SUPREME COURT OF INDIA
ANIL R. DAVE AND ADARSH KUMAR GOEL, JJ.
GUJARAT URJA VIKAS NIGAM LTD. – APPELLANT
VERSUS
ESSAR POWER LIMITED – RESPONDENT
CIVIL APPEAL NO. 3455 OF 2010
Decided On : 09-08-2016
(b) Interpretation – Instruments – Power Purchase Agreement (PPA) – Subsequent development – Respondent acknowledging its liability of allocating the generated power to the appellant and to the ESL in the ratio of 58 : 42 – Tribunal’s non-reliance on referred letters of acknowledgment – Erroneous and without any basis – Liable to be set aside. (Para 24)
(c) Administration of justice – Judicial propriety – Tribunal holding appellant in default for making payment of L 519 crores and it was breach of promise – Tribunal therefore holding respondent absolved from its obligation to supply power as per the agreement – Erroneous in the face of the records – Liable to be set aside. (Para 26, 27)
(d) Constitution of India – Articles 323A and 323B – Establishment of various Tribunals – Administration of justice by Tribunals – Leaves much to be desired – Constitution thereof – Selection of Chairpersons and Members – Need for review of composition of Tribunals under the Electricity Act or other corresponding statutes emphasissed – Sections 113(b)(i) to (iii) and 113(3) read with Section 78, Sections 84, 85 and 125 of the Electricity Act and corresponding provisions of similar Acts need a fresh look – Jurisdiction of such tribunals require review. (Para 33)
(1997) 3 SCC 261; (2014) 10 SCC 1 – Relied upon
(e) Administration of justice – Constitution of India – Article 136 – Many statutes providing direct appeal to Supreme Court from the decisions of the tribunals – Converting Supreme Court into a regular court of appeal – Straying from its original character as a constitutional court and the apex court of the country – Looking into the issue by Law Commission suggested. (Para 36, 37, 41, 43)
(2010) 4 SCC 358; (1986) 4 SCC 767 – Relied upon
Facts of the case:
Correct interpretation of the terms of Power Purchase Agreement is the issue in this case.
The appellant, Gujarat Urja Vikas Nigam Ltd. (`the GUVNL'), is the successor of the Gujarat Electricity Board and is a deemed licencee. The respondent, ESSAR Power Limited (`the EPL'), is a generation company. The appellant filed a petition before the (Regulatory) Commission for adjudication of the dispute arising out of the Power Purchase Agreement (`the PPA'). The appellant inter alia sought compensation for wrongful allocation of electricity by the EPL to its sister concern, Essar Steel Ltd. (ESL) in preference to the appellant.
The Commission upheld the plea of limitation raised by the respondent to the extent that the appellant was held entitled to its claims only for three years preceding the filing of the petition, i.e., from 14th September, 2002, the petition having been filed on 14th September, 2005.
The (Appellate) Tribunal upheld the said finding.
The Tribunal also upheld the order of the Commission accepting the claim of the appellant under the head of a Deemed Generation Incentive and the respondent has not challenged this aspect.
The Tribunal held that the PPA did not require the EPL to declare the capacity in the ratio of 300: 215 MW.
The Tribunal also held that non-declaration of available capacity on proportionate basis was not shown to have resulted in any loss or damage to GUVNL. The Electricity Board (R-1) cannot claim that by reasons of it's making payment for the Annual Fixed Charges up to the allocated capacity, it was always obligatory on the part of the EPL to supply power to the extent of 58% to the Electricity Board and that since EPL has sold a part of Electricity Board's share in the power generated by the EPL to its sister concern, EPL is liable to compensate the Electricity Board for the same by treating such power which sold by EPL to Essar Steel Ltd. as if it was sold by the Electricity Board itself to Essar Steel Ltd. after purchasing the same from the EPL.
The Tribunal held that the direction given by the State Commission with reference to reimbursement of Annual Fixed Charges to the Electricity Board when the Electricity Board has not secured energy to the extent allocated under the proportionate principle is not correct.
Finding of the Court:
Impugned judgment of the Tribunal is erroneous.
Result: Appeal allowed.
JUDGMENT :
ADARSH KUMAR GOEL, J.
Part I : Introductory
This appeal has been preferred under Section 125 of the Electricity Act, 2003 (`the Act') against the judgment and order dated 22nd February, 2010 passed by the Appellate Tribunal for Electricity (the Tribunal) in Appeal No.86 of 2009 whereby the Tribunal has set aside the order of the Gujarat Electricity Regulatory Commission (`the Commission') which was in favour of the appellant.
2. The substantial question of law sought to be raised by the appellant is :
"Whether the Tribunal has correctly interpreted the terms of Power Purchase Agreement dated 30th May, 1996 (PPA) and is justified in reversing the finding of the Commission based on interpretation of the said PPA and other documents on record.?"
Part II : Facts
3. The appellant, Gujarat Urja Vikas Nigam Ltd. (`the GUVNL'), is the successor of the Gujarat Electricity Board and is a deemed licencee under Section 2 (39) read with Sections 12 and 14 of the Act. The respondent, ESSAR Power Limited (`the EPL'), is a generation company within the meaning of Section 2 (28) of the Act. The appellant filed a petition before the Commission under Section 86 (i)(f) of the Act for adjudication of the dispute arising out of the Power Purchase Agreement (`the PPA'). The appellant inter alia sought compensation for wrongful allocation of electricity by the EPL to its sister concern, Essar Steel Ltd. (ESL) in preference to the appellant.
4. According to the appellant, the EPL was required to allocate 300 MW out of the total 515 MW of electricity and the remaining 215 MW was to be allocated to ESL. In case the quantum of generation was less than 515 MW, the allocation was to be in the proportion of 300 : 215. Contrary to this requirement, the EPL allocated more electricity to ESL. The EPL agreed, vide letter dated 17.02.2000, that the appellant will be entitled to electricity in the proportion of 300 : 215 but the same was not adhered to. This resulted in loss to the appellant and gain to the EPL which, according to the appellant, tentatively worked out to L 476.22 crores (towards principal amount). It was further pleaded by the appellant that under the agreement, the appellant was liable to pay the annual fixed charges, the variable charges, incentive etc. in relation to the allocated capacity of 300 MW out of total 515 MW. Similarly, the ESL to whom balance capacity of 215 MW was allocated was to bear proportionate annual fixed cost, thus, the EPL was required to make electricity available to the appellant in the proportion of 300 : 215 as per clause 3 of the Agreement. The EPL was required to declare the availability in the same proportion so that the dispatch instruction could be issued as per the Agreement. The appellant pleaded that it was entitled to compensation for wrong allocation of electricity based on the applicable HT rate from time to time. The appellant claimed damages equal to the difference of rate at which electricity was to be supplied to it and the rate at which the appellant was to supply the same to its consumers. For this purpose, the respondent was liable to give true details and complete account of the allocation made to the appellant and to ESL. The appellant had also raised a claim for recovery of Deemed Generation Incentive paid to the respondent to which the respondent was not entitled but the said claim is no longer subject matter of this appeal, the order of the Tribunal in that respect having become final.
5. It will be appropriate to refer to the prayer clause in the petition filed by the appellant :-
"(a) hold that the petitioner is entitled to adjust in the tariff payable by the petitioner to the respondent for purchase of electricity all amounts received by the respondent as a result of wrong allocation of electricity; and deemed generation incentive when Naphtha is proposed to be used as fuel;
(b)
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.