SUPREME COURT OF INDIA
Madan B. Lokur, N.V. Ramana, JJ.
Delhi Development Authority – Appellant
Versus
Kenneth Builders & Developers Ltd. & Ors. – Respondents
Civil Appeal No. 5370 of 2016 (Arising out of S.L.P. (Civil) No. 35374 of 2010) With Civil Appeal No. 5371 of 2016 (Arising out of S.L.P. (Civil) No. 13146 of 2011)
Decided on : 29-06-2016
(b) Environmental law – DPCC requiring ridge demarcation report to issue “consent to establish” – DDA not providing the report – Kenneth Builders taking all necessary steps to commence the construction activity – Failed due to impasse created by the governmental agencies – Section 56, Indian Contract Act, 1872 attracted. (Para 32)
(c) Indian Contract Act, 1872 – Section 56 – “Impossible” – Means impracticable and useless in the context of the object and purpose of the contract – Impossibility arising due to some contemplated intervening or supervening circumstance – Contract will not be frustrated – Instantly, prohibition on construction activity on the project land falling within the Ridge or having morphological similarity to the Ridge not contemplated by DDA – Making performance of the contract impracticable – Held, contract frustrated. (Para 33, 34, 39)
(1954) SCR 310 – Relied upon
MANU/DE/1815/2010 CA; (2013) 8 SCC 198 – Referred
(d) Environmental law – Area falling within the Ridge – No construction activity permissible on the Ridge – Government of India notifying project land as “Residential” – Shown as such in MPD-2001 and MPD-2021 – But exact boundaries of Ridge not demarcated – In absence of such demarcation position of law will not change by the said notification or Master Plan – Held this circumstance frustrated the contract Section 56, Indian Contract Act, 1872. (Para 35)
(e) Interpretation of contract – “As is where is basis” – Relates only to physical issues pertaining to the project land and ancillary or peripheral legal issues pertaining to the actual construction activity, such as compliance with the building bye-laws, environmental clearances etc – Obtaining environmental clearances not extending to commencement of construction activity prohibited by law except after obtaining permission of the Ridge Management Board and Supreme Court – Reliance by DDA on clauses 6 and 11 of the Development Agreement misplaced (Para 37, 38)
(2012) 8 SCC 197 – Relied upon
Facts of the case:
The project land was notified on 1st August, 1990 for “Recreation” (District Park) in the Master Plan for Delhi -2001 (MPD-2001). Two notifications were issued by the Ministry of Urban Development of the Government of India on 8th January, 2002 and 23rd February, 2006 converting the project land from “Recreation” (District Park) to “Residential”.
On 20th March, 2006 the DDA issued an advertisement for involving the private sector in Delhi’s development and for the development of the project land for the construction of 750 residential flats and 3500 resettlement houses.
Kenneth Builders was the highest bidder in the auction held on 26th April, 2006 and its bid was accepted. On 15th June, 2006 a demand-cum-allotment letter was issued to it requiring payment of balance 75% of the bid amount. It is not in dispute that Kenneth Builders deposited the entire bid amount of Rs. 450.01 crores with the DDA on 11th September, 2006.
Pursuant to the deposit of the entire bid amount by Kenneth Builders, a no objection certificate was issued by the DDA on November, 2006 for submission of building plans for the project to the Planning Department of the DDA. Thereafter possession of 11.70 hectares of the project land was handed over to Kenneth Builders but an area of approximately 2.60 hectares covered by the JJ cluster was left out and possession thereof was not given.
A Development Agreement was signed between the DDA and Kenneth Builders whereby it was agreed, inter alia, that Kenneth Builders would construct 3500 houses for the resettlement of slum dwellers and 750 free sale flats which Kenneth Builders would be entitled to dispose of. Kenneth Builders would also develop roads and peripheral services for the entire project.
It was the responsibility of Kenneth Builders to obtain various approvals and clearances from the appropriate authorities including environmental agencies of the State and the Central Government.
However objection of the Department of Forests compelled Kenneth Builders to stop all building activity on the project land.
