SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2014 Supreme(SC) 732

SUPREME COURT OF INDIA
J. CHELAMESWAR, A.K. SIKRI, JJ.
M/S. IVT (IB VALLEY TRANSPORT), VLT (VIJAY LAXMI PVT. LTD.), CC (COAL CARRIERS) (JV) - APPELLANTS
VERSUS
CHAIRMAN-CUM-MANAGING DIRECTOR MAHANADI COALFIELDS LTD. & ORS. - RESPONDENTS
CIVIL APPEAL NO. 9394 OF 2014 (ARISING OUT OF SLP (C) NO. 39122 OF 2013)
Decided on : 10-10-2014

IMPORTANT POINT
Alternative remedy should be exhausted before filing writ petition.

Headnote:Government contract – Dispute resolution – Clause 12 providing mechanism for dispute resolution – Accordingly, appellant was supposed to write to the Engineer Incharge for resolving the dispute – Instead appellant writing to to the Staff Officer (Mining) – Appellant not availing departmental remedy provided under Clause 12, before filing the writ petition – Not proper – Appellant directed to exhaust remedy under Clause 12 before taking recourse to any suitable legal remedy. (Para 14, 15)

       Facts of the case:

       The respondents floated a tender for “transportation of surface miner coal fact to Kanika Railway Siding and transportation of surface miner reject to face to surface miner reject dump of Kulda OCP, Basundhara Garjanbahal Area”. The period of contract for the said NIT was for three years and the estimated value of the work was Rs.63,68,45,000/-.

       Work order was awarded to the appellant but the site was handed over only after 22 months from the date of letter of acceptance. As such the appellant started execution of the contract with effect from June 07, 2011. The contract was performed upto June 06, 2014.

       A dispute arose between the parties about the rate at which payment of revised wages is to be made by the appellant to all contract workers engaged in the mining activities.

       Clause 37.06 of NIT514 contained Wage Compensation Formula. On September 28, 2012, the Central Government issued another notification for the revision of the Minimum Wages in Mines and Establishment falling under the Government of India. The appellant has been paying the workers wages at the aforesaid revised rates with effect from January 01, 2013.

       The respondents through a letter dated June 21-22, 2013 directed the appellant that it shall pay to all contract workers engaged in the mining activities, pursuant to NIT-514, the revised wages as per the recommendation of the High Power Committee of Coal India Limited contained in its Circular No. CIL/C-5B/ JBCCI/HPC/566 dated February 18, 2013.

       The appellant, vide letter dated June 29, 2013, intimated the respondents that it is ready and willing to accept the rate derived considering the Wage Compensation Formula as per the clause inserted in the contract of other NITs, the work of which is in progress in the same project (Kulda OCP), even though there is no provision of Wages Escalation/Compensation Formula in the contract awarded to the appellant. The appellant started paying the revised wages to the contract workers as per the directions of the respondents vide letter dated June 21-22, 2013.

       The respondents issued orders dated August 06, 2013 calling upon the appellant to pay wages at the rate of Rs.279/-(basic wage Rs.180/-plus Rs.99/-as variable dearness allowance) as base rate of minimum wages.

       According to the appellant, the mode of calculating the base rate of minimum wage by taking into consideration rates prescribed in Government Notification dated November 28, 2012 is per se erroneous.

       The appellant objected to the basic wage as calculated by the respondents and intimated its willingness to accept the rate derived considering the Wage Compensation Formula as per the aforesaid clause in NIT-514. Since no reply was received, the appellant filed writ petition.

       High Court has dismissed the writ petition on the ground that the dispute between the parties arises out of a commercial contract and, therefore, remedy for adjudication thereof by way of writ petition under Article 226 of the Constitution is not available.

       The High Court has, thus, observed that such a dispute has to be settled either in a suit or in other proceedings in accordance with the contract.

       Finding of the Court:

       Appellant ought to have exhausted departmental remedy before approaching the High Court.

       Result: Appeal disposed of.

ORDER :

A.K. SIKRI, J.

Leave granted.

2) In this appeal, the appellant is challenging the validity of orders dated November 21, 2013 passed by the High Court of Orissa in Writ Petition (Civil) No. 22022 of 2013 whereby the High Court has dismissed the writ petition on the ground that the dispute between the parties arises out of a commercial contract and, therefore, remedy for adjudication thereof by way of writ petition under Article 226 of the Constitution is not available. The High Court has, thus, observed that such a dispute has to be settled either in a suit or in other proceedings in accordance with the contract.

3) The brief facts which are discernible from the record are that the respondents floated a tender, i.e. NIT No. MCL/SBP/GM(TC)/ NIT-514 (hereinafter referred to as 'NIT-514') dated November 1819, 2008 for “transportation of surface miner coal fact to Kanika Railway Siding and transportation of surface miner reject to face to surface miner reject dump of Kulda OCP, Basundhara Garjanbahal Area”. The period of contract for the said NIT was for three years and the estimated value of the work was Rs.63,68,45,000/-(rupees sixty three crores sixty eight lacs and forty five thousand only). The appellant also submitted its bid and, on evaluation thereof, emerged as the Lowest Tenderer (L1). This resulted in the issuance of the letter of acceptance dated March 20, 2009 which was served upon the appellant and the first work order was issued on May 18, 2009. As per the appellant, it is only after 22 months from the date of letter of acceptance i.e. on June 7, 2011, the site was handed over to the appellant. As such the appellant started execution of the contract with effect from June 07, 2011. The contract was performed upto June 06, 2014.

4) A dispute arose between the parties which is about the rate at which payment of revised wages is to be made by the appellant to all contract workers engaged in the mining activities. It originated under the circumstances mentioned hereinafter.

5) It so happened in the Work Order dated May 18, 2009, working details were described pursuant to NIT-514. Clause 37.06 of NIT514 contained Wage Compensation Formula, which will be referred to by us later at the appropriate stage. What is relevant to point out at this stage is that on September 28, 2012, the Central Government issued another notification for the revision of the Minimum Wages in Mines and Establishment falling under the Government of India. It prescribed the minimum wages for workers working above the ground for the categories of unskilled as Rs.186/-, semi-skilled as Rs.231/-, skilled/clerical as Rs.279/-and highly skilled as Rs.324/-. According to the appellant, it has been paying the workers wages at the aforesaid revised rates with effect from January 01, 2013.

6) While the appellant was executing the said work, the first communication in regard to the payment of revised wages was made by the respondents through a letter dated June 21-22, 2013 directing therein that the appellant shall pay to all contract workers engaged in the mining activities, pursuant to NIT-514, the revised wages as per the recommendation of the High Power Committee of Coal India Limited contained in its Circular No. CIL/C-5B/ JBCCI/HPC/566 dated February 18, 2013. In this letter, the respondents had categorically stated that there is no provision of Wage Escalation/Compensation Formula in the contract awarded to the appellant. However, if the appellant had any reservation/ grievance in paying the revised wages to the workers, the appellant ought to submit a written representation.

7) In reply to the aforesaid letter, the appellant, vide letter dated June 29, 2013, intimated the respondents that it is ready and willing to accept the rate derived considering the Wage Compensation Formula as per the clause inserted in the contract of other NITs, the work of which is in progress in the same project (Kulda OCP), even though there is no provision of Wages E














Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top