SUPREME COURT OF INDIA
ABHAY MANOHAR SAPRE, R. SUBHASH REDDY, JJ.
Hori Lal - Appellant
Versus
State of Uttar Pradesh & Ors. - Respondents
Civil Appeal No. 1462 of 2019 (Arising out of S.L.P.(C) No. 14820 of 2017)
Decided On : 05-02-2019
Facts of the case:
In pursuance of declaration made under Section 6 of Land acquisition Act, 1894 on 29.11.2003 the appellant's land was acquired.
The Land Acquisition Officer passed an award on 30.06.2016.
The appellant filed the writ petition challenging the validity and legality of the notification issued under Section 4 of the Act, 1894 dated 30.10.2002 as also the award dated 30.06.2016.
The High Court dismissed the writ petition.
Finding of the Court:
There is no infirmity in the impugned judgment.
Result: Appeal dismissed.
JUDGMENT :
Abhay Manohar Sapre, J.
1. Leave granted.
2. This appeal is directed against the final judgment and order dated 09.03.2017 of the High Court of Judicature at Allahabad in Writ Petition No.44731 of 2016 whereby the Division Bench of the High Court dismissed the writ petition filed by the appellant herein.
3. A few relevant facts need mention to appreciate the short controversy involved in this appeal.
4. The appellant herein was the writ petitioner whereas the respondents herein were the respondents in the writ petition filed before the High Court out of which this appeal arises.
5. In exercise of the powers conferred under Section 4 (1) of the Land Acquisition Act, 1894 (for short called “the Act 1894”), the State of UP (respondent No.1 herein) issued a notification on 30.10.2002 (Annexure P-1) for acquisition of lands as detailed in the schedule to the notification.
6. The acquisition was for the public purpose, namely, construction of Varanasi Bye-Pass (Ring Road) in District Varanasi. The State, however, invoked the urgency clause under Section 17 and, therefore, dispensed with the inquiry as provided in Section 5-A of the Act, 1894. This was followed by a declaration made under Section 6 on 29.11.2003. The appellant's land was acquired in these acquisition proceedings.
7. "The Act, 1894" was repealed on 01.01.2014 and was replaced by another Act called “the Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation And Resettlement Act, 2013” (for short called “the Act, 2013”). The Act 2013 came into force on 01.01.2014.
8. The Land Acquisition Officer, however, passed an award on 30.06.2016 (Annexure P-4), i.e., after the repeal of the Act, 1894 in relation to the aforementioned lands by determining the compensation payable to the landowner (appellant herein) accordingly.
9. The appellant (writ petitioner) thereupon felt aggrieved by the entire acquisition proceedings including passing of the award dated 30.06.2016 and filed the writ petition in the Allahabad High Court challenging therein the validity and legality of the notification issued under Section 4 of the Act, 1894 dated 30.10.2002 as also the award dated 30.06.2016.
10. The main challenge of the appellant to the acquisition proceedings was that the entire acquisition proceedings initiated by the respondent-State on the strength of notification issued on 30.10.2002 under Section 4 of the Act, 1894 which eventually led to passing of the award on 30.06.2016, stood lapsed consequent upon the repeal of the Act, 1894.
11. It is pertinent to mention here that during the hearing before the High Court, the writ petitioner (appellant herein) expressly gave up his challenge to the acquisition proceedings and confined his challenge only to the manner in which the determination of the compensation was done by the Land Acquisition Officer and, in consequence, to its quantum.
12. The State, in the counter affidavit filed before the High Court, placed reliance on the order of the Central Government issued under Section 113 of the Act, 2013 and contended that the compensation payable to the appellant would be determined on the basis of market value as it was prevalent on 01.01.2014.
13. By impugned order, the High Court dismissed the writ petition. The High Court held that in view of the stand taken by the State in this case, that the compensation payable to the appellant would be determined on the basis of market value of the land in question as it was prevalent on 01.01.2014, nothing survives for deciding any question. The appellant was, however, granted liberty to claim reference to the competent authority for determination of the compensation under the Act, 2013 in accordance with law.
14. It is against this order of the High Court, the writ petitioner has felt aggrieved and filed this appeal by way of special leave in this Court.
15. The short question, which arises for consideration in this appeal, is whether the High Court was justified in dismissing the ap
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.