The DDA insisted that the project land was “Residential” and that the project could be undertaken thereon. The GNCTD was equally clear that the project land falls within the Ridge and no construction activity could be carried out without the consent of the Ridge Management Board and the permission of Supreme Court. The Ministry of Environment and Forest, Government of India (MoEF) kept aloof from the controversy and gave environmental clearance for the project subject to the condition that a “consent to establish” shall be obtained by Kenneth Builders from the DPCC under the Water (Prevention and Control of Pollution) Act, 1974 (for short the Water Act) and the Air (Prevention and Control of Pollution) Act, 1981 (for short the Air Act) and a copy submitted to the said Ministry before the start of any construction work at the site.
Kenneth Builders applied to the DPCC for “consent to establish”. The DPCC required Kenneth Builders to submit a “ridge demarcation report” at the earliest.
The DDA did not give any such report to Kenneth Builders on the ground that the issue had already been clarified to the GNCTD in a letter dated 17th October, 2008.
The High Court held that in the event the DPCC does not give its “consent to establish” and the project cannot be carried out then Kenneth Builders would be entitled to a return of the entire amount (with interest at the rate of 6% till realization) paid by it to the DDA since the project would stand frustrated and would be incapable of performance.
Finding of the Court:
Contract is frustrated.
Result: Appeal filed by DDA dismissed. Question raised in the connected appeal filed by the GNCTD and the Department of Forests of the GNCTD is left open.
JUDGMENT :
Madan B. Lokur, J.
1. Delay condoned. Leave granted in both petitions.
2. The appellant (Delhi Development Authority or the DDA) in the first appeal is aggrieved by the judgment and order dated 30th July, 2010 passed by a Division Bench of the High Court of Delhi in W.P.(C) No. 10647 of 2009. [Kenneth Builders and Developers Ltd. v. Union of India and others, MANU/DE/1815/2010 CA] The grievance of the DDA is that even though the High Court held that the project land that we are concerned with was “Residential” as contended by the DDA, yet the High Court held that in the event construction activity thereon is not permitted by the Delhi Pollution Control Committee (or the DPCC) the developer (Kenneth Builders) would be entitled to a refund of the entire amount deposited with the DDA pursuant to the acceptance of the developer’s bid in an auction, along with interest thereon.
3. In the connected appeal, the appellants (Government of the National Capital Territory of Delhi or the GNCTD and its Department of Forests) are aggrieved by the same judgment and order to the extent that it has been held that the DDA is the final authority to determine land use, even though its determination pertains to the Ridge in the National Capital Territory of Delhi.
4. Before referring to the facts of the case, which we have taken from the appeal filed and argued by the DDA, we would like to mention that there has been protracted correspondence between the DDA, Kenneth Builders and the Secretary (Environment) cum Chairman of the Delhi Pollution Control Committee of the GNCTD. However, we are of opinion that it is not necessary to detail the contents of every letter between them and we propose not to burden this judgment with avoidable details, as long as the narrative does not suffer.
5. The principal question that arises for our decision is whether the development agreement between the DDA and the developer Kenneth Builders was frustrated within the meaning of Section 56 of the Indian Contract Act, 1872 due to some intervening circumstances not contemplated by either party. Our answer to the question is in the affirmative.
The facts of the case
6. The DDA proposed a public-private partnership project for the development of an area of 14.3 hectares of prime land at Tehkhand in South Delhi for the construction of 750 premium residential flats in a self contained community to be sold by private real estate development on free sale basis. In addition to the premium residential flats, the developer would have to construct 3500 resettlement houses for the economically weaker sections of society with each house having a super area of 26 sq. metres. These resettlement houses and the developed common facilities relating thereto would be handed over to the DDA for allotment.
7. According to the DDA (and there is no dispute about this) the project land was notified on 1st August, 1990 for “Recreation” (District Park) in the Master Plan for Delhi -2001 (MPD-2001). According to the DDA (and again there is no dispute in this regard) two notifications were issued by the Ministry of Urban Development of the Government of India on 8th January, 2002 and 23rd February, 2006 converting the project land from “Recreation” (District Park) to “Residential”.
8. On 20th March, 2006 the DDA issued an advertisement for involving the private sector in Delhi’s development and for the development of the project land for the construction of 750 residential flats and 3500 resettlement houses. Pursuant to the advertisement, an auction was held by the DDA in terms of the Delhi Development Authority (Disposal of Developed Nazul Land) Rules, 1981 on an “as is where is basis” and as per the terms and conditions prescribed for the auction.
9. The terms and conditions for the auction specifically mentioned that the bid would be for the amount of premium offered for the project land to execute the project and that the project was being offered on an “as is where is basis”. It was stated t
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.