SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2014 Supreme(SC) 227

SUPREME COURT OF INDIA
GYAN SUDHA MISRA & PINAKI CHANDRA GHOSE, JJ.
Executive Director, Steel Authority of India & Others – Appellants
Versus
Tycoon Traders & Others – Respondents
Civil Appeal No. 4026 of 2014 [Arising out of Special Leave Petition (Civil) No.12463 of 2012]
Decided On : 26.03.2014

Headnote:Wildlife (Protection) Act, 1972 – Section 38(v) – E – auction of 1.00 lakh metric tons of iron ore by ‘SAIL’ – Declaration of Respondent No.1 as the successful tenderer – SAIL addressed a letter to the Principal Chief Conservator of Forests (Wildlife) and Chief Wildlife Warden, Karnataka, for renewal of permission granted for lifting and transporting iron ore fines through Bhadra Wildlife Sanctuary – The Principal Chief Conservator of Forests declined to grant such permission for the removal of 1.00 lakh tons of iron ore fines by plying vehicles – High Court in writ petition held that the contract itself stood frustrated and could not have been performed by the respondent even if it desired to do so, and that in case of frustrated contract, parties must be restored to their original position – Appeal – Held contract was unenforceable and was also hit by Section 38(v) of the Wildlife (Protection) Act, 1972 as amended in 2006 – Hence object of contract was forbidden by law – Said contract was unlawful and could not be given effect to – High Court held correct in allowing the writ petition – No reason to interfere with said order of High Court – Appeal dismissed(paras8,9)

       Facts of the Case – The facts of the case reveal that Steel Authority of India had advertised for E – auction of 1.00 lakh metric tons of iron ore (fines) from Kemmanagundi mines. Auction was held and respondent No.1 was declared as the successful tenderer.The entire material was to be lifted within four months from the date of the sale order. On May 26, 2010, SAIL informed the respondent that the contract was revalidated for a period of four months commencing from July 27, 2009 and that the said contract had expired on the lapse of the said period. It is also not in dispute that SAIL had addressed a letter to the Principal Chief Conservator of Forests (Wildlife) and Chief Wildlife Warden, Karnataka, for renewal of permission granted for lifting and transporting iron ore fines through Bhadra Wildlife Sanctuary. The Principal Chief Conservator of Forests by letter dated March 31, 2010, declined to grant such permission for the removal of 1.00 lakh tons of iron ore fines by plying vehicles. In these circumstances, the High Court held that the contract itself stood frustrated and could not have been performed by the respondent even if it desired to do so, and further held that in case of frustrated contract, parties must be restored to their original position.

       B. Present appeal has been filed against said order passed by High Court.

       Findings of the Court – The Apex Court held that contract was unenforceable and was also hit by Section 38(v) of the Wildlife (Protection) Act, 1972 as amended in 2006. Hence object of contract was forbidden by law. Said contract was unlawful and could not be given effect to. High Court held correct in allowing the writ petition. There was no reason to interfere with said order of High Court. Appeal was dismissed.

       

Judgment : –

Pinaki Chandra Ghose, J. –

1. Leave granted.

2. This appeal has been filed against the order dated February 21, 2012 passed by the High Court of Karnataka in W.P. No.38280/2011.

3. The facts of the case reveal that on February 19, 2007, Steel Authority of India (for short ‘SAIL’) had advertised for E – auction of 1.00 lakh metric tons of iron ore (fines) from Kemmanagundi mines. On March 13, 2007, auction was held and respondent No.1 was declared as the successful tenderer. It would be evident from the sale order dated March 16, 2007 that the price was agreed upon at [pic]1,132/ – per metric ton plus VAT of 4% aggregating to [pic]11,32,00,000/ – plus VAT of 4%. The appellant duly paid [pic]176 lakhs being 15% of the total sale value on March 15, 2007. Out of the said amount, [pic]58.86 lakhs being 5% of the total sale value was retained as Security Deposit and a sum of [pic]117.74 lakhs was kept for adjustment along with the final instalment. The balance payment was to be made in two monthly instalments with the grace period of 30 days with interest at the rate of 6% per annum. The entire material was to be lifted within four months from the date of the sale order.

4. On May 26, 2010, SAIL informed the respondent that the contract was revalidated by letter dated July 27, 2009 till November 26, 2009 for a period of four months commencing from July 27, 2009 and that the said contract had expired on the lapse of the said period. It is also not in dispute that on November 9, 2009, SAIL had addressed a letter to the Principal Chief Conservator of Forests (Wildlife) and Chief Wildlife Warden, Karnataka, for renewal of permission granted for lifting and transporting iron ore fines through Bhadra Wildlife Sanctuary. The Principal Chief Conservator of Forests by letter dated March 31, 2010, declined to grant such permission for the removal of 1.00 lakh tons of iron ore fines by plying vehicles. In these circumstances, the High Court held that the contract itself stood frustrated and could not have been performed by the respondent even if it desired to do so, and further held that in case of frustrated contract, parties must be restored to their original position.

5. On the basis of the aforesaid reason, the High Court held that it is illegal and unconscionable for SAIL not to refund the entire sum of money received by it from the respondent. The High Court further held that the extension was granted at the instance of SAIL and such extension amounts to waiver of the delivery conditions in the sale order dated March 16, 2007. The High Court further held that the Bhadra Wildlife Sanctuary has been declared as a ‘Tiger Reserve’ and that it is required to be maintained as ‘inviolate’ for tiger population, and the permission which has been refused cannot be granted in view of section 38(v) of the Wildlife (Protection) Act, 1972 as amended in 2006. In this background, the writ petition was allowed and SAIL was directed to refund the entire amount within four weeks from the date of the order.

6. Being aggrieved, the appellant filed the present appeal before this Court. It was contended before us that this is a case where there was a breach of contract which was committed by the respondent and thereby SAIL has a right to forfeit the earnest money and security deposit on the basis of such breach. It is also stated whether it would come within the purview of a case of frustration of the contract. Dr. Rajiv Dhawan, learned senior counsel appearing in support of the appellants, has drawn our attention to the original agreement and contended that there was a breach of the original agreement since no clearances were obtained, payments were not made and further contract was not completed. It has been further submitted that the respondent could not lift the iron ore fines although SAIL could manage to get permission from the State Government. Furthermore, it is the case of the appellant that in the light of the respondent’s request, the contra



Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top