SUPREME COURT OF INDIA
Madan B. Lokur, R.K. Agrawal, JJ.
Afcons Infrastructure Ltd. – Appellant
Versus
Nagpur Metro Rail Corporation Ltd. & Anr. – Respondents
CIVIL APPEAL NO. 9078 OF 2016 WITH C.A. NO. 9079 OF 2016 WITH C.A. NOS. 9080-9081 OF 2016
Decided On : 15-09-2016
(b) Constitution of India – Article 226 – High Court disagreeing with NMRCL interfered with its decision – Mere disagreement with the decision making process or the decision of the administrative authority – No reason for a constitutional Court to interfere – Threshold of mala fides, intention to favour someone or arbitrariness, irrationality or perversity must be met before interference. (Para 13, 15, 16)
2016(8) SCALE 99; (1989) 3 SCC 293; (1994) 6 SCC 651; (2007) 14 SCC 517 – Relied upon
(c) Government contract – Tender – Words used in tender documents – Cannot be ignored or treated as redundant or superfluous – They must be given meaning and their necessary significance – Instantly tender document using term ‘metro’ – Its connotation in ordinary parlance cannot be overlooked. (Para 14)
(1979) 3 SCC 489 – Relied upon
(d) Constitution of India – Article 226 – Government contract – Petition filed by unsuccessful or ineligible bidder – Court should insist on all eligible bidders being made parties to the proceedings. (Para 18)
Facts of the case:
Bids were invited by NMRCL for the design and construction of a viaduct in Reach-3 between Jhansi Rani Square and Lokmanya Nagar Stations from CH 7825M to CH 18212M on the East-West Corridor of Nagpur Metro Rail Project.
GYT-TPL JV gave its bid for the contract but NMRCL communicated to GYT-TPL JV that its bid was disqualified at the technical bid opening. The comment/remark relating to the disqualification stated that the documents submitted by GYT-TPL JV do not meet the eligibility conditions as stipulated in Clause 4.2 (a) of Section III of the bid documents.
The sole question before the High Court was whether the Pearl River Delta Intercity High Speed Railway Project met the requirement of a ‘metro civil construction work’. According to NMRCL, an inter-city high speed railway project did not meet the requirements of a metro civil construction work.
The High Court disagreed with NMRCL.
Finding of the Court:
High Court ought not to have interfered.
Result: Appeals allowed.
JUDGMENT
Madan B. Lokur, J.
1. In Civil Appeal No. 9078 of 2016 and Civil Appeal No. 9079 of 2016 filed by Afcons Infrastructure Ltd., the challenge is to the judgment and orders dated 28th July, 2016 and 11th August, 2016 passed by the Bombay High Court. In Civil Appeal Nos. 9080-9081 of 2016filed by the Nagpur Metro Rail Corporation Ltd., the challenge is to the judgment and orders dated 28th July, 2016 and 12th August, 2016 passed by the Bombay High Court. The combined effect of all the impugned orders is that the High Court held that M/s. Guangdong Yuantian Engineering Company (GYT) of China and M/s. TATA Projects Limited (TPL) as a Joint Venture (hereinafter referred to as the ‘GYT-TPL JV’) are eligible to bid for a tender invited by the Nagpur Metro Rail Corporation Limited (for short ‘NMRCL’) on 12th May, 2016.
2. Bids were invited by NMRCL for the design and construction of a viaduct in Reach-3 between Jhansi Rani Square and Lokmanya Nagar Stations from CH 7825M to CH 18212M on the East-West Corridor of Nagpur Metro Rail Project.
3. GYT-TPL JV gave its bid for the contract but NMRCL, by an e-mail dated 23rd July, 2016 communicated to GYT-TPL JV that its bid was disqualified at the technical bid opening. The comment/remark relating to the disqualification stated that the documents submitted by GYT-TPL JV do not meet the eligibility conditions as stipulated in Clause 4.2 (a) of Section III of the bid documents.
4. The controversy on the eligibility of GYT-TPL JV arises in view of Clause 4.2
(a) of Section III of the tender conditions which reads inter alia as follows:
| 4.2(a) | Specific Construction & Contract Management experience | A minimum number of similar contracts specified below that have been satisfactorily completed as a prime contractor, joint venture member during last 10 (ten) years i.e. up till 31.05.2016 (a) Should have received minimum INR 3200 Million from 1 contract in a metro civil construction work and should have completed viaduct length not less than 5 km in the same contract. |
5. According to GYT-TPL JV, it had executed the Pearl River Delta intercity high speed railway project in China; it had received INR 3200 million from that project and it had constructed a viaduct of 7.284 km length under that contract. Before the High Court and before us, there was no controversy that GYT-TPL JV had received a minimum of INR 3200 million from its Pearl River Delta Intercity High Speed Railway Project and that whether it had completed a viaduct having a length of not less than 5 km. The sole question before the High Court was whether the Pearl River Delta Intercity High Speed Railway Project met the requirement of a ‘metro civil construction work’. According to NMRCL, an inter-city high speed railway project did not meet the requirements of a metro civil construction work.
6. The High Court disagreed with NMRCL in the following words:
“The civil construction work completed by the petitioner [GYT-TPL JV] in terms of condition no. 4.2 (a) was for an intercity high speed railway project in China and in the said contract, the petitioner had completed a viaduct of 7.284 km length….The petitioner has admittedly constructed a viaduct of not less than 5 km for the prestigious Pearl River Delta Intercity high speed railway project in China. We find on a reading of the tender conditions and particularly clause 4.2(a) thereof that a contractor or a joint venture company is required to have the experience in Metro Civil Construction work and of completing a viaduct having a length of not less than 5 kms. We do not appreciate the submission on behalf of the respondent that since the petitioner had constructed the viaduct for a high speed railway project, the petitioner would not have the experience of constructing a viaduct for a metro. It is not disputed by the respondent that ‘metro’ would mean a r
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.