and presiding arbitrator.

       

Judgment :

SURINDER SINGH NIJJAR,J.

1. This petition has been filed under Section 11(6) of the Arbitration Act, 1996, with a prayer for appointment of the third and the presiding arbitrator, as the two arbitrators nominated by the parties have failed to reach a consensus on the appointment of the third arbitrator.

2. Petitioner No.1 is a company incorporated and registered under the provisions of the Companies Act, 1956; Petitioner No.2 is a company incorporated in Cayman Islands, British Virgin Islands; Petitioner No.3 is a company incorporated according to the laws of England & Wales. The Respondent herein is Union of India (hereinafter referred to as "UOI"), represented by the Joint Secretary, Ministry of Petroleum and Natural Gas.

3. Briefly stated, the relevant facts are as under:

4. In 1999, UOI announced a policy-New Exploration and Licensing Policy (hereinafter referred to as "NELP"). Under NELP, certain blocks of hydrocarbon reserves were offered for exploration, development and production to private contractors under the agreements which were in the nature of Production Sharing Contract. One of the said blocks was Block KG-DWN-98/3 ("Block KG-D6"). The joint bid made by the Petitioners No.1 and 2 for the Block KG-D6 was accepted by the UOI. Thereafter on 12th April, 2000, Production Sharing Contract (hereinafter referred to as 'PSC') was executed between the Petitioners No.1 and 2 as Contractor on one side and UOI on the other. The Arbitration Agreement in the PSC is contained in Article 33. Relevant facts thereof, is in the following words:

"ARTICLE 33 SOLE EXPERT, CONCILIATION AND ARBITRATION

33.1 * * *

33.2 * * *

33.3 Subject to the provisions of this Contract, the Parties hereby agree that any controversy, difference, disagreement or claim for damages, compensation or otherwise (hereinafter in this Clause referred to as a "dispute") arising between the Parties, which cannot be settled amicably within ninety (90) days after the dispute arises, may (except for those referred to in Article 33.2, which may be referred to a sole expert) be submitted to an arbitral tribunal for final decision as hereinafter provided.

33.4 The arbitral tribunal shall consist of three arbitrators. Each Party to the dispute shall appoint one arbitrator and the Party or Parties shall so advise the other Parties. The two arbitrators appointed by the Parties shall appoint the third arbitrator.

33.5 Any Party may, after appointing an arbitrator, request the other Party(ies) in writing to appoint the second arbitrator. If such other Party fails to appoint an arbitrator within thirty (30) days of receipt of the written request to do so, such arbitrator may, at the request of the first Party, be appointed by the Chief Justice of India or by a person authorised by him within thirty (30) days of the date of receipt of such request, from amongst persons who are not nationals of the country of any of the Parties to the arbitration proceedings.

33.6 If the two arbitrators appointed by or on behalf of the Parties fail to agree on the appointment of the third arbitrator within thirty (30) days of the appointment of the second arbitrator and if the Parties do not otherwise agree, at the request of either Party, the third arbitrator shall be appointed in accordance with Arbitration and Conciliation Act, 1996.

x --------------- x ---------------x ------------x -----------x

33.12 The venue of the sole expert, conciliation or arbitration proceedings pursuant to this Article, unless the Parties agree otherwise, shall be New Delhi, India and shall be conducted in the English language. Insofar as practicable, the Parties shall continue to implement the terms of this Contract notwithstanding the initiation of arbitral proceedings before a sole expert, conciliator or arbitral tribunal and any pending claim or dispute.

33.13 * * *"

5. On 8th August, 2011, UOI granted its approval to the Petitioner No.1 to assign 30% of its participating interest in the Block KG- D6, under the PS








































































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top