1. Challenge to ad-interim directions of a High Court concerning the demolition and release of property in a writ petition. (Para 2 , 3 )
2019 Supreme(SC) 1637
SUPREME COURT OF INDIA
Dhananjaya Y. Chandrachud, Hemant Gupta, JJ.
Meerut Development Authority & Anr. - Appellants
Versus
Babita Devi & Anr. - Respondents
Civil Appeal No. 20 of 2019; Special Leave Petition (Civil) No. 32359 of 2018
Decided On : 03-01-2019
Important Points
Subject
Civil Law - Property Law
Headnote
Ad-Interim Direction - Meerut Development Authority - The court maintained the ad interim direction restraining the demolition of the property but stayed the release of the property pending the disposal of the writ petition, as it would virtually amount to final relief in the proceedings.
Fact of the Case:
The High Court issued ad-interim directions restraining the demolition of the property and directing the release of the property subject to an undertaking. The Meerut Development Authority challenged these directions.
Finding of the Court:
The court maintained the ad interim direction restraining the demolition of the property but stayed the release of the property pending the disposal of the writ petition. The court also directed the appellants to file a counter affidavit and the High Court to take up the writ petition for final hearing at an early date.
Issues: Ad-interim directions restraining demolition and directing release of property, staying of release pending disposal of writ petition, filing of counter affidavit, and early final hearing.
Ratio Decidendi: The court found merit in the submission that the release of the property would virtually amount to final relief in the proceedings, and therefore stayed this part of the direction pending the disposal of the writ petition.
Final Decision: The appeal was disposed of with the direction to maintain the ad interim direction restraining the demolition of the property and to stay the release of the property pending the disposal of the writ petition.
Legal Category Hierarchy
Sudhir Kulshreshtha, Adv., Sameer Kulshreshtha, Adv., Sanchit Garya, Adv., Pahlad Singh Sharma, Adv., Sanjay Sharma, Adv.
Table of Contents
2. The authority contested the High Court's direction to release the property to the petitioner subject to an undertaking. (Para 3 )
3. Granting the release of the property at an interim stage would effectively amount to granting the final relief in the proceedings. (Para 5 )
4. Interim relief should not be granted if it virtually amounts to the final relief sought in the proceedings. (Para 5 )
5. Stay on demolition maintained; direction for release of property stayed; High Court directed to dispose of the writ petition expeditiously. (Para 6 )
6. Under what circumstances may a court stay an interim direction for the release of property?
A court may stay an interim direction for the release of property if granting such relief would virtually amount to granting the final relief in the proceedings. (Para 5 )
ORDER
1. Leave granted.
2. By the impugned order of the High Court, the following ad-interim directions have been issued:
"In the meanwhile, the respondent-Meerut Development Authority shall not demolish the property in question. The Meerut Development Authority is further directed to release the property and hand over to the petitioner provided the petitioner undertakes that in the event of dismissal of this petition for writ, he will hand over complete vacant possession of the property to the Meerut Development Authority and further shall also pay mesne profit i.e. to be determined at the rate of Rs.10,000/- per month for the period he keep the property in his possession.
The petitioner shall also furnish an undertaking that till disposal of the writ petition he will not sale, transfer or otherwise alienate the property in question."
3. The Meerut Development Authority has assailed the above directions.
4. Learned counsel appearing on behalf of the original petitioners, who is on caveat, has entered appearance.
5. In our view, it will be appropriate, at this stage, to maintain the ad interim direction of the High Court restraining the demolition of the property. However, the second part of the direction for the release of the property subject to an undertaking should, in our view, be stayed pending the disposal of the writ petition. There is merit in the submission that the grant of this part of the relief would virtually amount to final relief in the proceedings.
6. We accordingly direct that:
(i) The appellants shall file their counter affidavit before the High Court within a period of two weeks from today;
(ii) The High Court is required to take up the writ petition for final hearing at an early date and endeavour a final disposal preferably within a period of one month thereafter;
(iii) Pending further orders, the interim direction for the release of the property to the original petitioners shall remain stayed.
7. We clarify that we have not expressed any opinion on the merits so as not to affect the respective rights and contentions of the parties at the final hearing. The High Court would, it is needless to add, dispose of the petition on its own merits after considering the rival submissions.
8. The appeal is accordingly disposed of.