SUPREME COURT OF INDIA
Arun Mishra, M.R. Shah, B.R. Gavai, JJ.
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. – APPELLANT
VERSUS
UNION OF INDIA AND OTHER – RESPONDENTS
CIVIL APPEAL NO. 4304 OF 2007
Decided On : 28-02-2020
(a) Electricity Supply Act, 1948 - Section 59 - State Government empowered to revise tariff before enactment of Electricity Regulatory Act, 1998 and constitution of Electric Regulatory Commission thereunder - However, - Captive Power Plant Policy remaining with State Government - MERC constituted on 5.8.1999 - MSEB’s proposal for tariff revision vide circular dated 23.7.1998 remaining pending with Government in the year 1999 - Government advising MSEB to submit tariff revision proposal to MERC - MSEB granting permission for installation of CPP by Circular No.619 dated 25.5.1999 - Two more circulars issued subsequently on 2.9.1999, 19.9.2000 - AppellantMSEDCL submitting its tariff revision proposal on 31.8.2001 along with the four circulars to MERC for approval - On 21.5.2004 MERC set aside the four circulars issued by appellantMSEDCL including even those when MERC was not in existence at the time the circulars were issued on the ground that no approval from MERC had been obtained - Quashing of circulars before constitution of MERC without jurisdiction. (Para 24)
(b) Electricity Regulatory Act, 1998 - Section 29 - Tariff revision - Captive Power Plant Policy - Tariff from 2.9.1999 to 28.4.2000 - MERC though accepting that CPP is in Government domain, not considering the same and quashing related circulars without going into merits - MERC further directing refund of tariff collected on basis of those circulars, with interest - Moreover the enhanced tariff had been passed on by respondents to their customers - Refund will result in unjust enrichment to respondents - Impugned judgment not sustainable. (Para 27, 28)
Facts of the case:
The appeal has been preferred by Maharashtra State Electricity Distribution Company Limited against the order dated 30.5.2007, passed by Appellate Tribunal for Electricity, dismissing the appeal against the order dated 21.5.2004 passed by Maharashtra State Electricity Regulatory Commission, quashing Circular No.602 dated 23.7.1998, Circular No.619 dated 25.5.1999, Circular No.627 dated 2.9.1999, Circular No.651 dated 19.9.2000 and Circular No.663 dated 5.10.2001, insofar as they purport to impose “take or pay” obligation and minimum offtake requirement as also of any additional tariff for captive power plant holders on the ground that there was no approval of the MERC constituted in terms of the provisions of the Electricity Regulatory Act, 1998. The appellantMSEDCL has been directed to make refund to respondent nos.3 to 7. The financial liability has been imposed upon the appellantMSEDCL. The MERC was constituted on 5.8.1999. The appellantMSEDCL had submitted all its circulars to MERC for approval and the MERC after four years has quashed the circulars with retrospective effect. The financial condition of the appellant MSEDCL is not sound enough to sustain such kind of liability for refund. It was unable to pay a sum of Rs.504 crores as against liability to other parties.
Finding of the Court:
Impugned judgment is not sustainable.
Result: Appeal allowed.
JUDGMENT
Arun Mishra, J.
1. The appeal has been preferred by Maharashtra State Electricity Distribution Company Limited (for short, ‘the MSEDCL’) against the order dated 30.5.2007, passed by Appellate Tribunal for Electricity (for short, ‘the APTEL’), dismissing the appeal against the order dated 21.5.2004 passed by Maharashtra State Electricity Regulatory Commission (for short, ‘the MERC’), quashing Circular No.602 dated 23.7.1998, Circular No.619 dated 25.5.1999, Circular No.627 dated 2.9.1999, Circular No.651 dated 19.9.2000 and Circular No.663 dated 5.10.2001, insofar as they purport to impose “take or pay” obligation and minimum offtake requirement as also of any additional tariff for captive power plant holders on the ground that there was no approval of the MERC constituted in terms of the provisions of the Electricity Regulatory Act, 1998 (for short, ‘the Act of 1998’). The aforesaid circulars dealt with Captive Power Plant Policy (for short, ‘the CPP Policy’). The appellantMSEDCL has been directed to make refund to respondent nos.3 to 7. The financial liability has been imposed upon the appellantMSEDCL. The MERC was constituted on 5.8.1999. The appellantMSEDCL had submitted all its circulars to MERC for approval and the MERC after four years has quashed the circulars with retrospective effect. The financial condition of the appellant MSEDCL is not sound enough to sustain such kind of liability for refund. It was unable to pay a sum of Rs.504 crores as against liability to other parties.
2. Respondent no.3M/s. NRC Ltd. initially had its two units on Plot No.E 23. Unit Nos.1 and 2 had a contract demand of 3500 KVA and 1800 KVA respectively. In 1995, an independent connection was sought by respondent no.3 for its Unit No.2. Representation was made that two units were separate units and on that basis, two independent connections were given. After that, respondent no.3 filed an application dated 5.4.1997 to set up a CPP of 7MW capacity. In respect of contract demand, it was proposed to retain total contract demand for 812 months after the CPP was fully operational and to surrender around 50% of the contract demand after that. Prayer was also made to provide standby power.
3. The Government of Maharashtra issued a notification dated 20.12.1997, whereby it empowered Maharashtra State Electricity Board (for short, ‘the MSEB’) to finalise the technical and commercial arrangements between captive power purchasers and their party purchasers. No objection certificate dated 7.1.1998 was issued by appellantMSEDCL subject to the Condition No.4, which permitted respondent no.3 to decide the level of contract demand after the commissioning of the set and any changes for interconnection would be governed as per the Board’s Condition of Supply framed from time to time and its policies as no rules were framed.
4. Circular No.602 dated 23.7.1998 was issued vesting power with the Board to permit the CPP holder for sale of their CPP power to any third party through the Board's grid, grant of permission to those persons to use their CPP power for self use only and to charge wheeling and transmission loss charges.
5. The Act of 1998 was enacted on 25.4.1998. Before that, field of electricity was regulated by Electricity Supply Act, 1948 (for short, 'the Act of 1948'). Section 49 of the Act of 1948 empowered the respective Electricity Boards to come up with their tariffs, which could have differential. Section 79(j) of the Act empowered the Board to make regulations pertaining to supply of electricity to the licensees under Section 49. Section 44 further provided that for establishing the CPP unit, prior consent of the Board was mandatory. MSEB was regulating the field of CPP as per notifications issued by the Government and the provisions contained in the Act of 1948.
6. On 23.9.1998, respondent no.3 sought clubbing of the contract demand and subsequent reduction to 3000 KVA for both the units. The clubbing of two units would increase the t
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.