SUPREME COURT OF INDIA
T.S. Thakur and A.K. Goel, JJ.
Construction and Design Services – Appellant
Vs.
Delhi Development Authority – Respondent
Civil Appeal Nos. 1440-1441 of 2015 (Arising out of SLP (C) Nos. 35365-35366 of 2012)
Decided On : 04-02-2015
Indian Contract Act - Sections 73 and 74 - Whether burden of proving that amount stipulated as damages for breach of contract was penalty is on person committing breach - Nature of penalty in absence of evidence - Levy of compensation - These appeals have been preferred against final judgment and order and passed by High Court of Delhi at New Delhi - Question raised for our consideration is when and to what extent can stipulated liquidated damages for breach of a contract be held to be in nature of penalty in absence of evidence of actual loss and to what extent stipulation be taken to be measure of compensation for loss suffered even in absence of specific evidence. Further question is whether burden of proving that amount stipulated as damages for breach of contract was penalty is on person committing breach – Held, Applying above principle to present case it could certainly be presumed that delay in executing the work resulted in loss for which Respondent was entitled to reasonable compensation- Evidence of precise amount of loss may not be possible but in absence of any evidence by party committing breach that no loss was suffered by party complaining of breach Court has to proceed on guess work as to quantum of compensation to be allowed in given circumstances - Since Respondent also could have led evidence to show extent of higher amount paid for work got done or produce any other specific material but it did not do so Court are of view that it will be fair to award half of amount claimed as reasonable compensation - Accordingly this appeal is partly allowed and the decree granted by High Court is modified to effect that Respondent-Plaintiff is entitled to half of amount claimed with rate of interest as awarded by High Court - Out of amount deposited in this Court Respondent will be entitled to withdraw said decrial amount and Appellant will be entitled to take back remaining - Appeals disposed of
JUDGMENT
A.K. Goel, J.
1. Leave granted.
2. These appeals have been preferred against final judgment and order dated 10thFebruary, 2012 in RFA(OS) No. 35 of 2010 and dated 1st June, 2012 in R.P. No. 369 of 2012 in RFA (OS) No. 35 of 2010 passed by the High Court of Delhi at New Delhi.
3. The question raised for our consideration is when and to what extent can the stipulated liquidated damages for breach of a contract be held to be in the nature of penalty in absence of evidence of actual loss and to what extent the stipulation be taken to be the measure of compensation for the loss suffered even in absence of specific evidence. Further question is whether burden of proving that the amount stipulated as damages for breach of contract was penalty is on the person committing breach.
4. The Respondent-Delhi Development Authority awarded a contract vide agreement dated 4th October, 1995 to the Appellant for constructing a sewerage pumping station at CGHS area at Kondli Gharoli at Delhi. Clause 2 in the agreement provided as follows:
the contractor shall comply with the said time schedule. In the event of the contractor failing to comply with this condition, he shall be liable to pay as compensation an amount equal to one percent or such smaller amount as the Superintending Engineer Delhi Development Authority (whose decision shall be final) may decide on the said estimated cost of the whole work for everyday that the due quantity of work remains incomplete; provided always that the entire amount of compensation to be paid under the provisions of this clause shall not exceed ten percent of the estimated cost of work as shown in the tender.
Since the work proceeded at slow pace and the Appellant-Defendant failed to complete the same, the contract was terminated on 17th September, 1999. Under Clause 2 of the agreement, the Superintending Engineer of the Respondent levied compensation of Rs. 20,86,446/- for delay in execution of the project by an order of penalty dated 21st July, 1999 and called upon the Appellant to deposit the same. The said order reads thus:
The work was being executed by you at extremely slow pace. You had to complete the job by 7.1.97. You had failed to complete the work even after expiry of 2 years six months after stipulated date of completion. Despite the clear direction from Hon'ble Supreme Court to expedite the work and complete the job by June-99, you have failed to comply the direction of Court and have rather abandoned the work since 6.4.99 and you failed to complete the work till date.
In exercise of the power conferred on me Under Clause-2 of the agreement, I, R.C. Kinger, the SE/CC-10/DDA decide and determine that you are liable to pay Rs. 20,86,446/- (Rs. Twenty lacs eighty six thousand four hundred forty six only) as and by way of compensation as stipulated in clause-2 of the agreement.
5. On failure of the Appellant to respond to the above order, the Respondent filed suit No. 1311 of 2002 before the Delhi High Court for recovery of the said amount with interest. The Appellant-Defendant failed to contest the suit inspite of service but made an application raising objection to the maintainability of the suit on the ground that vide order dated 19th December, 2001, a former Judge of Delhi High Court had been appointed arbitrator to decide the disputes arising out of the contract. The said application was, however, dismissed on the ground that the matter in the suit was not within the purview of the arbitration. The Court proceeded to decide the suit on merits.
6. Learned single Judge dismissed the suit holding that the Plaintiff had not treated the time fixed for performance of the contract as of essence and the compensation stipulated in Clause 2 of the agreement was in the nature of penalty. The basis for levy of compensation had not been indicated so as to determine whether the compensation claimed was reasonable. Reliance was placed on the judgment of this Court in Arosan Enterprises Ltd. v. Union of India and
Arosan Enterprises Ltd. v. Union of India and Anr. (1999) 9 SCC 449
Fateh Chand v. Bal Kishan Das (1964) 1 SCR 515
Maula Bux v. Union of India (1969) 2 SCC 554
M.L. Devendra Singh v. Syed Khaja (1973) 2 SCC 515
P. DSouza v. Shondrilo Naidu (2004) 6 SCC 649
Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 : AIR 2003 SC 2629
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.