SUPREME COURT OF INDIA
G.S. Singhvi and H.L. Gokhale, JJ.
Municipal Corporation of Greater Mumbai and Ors. - Appellants
Vs.
Kohinoor CTNL Infrastructure Company Private Limited and Anr. - Respondent
Special Leave Petition (Civil) No. 33402 of 2012
Decided On: 25.07.2013
Constitution of India – Articles 14, 19, 21 and 48 – Maharashtra Regional and Town Planning Act, 1966 – Section 51 – Cause Affidavits – Competent Authority – Plans submitted by Respondent for construction of Wings-A, B and C of the building were sanctioned by competent authority of Municipal Corporation of Greater Mumbai and Intimation of Disapproval was issued on Ministry of Environment and Forests, Government of India granted clearance for construction of commercial building competent authority issued commencement certificate – Commissioner of Police (Traffic) issued NOC development of a multi-storied public parking lot and vide letter State Government granted in-principle approval under Clause 33(24) of Development Control Regulations (DCR) for Greater Mumbai, 1991 for construction of a multi-storied public parking lot – Held, Questions in light of statistics of population in the island city of Mumbai availability of the roads therein, and incidents of fire which have taken place in island city require assistance of Municipal Corporation of Greater Mumbai and State of Maharashtra for this purpose issues have become urgent particularly for the residents of island city which is not disputed by learned senior counsel for Petitioners as well as Mr. Nariman, learned senior counsel appearing for Respondents we feel that although Petitioners and Respondents may be permitted to proceed with the settlement that they have arrived at, this SLP be kept alive so that Mr. Salve and can assist us on these issues in public interest – Ordered accordingly –
ORDER
G.S. Singhvi, J.
Part-I
1. This petition is directed against order dated 9.7.2012 passed by the Division Bench of the Bombay High Court whereby Writ Petition No. 143/2012 filed by the Respondents was allowed and stop work notice dated 22.12.2011 issued by Executive Engineer (Building Proposal) City-III, Municipal Corporation of Greater Mumbai and order dated 27.4.2012 passed by the Additional Municipal Commissioner restricting the height of Wing 'C' of the buildings being constructed on Plot No. 46 of Town Planning Scheme - III, N. Kelkar Road, Shivaji Park, Mumbai to ground and 4 upper floors were quashed.
2. The plans submitted by Respondent No. 1 for construction of Wings-'A', 'B' and 'C' of the building were sanctioned by the competent authority of the Municipal Corporation of Greater Mumbai (for short, 'the Corporation') and Intimation of Disapproval was issued on 15.2.2006. After the Ministry of Environment and Forests, Government of India granted clearance for the construction of commercial building, the competent authority issued commencement certificate dated 13.9.2006. The Joint Commissioner of Police (Traffic) issued NOC dated 11.12.2009 for the development of a multi-storied public parking lot and vide letter dated 2.6.2010, the State Government granted in-principle approval under Clause 33(24) of the Development Control Regulations (DCR) for Greater Mumbai, 1991 for construction of a multi-storied public parking lot. Thereafter, the competent authority issued the Letter of Intent dated 27.7.2010.
3. During the construction of the building, the Urban Development Department of the State Government sent letter dated 4.3.2011 to the Municipal Commissioner requiring him to submit a proposal for amendment of Clause 33 (24) of the DCR for limiting the height of parking towers to 4 floors and also for revocation of all sanctioned proposals where the commencement certificates had not been issued. In view of that letter, the Corporation issued circular dated 22.6.2011 prescribing certain conditions under Clause (iv) of DCR 33(24) and clarified that all proposals for public parking lots shall be considered subject to those conditions. The new conditions sought to limit the height of public parking to ground plus 4 upper floors and 2 basements.
4. As a sequel to the above changes, the Corporation issued notice dated 29.11.2011 to Respondent No. 1 under Section 51 of the Maharashtra Regional and Town Planning Act, 1966 requiring it to show cause as to why the commencement certificate may not be revoked. Respondent No. 1 submitted detailed reply dated 14.12.2011 and pleaded that the amended DCR 33(24) cannot be made applicable to its buildings because substantial construction had already been made at a cost of Rs. 167/- crores. Thereafter, the concerned Executive Engineer issued stop work notice dated 22.12.2011 and directed Respondent No. 1 to restrict the work of public parking to 4 floors instead of 13 floors. After about six months, Additional Municipal Commissioner passed order dated 27.4.2012, the relevant portion of which is extracted below:
As there is a substantial construction on core part of the plot, PPL done in this part shall be allowed to the extent of already executed construction as per report dated 27/12/2011. In the remaining portion of the plot, where there is no substantial construction, PPL shall be limited to G + 4, Developer is to be asked to modify his plans in consonance with modified DCR.
5. The Respondent challenged the stop work notice and the order of the Additional Municipal Commissioner in Writ Petition No. 143/2012, which was allowed by the High Court in the following terms:
In the facts of this case, the admitted position as accepted in the order of the Additional Municipal Commissioner indicates that the work of development had substantially progressed by the time a notice to show cause was issued under Section 51 of the M.R. & T.P. Act, 1966. The impugned order passed by the Additional Municipal
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.