SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2014 Supreme(SC) 669

SUPREME COURT OF INDIA
J. CHELAMESWAR & A.K. SIKRI, JJ.
Orissa Manganese & Minerals Ltd. – Appellant
Versus
Synergy Ispat Pvt. Ltd. – Respondent
CIVIL APPEAL NO. 8645 OF 2014
Decided on: 12-09-2014

Headnote:Arbitration & Conciliation Act, 1996 – Section 9 – Appellant and respondent entering into an agreement to sell iron ore extracted by appellant through Metsil to the respondent – Agreement with Metsil found to be contrary to Rules – Terminated – Agreement with respondent also terminated – Matter before arbitral tribunal to adjudicate on specific performance of the agreement – Appellant extracting the ore by itself and using it captively – Giving undertaking not to sell the ore to any third party – Respondent, if succeeding in arbitral proceeding, can always claim compensation for losses – Injunction declined. (Para 23)

       Facts of the case:

       The appellant secured a mining lease originally from the State of Bihar (now Jharkhand) in the year 1996. However, the appellant could not secure the necessary approval under the Forest Conservation Act, 1980. Therefore, the mining operation had to be kept under suspension.

       Sometime in the year 2005-2006, at the instance of the respondent herein, the appellant entered into two agreements. According to the appellant, one of the agreements is that the mining activity pursuant to the mining lease secured by the appellant, shall be carried on by M/s. Metsil Exports Pvt. Ltd. (Metsil) which is said to be an associate company of the respondent.

       The second agreement is between the appellant and the respondent herein for the sale of iron ore extracted by Metsil for being utilised in a sponge iron plant to be jointly set up by the appellant and the respondent herein.

       The appellant realised on 22nd June, 2007 that the contract with Metsil is in violation of Rule 37 of the Mineral Concession Rules, 1960. Therefore, the appellant sent letters to the respondent as well as to Metsil purporting to terminate both the contracts. Metsil never questioned the termination of the contract.

       Subsequent to the decision of the appellant to terminate both the agreements, the appellant commenced the mining operation from January 2009.

       The respondent filed an application under Section 9 of the Arbitration and Conciliation Act, 1996 praying, inter alia, for an order of injunction restraining the appellant herein from selling iron ore to the third party.

       The learned single Judge of the Calcutta High Court declined to grant any ad interim order as sought by the respondent.

       8. Thereafter, the respondent preferred another application in which an interim order came to be passed restraining the appellant herein from selling any part of the iron ore extracted from the mines in question without first offering the entire extract to the respondent.

       The appellant carried the matter in appeal under Section 37(1)(a) of the Arbitration and Conciliation Act, 1996 before a Division Bench of the High Court. By a consent order the parties agreed for the appointment of one Shri Pradeep Kumar Ghosh, Senior Advocate, as the Arbitrator to adjudicate upon the dispute between the parties. The said A.P.O.T. came to be finally disposed of with a direction that the appellant would sell iron ore to the respondent, if the respondent so opted, at the prevailing market price during the pendency of the arbitration proceedings.

       The impugned order is a reversing order in appeal against the judgment and order of single Judge of the Calcutta High Court by which the learned single Judge rejected an application filed under Arbitration & Conciliation Act, 1996 holding that the appellant was not entitled to interim injunction in aid of his claim for specific performance of an agreement to sell iron ore.

       Finding of the Court:

       In view of captive use of the iron ore and appellant’s undertaking not to sell the ore to any third party, there is no need to grant injunction.

       Result: Appeal disposed of.

JUDGMENT

J. Chelameswar, J.

1. Leave granted.

2. Aggrieved by the judgment dated 16th May 2014 of the High Court of Calcutta in A.P.O.T. No.460/2012, the respondent therein filed this appeal.

3. The impugned order is a reversing order in appeal against the judgment and order dated 5th September, 2012 of single Judge of the Calcutta High Court in A.P. No.245/2012 by which the learned single Judge rejected an application filed under Arbitration & Conciliation Act, 1996 holding that the appellant was not entitled to interim injunction in aid of his claim for specific performance of an agreement to sell iron ore.

4. The factual background of the case is as follows.

5. The appellant herein secured a mining lease originally from the State of Bihar (now Jharkhand) in the year 1996. However, the appellant could not secure the necessary approval under the Forest Conservation Act, 1980. Therefore, the mining operation had to be kept under suspension.

6. Sometime in the year 2005-2006, at the instance of the respondent herein, the appellant entered into two agreements. According to the appellant (we say so because what exactly is the purport of the agreements is a matter pending consideration in arbitration, therefore, we do not wish to make any definite statement in that regard), one of the agreements is that the mining activity pursuant to the mining lease secured by the appellant (referred to supra), shall be carried on by M/s. Metsil Exports Pvt. Ltd. (Metsil) which is said to be an associate company of the respondent herein on various terms and conditions, the details of which may not be necessary. The agreement is dated 27.2.2005 between the appellant herein and Metsil. The agreement is styled as ‘Raising Contract’. The second agreement is between the appellant and the respondent herein for the sale of iron ore extracted by Metsil for being utilised in a sponge iron plant to be jointly set up by the appellant and the respondent herein. According to the appellant, both the contracts are inter dependent. Failure of the first contract automatically results in failure of the second contract.

7. However, the appellant claims to have realised on 22nd June, 2007 that the ‘Raising Contract’ by which the activity of mining was sought to be entrusted to Metsil is in violation of Rule 37 of the Mineral Concession Rules, 1960, therefore, the appellant sent letters to the respondent as well as to the Metsil purporting to terminate both the contracts. It is stated at the Bar that, admittedly, Metsil never questioned the termination of the contract. However, the respondent company chose to dispute the legality of the decision of the appellant in terminating the agreement for sale of iron ore. The respondent filed an application (A.P. No.922/2011) under Section 9 of the Arbitration and Conciliation Act, 1996 praying, inter alia, for an order of injunction restraining the appellant herein from selling iron ore to the third party. It may be mentioned here that subsequent to the decision of the appellant to terminate both the agreements, the appellant commenced the mining operation from January 2009. The learned single Judge of the Calcutta High Court, by his order dated 14.11.2011, declined to grant any ad interim order as sought by the respondent. By an order dated 14.3.2012, the said A.P. No.922/2011 was disposed of.

8. Thereafter, the respondent preferred another application in A.P. No.245/2012 in which an interim order came to be passed on 29.3.2012 restraining the appellant herein from selling any part of the iron ore extracted from the mines in question without first offering the entire extract to the respondent. Aggrieved by the same, the appellant herein carried the matter in appeal under Section 37(1)(a) of the Arbitration and Conciliation Act, 1996 before a Division Bench of the High Court in A.P.O.T. No.184/2012. By a consent order dated 17.4.2012 in the abovementioned A.P.O.T., the parties agreed for the appointment of one Shri Pradeep K























Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top