SUPREME COURT OF INDIA
J. Chelameswar, Prafulla C. Pant, JJ.
Bindeshwari Chaudhary – Appellant
Versus
State of Bihar & Ors. – Respondents
CIVIL APPEAL NO. 3829 OF 2011
Decided On : 29-11-2016
(b) Bihar Pension Rules – Rule 43(b) r/w Rule 139 – Appellant’s action bona fide – No pecuniary loss to government – Rule 43(b) r/w Rule 139 not attracted – Impugned order not sustainable. (Para 12)
Facts of the case:
Appellant who was posted as Executive Engineer with Irrigation Department of State of Bihar, in the District of Singhbhum, awarded a contract on 29.08.1989 to one M/s. D.K. Road Lines, for bed and slope lining of canal in Galudih. In terms of the contract, the contractor was required to furnish bank guarantee, and the same was submitted by him for an amount of Rs.23,61,500/-. In order to verify the genuineness of the bank guarantee furnished by the contractor, the appellant sent his Accounts Clerk to Punjab & Sindh Bank, Jamshedpur, with letter dated 29.08.1989. In response to said letter, appellant received letter dated 01.09.1989 from Shri T.S. Gandhok, Branch Manager of the bank, confirming the bank guarantee. The appellant made payment of Rs.15,00,000/-on 02.09.1989 towards mobilization advance to the contractor. The appellant released payment of Rs.8,60,000/-on 31.10.1989 towards second mobilization advance upon permission from competent authority. On 12.02.1990, the appellant made further payment of Rs.2.55 lacs on approval of works by competent authority.
The new Manager informed the appellant that no such bank guarantee has been issued by the bank. On 04.05.1990, bank cancelled its earlier communication dated 01.09.1989. The appellant finally released Rs.4.4 lacs towards current bill of the contractor.
C.B.I. registered a case RC37(A)/91, Patna in pursuance to the fraudulent/forged bank guarantee furnished by the contractor.
On 04.04.1991, appellant was placed under suspension in contemplation of departmental proceedings which was quashed by the High Court.
C.B.I. submitted charge sheet against accused T.S. Gandhok, Manager of Punjab & Sindh Bank who confirmed the bank guarantee, and accused Ramdahin Singh, Senior Accounts Clerk of the Irrigation Department who received the bank guarantee from the contractor and verified.
The appellant was not an accused in the charge sheet, still on 18.06.1993, after the departmental enquiry was earlier dropped, the respondent authorities awarded punishment against the appellant withholding his three increments with cumulative effect, and also ‘censured’ for the year 1989-90. High Court held that withholding of three increments with cumulative effect is a major punishment, and could not have been awarded without resorting to regular departmental enquiry. However punishment of “Censure’ was not interfered with by the High Court.
On 20th May, 1995, the respondent authorities initiated fresh departmental enquiry against the appellant, and second charge sheet was served on him relating to the same allegations of release of unsecured advance of Rs. 14.5 lacs to the contractor against the order of Superintending Engineer. The appellant filed his objections and participated in the enquiry. The enquiry report dated 18.10.1996 recorded the finding that part of the charge stood proved. Thereafter the appellant stood retired on 31.01.1997. On 24.09.1997, appellant was awarded punishment of withholding of 100% pension and gratuity.
The High Court restricted withholding of gratuity and pension to the extent of fifty percent.
Finding of the Court:
Impugned order is not sustainable.
Result: Appeal allowed.
JUDGMENT
Prafulla C. Pant, J.
This appeal is directed against judgment and order dated 20.05.2008, passed by High Court of Judicature at Patna, whereby Letters Patent Appeal No. 436 of 2000 was disposed of allowing respondent authorities to withhold 50% of gratuity and 50% of pension, of the appellant.
2. Brief facts of the case are that appellant who was posted as Executive Engineer with Irrigation Department of State of Bihar, in the District of Singhbhum, awarded a contract on 29.08.1989 to one M/s. D.K. Road Lines, for bed and slope lining of canal in Galudih. In terms of the contract, the contractor was required to furnish bank guarantee, and the same was submitted by him for an amount of Rs.23,61,500/-. In order to verify the genuineness of the bank guarantee furnished by the contractor, the appellant sent his Accounts Clerk to Punjab & Sindh Bank, Jamshedpur, with letter dated 29.08.1989 (Annexure-P1). In response to said letter, appellant received letter dated 01.09.1989 (Annexure-P-3) from Shri T.S. Gandhok, Branch Manager of the bank, confirming the bank guarantee. The appellant made payment of Rs.15,00,000/-on 02.09.1989 towards mobilization advance to the contractor. On 04.09.1989, Superintending Engineer, issued letter (Annexure P-4), directing the appellant not to make mobilization advance. But, subsequently said authority allowed the appellant to make second mobilization advance to the contractor vide its letter dated 27.10.1989, consequently the appellant released payment of Rs.8,60,000/-on 31.10.1989 towards second mobilization advance. After three months, the Superintending Engineer, vide letter dated 23.12.1989 (Annexure-P-5) approved the work done by M/s D.K. Road Lines assessing the work done at Rs.42,79,021/-. On 12.02.1990, the appellant made further payment of Rs.2.55 lacs.
3. Meanwhile, when new Manager took over the charge of Jamshedpur Branch of Punjab & Sindh Bank, issued letter dated 13.02.1990 (Annexure-P-7), asking the appellant to send photocopy of the bank guarantee in question. And vide letter dated 20.03.1990 (Annexure-P-8) the new Manager informed the appellant that no such bank guarantee has been issued by the bank. Appellant has pleaded that he received said letter on 10.04.1990, and by then the appellant had released further payment of Rs.7.33 lacs towards bill of the contractor. On 04.05.1990, bank cancelled its earlier communication dated 01.09.1989. The appellant finally released Rs.4.4 lacs towards current bill of the contractor, whereafter he was transferred on 11.06.1990 to Daltanganj. It appears that C.B.I. registered a case RC37(A)/91, Patna in pursuance to the fraudulent/forged bank guarantee furnished by the contractor.
4. On 04.04.1991, appellant was placed under suspension in contemplation of departmental proceedings. The appellant challenged order of suspension in Writ Petition C.W.J.C. No. 2673 of 1991 before the High Court which was disposed of with the observation that if charge sheet is not served within three weeks on the appellant, the suspension order shall stand quashed. On 13.06.1991 the respondent authorities served charge sheet (dated 02.05.1991) on the appellant, relating to payment of unsecured advance of Rs.14.5 lacs to the contractor. The appellant then filed another Writ Petition C.W.J.C. No. 4439 of 1991 once again seeking quashing of the suspension order, and the High Court vide its order dated 10.10.1991, quashed the same. The respondent authorities vide order dated 05.12.1991 (Annexure–P12) revoked the suspension order, and departmental enquiry was dropped. Consequently on 14.01.1992, the appellant joined his new assignment as a Technical Advisor to Water Nigam Circle, Dumka.
5. After investigation, C.B.I. submitted charge sheet against accused T.S. Gandhok, Manager of Punjab & Sindh Bank who confirmed the bank guarantee, and accused Ramdahin Singh, Senior Accounts Clerk of the Irrigation Department who received the bank guarantee from the contractor and ve
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.